NATIONAL UNIVERSITY OF CIVIL ENGINEERING
CONSTRUCTION ENGINEERING AND MANAGEMENT
----------------
MINI PROJECT
CONSTRUCTION ORGANIZATION
Content: Design of Construction schedule and Site logistics
SUPERVISOR NAME
: PHAM NGUYEN VAN PHUONG
STUDENT NAME
: HOANG XUAN THIEN LONG
STUDENT ID
: 1527963
CLASS
: 63XE4
DATE OF ASSIGNMENT
: 05/10/2022
HANOI , 2022
C0NSTRUCTION ORGANIZATION PROJECT
TABLE OF CONTENTS
LIST OF FIGURES
LIST OF TABLES
STUDENT: HOANG XUAN THIEN LONG
2
C0NSTRUCTION ORGANIZATION PROJECT
PROJECT DESCRIPTION
1. Introduction in the building
- Structure of the building is monolithic reinforced concrete structure. The building has
11 storeys and 20 spans. All the geometric data of the building is illustrated in the
below table.
- Construction and site conditions of the building:
• Geological properties: soil grade II with high strength of soil. There’s no need to
reinforce foundation pit.
• The level of water table is by far greater than the level of foundation pit.
2. Project data
Table 1. Project information
Number of stories
Number of bays
[�]���� (�� /�� 2)
�����(��� /�3)
Season
b(m)
Foundation
A
B
C
A(m)
t(cm)
B(m)
Body
1
2
L(m)
H1(m)
Ht(m)
Hm(m)
C1(d/h1)
Column
C2(d/h2)
F1,F2
F3, F4
F5, F6
F7, F8
F9, F10, F11
F1,F2
F3, F4
F5, F6
F7, F8
F9, F10 , F11
s(cm)
D1b
D1g
D1
Beam D (cm)
STUDENT: HOANG XUAN THIEN LONG
D2
D3
11
20
100
600
Winter
1,2
1,7
1,7
1,5
45
3,3
5,8
4,0
4,5
3,4
3,4
25/45
25/40
25/35
25/30
25/25
25/50
25/45
25/40
25/35
25/30
12
25x60
25x40
20x30
20x30
3
C0NSTRUCTION ORGANIZATION PROJECT
Roof
Dm
D roof(cm)
�%
Reinf.ratio
25x60
10
2,0%
Figure 1. Structural plan of building
STUDENT: HOANG XUAN THIEN LONG
4
C0NSTRUCTION ORGANIZATION PROJECT
A
B
C
D
E
Figure 2. Structural elevation B-B
STUDENT: HOANG XUAN THIEN LONG
5
C0NSTRUCTION ORGANIZATION PROJECT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Figure 3. Structural Elevation A-A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Figure 4. Isolated footing plan
3. Foundation structure
a. Depth of foundation:
Hm = 3t = 120 + m ×10 = 120 + 1×10 = 130(cm) à Choose t = 45 (cm)
b. Dimension of foundation are chosen following to the formula below:
STUDENT: HOANG XUAN THIEN LONG
6
16
17
C0NSTRUCTION ORGANIZATION PROJECT
- Outer footing (axis A & E):
1
1
a1 = × (0,5L1 ) + 10 × T = × (0,5 × 580) + 10 ×11 = 139(cm)
10
10
7
7
b1 = a1 = ×139 = 97.3(cm)
10
10
Choose: a1 = 140cm; b1 = 100cm
2
A
Figure 5. Foundation axis A
- Middle footing (axis B & D):
1
1
a2 = L2 + 10 × T = × 580 + 10 ×11 = 168(cm)
10
10
7
7
b2 = a2 = ×168 = 117(cm)
10
10
Choose: a2 = 170cm; b2 = 120cm
STUDENT: HOANG XUAN THIEN LONG
7
C0NSTRUCTION ORGANIZATION PROJECT
2
B
Figure 6. Foundation axis B
- Middle footing (axis C)
1
1
a3 = L2 + 10 × T = × 400 + 10 ×11 = 150(cm)
10
10
7
7
b3 = a3 = ×150 = 105(cm)
10
10
Choose: a3 = 150cm; b3 = 105cm
STUDENT: HOANG XUAN THIEN LONG
8
C0NSTRUCTION ORGANIZATION PROJECT
2
C
Figure 7. Foundation axis C
4. Ground
h0 = 2 × 45 = 90(cm)
Thickness of lining concrete:
t1 = 10 + m = 10 + 1 = 11(cm) à Choose: t = 15 (cm)
1
Thickness of reinforced concrete:
t2 = 10 + 2m = 10 + 2 ×1 = 12(cm) à Choose: t = 15 (cm)
2
Thickness of foundation sand:
STUDENT: HOANG XUAN THIEN LONG
9
C0NSTRUCTION ORGANIZATION PROJECT
t3 = h0 − t1 − t2 = 95 − 15 − 15 = 65(cm)
Figure 8. Ground
5. Roof
- Waterproofing:
4,5 +
n
6
= 4,5 +
= 4,8
20
20
à Choose: 5 cm
n
6
12 + = 12 + = 14
3
3
- Heat proofing:
à Choose: 15 cm
- 2 layers of traditional terra-cotta floortile (ceramic tile)
Figure 9. Roof
6. Wall
- According to axis: External wall 200 (mm), internal wall 110 (mm).
- Plaster 40% of external wall area ; 50% of internal wall area.
- Paint 40% of external wall area ; 50% of internal wall area.
STUDENT: HOANG XUAN THIEN LONG
10
C0NSTRUCTION ORGANIZATION PROJECT
- Doors ( and windows) take 60% of external wall area ; 10% of internal wall
area.
7. Power, water factor :
- 0,32 working hour per 1m2 of floor.
8. Construction plan and location of building
a) Construction plan
Figure 10. Construction plan
Figure 11. Building location on construction plan
X1 = 10 + 5n = 10 + 5 × 6 = 40(m)
n
6
X 2 = 15 + = 15 + = 18(m)
2
2
Y1 = 10m + n = 10 ×1 + 6 = 16(m)
Y2 = (m + n) ×10 = (1 + 6) ×10 = 70(m)
STUDENT: HOANG XUAN THIEN LONG
11
C0NSTRUCTION ORGANIZATION PROJECT
CHAPTER 1. CONSTRUCTION SCHEDULE
A. FOUNDATION CONSTRUCTION
1. List of tasks
Main ask:
1. Machanical excavation.
2. Manual excavation (fixing).
3. Pouring lean concrete of foundations and ground beams.
4. Installing foundation, ground beam and column reinforcement.
5. Installing foundation and ground beam formwork.
6. Pouring foundation and ground beam concrete.
7. Dismantling foundation and ground beam formwork.
8. Installing column formwork.
9. Pouring column concrete.
10. Dismantling column formwork.
11. Brickwork (foundation wall)
12. Installing plinth beam formwork
13. Installing plinth beam reinforcement
14. Pouring plinth beam concrete
15. Dismantle plinth beam formwork
16. Back-filling phase
17. Foundation sand
18. Pouring lean concrete for 1st floor ground base
19. Installing reinforcement for 1st floor ground base
20. Pouring concrete for 1st floor ground base
2. Construction method and the calculation of work volumn
2.1.
Excavation
2.1.1. Selection of soil excavation method
Select the dimensions of ground beam : 45 x 20(cm)
Total depth of the excavation: Hd = 3 × 45 + 10 =145 (cm) = 1,45 (m)
Slope factor: m = 1:0,25 (soil grade II)
Distance B d = 0,25 × H d = 0, 25 ×1, 45 = 0,3625(m) à Choose Bd = 0,4 (m)
STUDENT: HOANG XUAN THIEN LONG
12
C0NSTRUCTION ORGANIZATION PROJECT
Excavation dimensions:
- Bottom pit:
• Axis A&E:
• Axis B&D:
• Axis C:
- Top pit:
• Axis A&E:
• Axis B&D:
• Axis C:
ad1 = a1 + 2 × 0,5 = 1, 4 + 2 × 0,5 = 2,4(m)
bd1 = b1 + 2 × 0,5 = 1,0 + 2 × 0,5 = 2(m)
ad2 = a2 + 2 × 0,5 = 1,7 + 2 × 0,5 = 2,7(m)
bd2 = b2 + 2 × 0,5 = 1,2 + 2 × 0,5 = 2,2(m)
ad3 = a3 + 2 × 0,5 = 1,5 + 2 × 0,5 = 2,5(m)
bd3 = b3 + 2 × 0,5 = 1,05 + 2 × 0,5 = 2,05(m)
a1 ' = ad1 + 2 Bd = 2, 4 + 2 × 0.4 = 3,2(m)
b1 ' = bd1 + 2 Bd = 2 + 2 × 0.4 = 2,8(m)
a2 ' = ad2 + 2 Bd = 2,7 + 2 × 0.4 = 3,5(m)
b2 ' = bd2 + 2 Bd = 2,2 + 2 × 0.4 = 3(m)
a3 ' = ad3 + 2 Bd = 2,5 + 2 × 0.4 = 3,3(m)
b3 ' = bd3 + 2 Bd = 2,05 + 2 × 0.4 = 2,85(m)
The figure below shows the dimensions of a typical foundation.
A
2
2
Figure 12. Excavation pit for isolated footing axis A-2
STUDENT: HOANG XUAN THIEN LONG
13
C0NSTRUCTION ORGANIZATION PROJECT
B
2
2
Figure 13. Excavation pit for isolated footing axis B-2
2
C
2
Figure 14. Excavation pit for isolated footing axis C-2
STUDENT: HOANG XUAN THIEN LONG
14
C0NSTRUCTION ORGANIZATION PROJECT
When not considering the excavation for the construction of ground beams, we
have a excavation plan of isolated footings as flollow:
B
A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
B
Figure 15. Excavation plan
1
2
3
4
5
Figure 16. Section A-A
STUDENT: HOANG XUAN THIEN LONG
15
18
19
C0NSTRUCTION ORGANIZATION PROJECT
A
B
C
D
E
Figure 17. Section B-B
According to figure 15, 16 and 17, although soil left after digging foundation pits
following to axis A and B, D and E are large with 2.45m length, that after digging
foundation pits axis B, C and D are small with 0.6m lenth. In addition, soil left
after digging foundation pit following to axis 1,2,3,…,21 are also small with 0.3m
length. Moreover, ground beams are located on the surface of 1 st step of isolated
footing.
⇒ Excavation method: Mechanical combined with manual method. The
method is divided into 2 phases:
• 1st phase: Excavating pond dig from ground level (-0,9 m) to bottom of lean
concrete of ground beam level (-1,9 m)
• 2nd phase: Excavating holes for 2nd level of footing from bottom of concrete
of ground beam level (-1,9 m) to bottom of lean concrete of isolated footing
level (-2.35 m)
• The foundation pits are flattened by labour and roller.
� I have excavation plan as blow:
STUDENT: HOANG XUAN THIEN LONG
16
C0NSTRUCTION ORGANIZATION PROJECT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Figure 18. 1st phase excavation plan
STUDENT: HOANG XUAN THIEN LONG
17
15
16
C0NSTRUCTION ORGANIZATION PROJECT
B
A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
B
Figure 19. 2nd phase excavation plan
STUDENT: HOANG XUAN THIEN LONG
18
16
17
18
C0NSTRUCTION ORGANIZATION PROJECT
1
2
3
4
5
Figure 20. Section A-A
A
B
C
D
E
Figure 21. Section B-B
2.1.2. Calculation of soil volume
Recalculate the pit excavation dimension:
a) 1st phase: Excavating pond dig from ground level (-0,9 m) to bottom of lean
concrete of ground beam level (-1,9 m)
- Pit bottom:
1, 2
A = 20B + 2 × 0,5 + + tan(90° −15°) × 0,9
2
1, 2
= 20 × 3,3 + 2 × 0,5 + + tan(90°−15°) × 0,9 = 68,26m
2
B = 2(L1 + L2) + 2 × 0,5 + 2 × 0,7 + tan(90 −15) × 0,9
= 22,26m
- Pit top:
C = 2 × 0,55 × tan(90 − 75) + A = 68,8m
D = 2 × 0,55× tan(90 − 75) + B = 22,8m
Excavation volume:
V1 =
H
6
[A × B + (C + A) × ( B + D) + D × C ]
1
= [68,26 × 22,26 + (68,26 + 68,8) × (22,8 + 22,26) + 22,8 × 68,8]
6
=1555(m3 )
b) 2nd phase: Excavating holes for 2nd level of footing from bottom of concrete
of ground beam level (-1,45 m) to bottom of lean concrete of isolated
footing level (-2.35 m)
STUDENT: HOANG XUAN THIEN LONG
19
C0NSTRUCTION ORGANIZATION PROJECT
Excavating holes for axis A, E: There are 42 pit holes.
A = 2,65(m)
B = 2,25(m)
Excavation volume:
V2 = 42 × A × B × H
=42 × 2,65 × 2, 25 × 0, 45
= 112,7m3
Excavating holes for axis B, D: there are 42 pit holes
A = 2,945(m)
B = 2, 25(m)
Excavation volume:
V3 = 42 × A × B × H
=42 × 2,945 × 2, 25 × 0, 45
= 125,2m3
Excavating holes for axis C: there are 21 pit holes
- Pit bottom:
A = 2,75(m)
B = 2,05(m)
Excavation volume:
V3 = 42 × A × B × H
=42 × 2,75 × 2, 25 × 0, 45
= 116,9m3
Total excavation volume:
V = V1 + V2 + V3 + V4 = 1555 +112,7 + 125,2 +116,9 = 1909,8(m3 )
- Excavation volume by machine:
Vm = 0,9 ×V = 0,9 ×1909,8 ×1,2 = 2062,6(m3 )
- Excavation volume by manual method:
Vmm = 0,1×V = 0,1×1909,8 ×1,2 = 229.176(m3 )
2.1.3. The selection of excavator
a) Excavator selection
Base on volume of soil excavated, we select Backhoe excavator EO-3322B1
with the following parameters:
STUDENT: HOANG XUAN THIEN LONG
20
C0NSTRUCTION ORGANIZATION PROJECT
-
Bucket volume: q= 0,5(� 3)
Maximum radius: R=7,5 (m)
Maximum dumping height: h= 4,8 (m)
Maximum digging depth: H=4,2 (m)
Slewing cycle: t= 17 (s)
Productivity:
N = q × K d × nck × Ktg
In which:
q = 0,5 m3: Bucket volume
Kd = 1: Factor of full-filling bucket
Ktg = 0,75: Time factor
nck =
3600
3600
3600
=
=
= 192,51
Tck
tck × K vt × K quay 17 ×1,1×1
N = q × K d × nck × Ktg = 0,5 ×1×192,51× 0,75 = 65,16(m3 / h)
3
Productivity of backhoe per shift: N = 65,16 × 8 = 521,3(m / shift )
Number of shifts for the excavation:
STUDENT: HOANG XUAN THIEN LONG
n=
Vm 2062,6
=
= 3,95
N 521,3
(shifts)
21
C0NSTRUCTION ORGANIZATION PROJECT
Select one machine with 4 shifts for excavation process
Using a excavator, the working time 1 shift/day and work for 4 days
Method of digging soil:
The machine stands on high to put the bucket under the foundation pit to dig the
ground. When the bucket is full of soil, turn the bucket from the digging position
to the pouring position, and the car is standing next to it.
b) Dump truck selection
Assume that distance from site to the material gathering yard about 30km. Velocity
of the truck is about 70km/h.
Time for truck to do a cycle:
t1 =
2 × 30
= 0,86(h)
70
t2 = 0,5(h)
Bufer time:
Number of cycle a truck can do in a shift:
n1 =
8
= 5,88(cycles) = 6(cycles)
0,86 + 0,5
The truck can do 6 cycles in a shift
Select dump truck VEAM VM-551605 with following parameters:
3
ã Bucket volume: P = 4, 44 ì 2, 28 ì1,54 = 15,6(m )
ã Body weight: P = 20 (T)
3
Volume of soil that one truck can do in a shift: V = 6 ×15,6 = 93,6(m )
Number of trucks needed in a shift:
n=
521,3
= 5,57(trucks)
93,6
6 trucks needed for the transportation in 1 shift
Select 6 trucks with 4 shifts for excavation process
2.2.
Lean concrete construction
Lean concrete is mixed at construction site and then transported to the foundation
pit by manner. The lean concrete volume is estimated by the following table:
STUDENT: HOANG XUAN THIEN LONG
22
C0NSTRUCTION ORGANIZATION PROJECT
Table 2. Lean concrete volume
LEAN CONCRETE
Quantit
y
Volume (m3)
(5)
(6)
(7)=(3)x(4)x(5)x(6
)
1,2
0,1
42
8,064
1,9
1.4
0,1
42
11,172
Foundation
1,7
1,15
0,1
21
4,105
AB. DE
Ground
beam
4,85
0,4
0,1
42
8,148
BC, CD
Ground
beam
3,35
0,4
0,1
42
5,628
A,E1,2,…,21
Ground
beam
2,675
0,4
0,1
40
4,28
B,D1,2,
…,21
Ground
beam
2,5
0,4
0,1
40
4
C1,2,…,21
Ground
beam
2,675
0,4
0,1
20
2,14
Ground
floor
66
19,6
0,1
5
1
194,04
Axis
Componen
t
Dimension (m)
(1)
(2)
(3)
(4)
A, E
Foundation
1,6
B, D
Foundation
C
Total concrete volume (m3)
2.3.
241,57
Isolated footing and gorund beam construction
2.3.1. Calculation of concrete, reinforcement, formwork volume for
isolated footings and ground beams
Table 3. Foundation concrete volume
Axis
Element
Dimension (m)
Quantit
y
Volume
42
26,46
(m3)
Length Width Height
A, E
Spread
footing
2nd
step
STUDENT: HOANG XUAN THIEN LONG
1,4
1
0,45
23
C0NSTRUCTION ORGANIZATION PROJECT
B, D
C
1st step
0,9
0,625
0,45
2nd
step
1,7
1,2
0,45
1st step
1,025
0,8
0,45
2nd
step
1,5
1,05
0,45
1st step
0,9
0,625
0,45
Spread
footing
Spread
footing
10,62
42
38,55
15,5
21
14,88
5,31
A, E
Column
0,45
0,25
0,45
42
1,65
B, C, D
Column
0,5
0,25
0,45
63
2,84
AB, DE
Ground beam
5,425
0,2
0,45
42
20,5
BC, CD
Ground beam
3,6
0,2
0,45
42
13,61
A,E1,2,…,21
Ground beam
3,05
0,2
0,45
40
10,98
B,D1,2,
…,21
Ground beam
3,05
0,2
0,45
40
10,98
C1,2,…,21
Ground beam
3,05
0,2
0,45
20
5,49
Total concrete volume (m3)
177,37
Table 4. Foundation reiforcement
FOUDATION REINFORCEMENT
Axis
Component
Volumn (m3) Ref. Unit
Weight
(kg/m3)
Ref.
Ratio
(%)
Mass per
unit
A, E
2nd step
26,46
7850
2
4154,22
1st step
10,62
7850
2
1667,34
2nd step
38,55
7850
2
6052,35
1st step
15,5
7850
2
2433,5
2nd step
14,88
7850
2
2336,16
1st step
5,31
7850
2
833,67
Column
1,65
7850
2
259,05
B, D
C
A, E
STUDENT: HOANG XUAN THIEN LONG
24
C0NSTRUCTION ORGANIZATION PROJECT
B, C, D
Column
2,84
7850
2
445,88
AB, DE
Ground beam
20,5
7850
2
3218,5
BC, CD
Ground beam
13,61
7850
2
2136,77
A,E1,2,…,21 Ground beam
10,98
7850
2
1723,86
B,D1,2,
…,21
Ground beam
10,98
7850
2
1723,86
C1,2,…,21
Ground beam
5,49
7850
2
861,93
Total reinforcement mass (kg)
27847,09
Table 5. Foundation formwork area
Axis
A, E
B, D
C
A, E
Element
Spread
footin
g
Spread
footin
g
Spread
footin
g
Lengt
h
Widt
h
Heigh
t
Area
per
unit
(m2)
2nd
ste
p
1,4
1
0,45
2,12
1st
ste
p
0,9
0,625
0,45
1,22
2nd
ste
p
1,7
1,2
0,45
2,66
1st
ste
p
1,025
0,8
0,45
1,44
5
2nd
ste
p
1,5
1,05
0,45
2,3
1st
ste
p
0,9
0,625
0,45
1,22
0,45
0,25
0,45
0,23
Column
Dimension (m)
STUDENT: HOANG XUAN THIEN LONG
Quantit
y
Area
(m2)
42
89,04
51,24
42
111,72
60,69
21
48,3
25,26
42
9,66
25