8/13/2018
LEAN FLOW
GVC. ThS. Nguyễn Như Phong
; www.isem.edu.vn
Kỹ thuật Hệ thống Công nghiệp
ĐH BÁCH KHOA – ĐHQG TPHCM
(Tài liệu giảng dạy cho ISE)
2018
LEAN FLOW
Takt Time
Activity Time
5S
Visual Management
Changeover Reduction
TPM
Standard Work
Small machines
Demand Smoothing
11 April 2003
Nguyễn Như Phong
1
8/13/2018
LEAN FLOW
Preparing 4 Lean Flow
The foundation 4 fast, flexible flow
Takt Time
Activity Time
5S
Visual Management
Changeover Reduction
TPM
Standard Work
Small machines
Demand Smoothing
11 April 2003
Nguyễn Như Phong
LEAN FLOW
Takt Time & Activity Time –
5S
basic building block 4 lean flow
The housekeeping
Closely related 2 the TPM methodology
Visual Management
Enabled by 5S
Make TPM & Standard Work more effective
11 April 2003
Nguyễn Như Phong
2
8/13/2018
LEAN FLOW
5S, Standard Work & TPM
Demand Smoothing & Small machines
the basic 4 fast, consistent Changeover Reduction
Allow the other 2 be more effective
Combination – an effective attack on 3M
Muda (waste)
Muri (difficult work)
Mura (unevenness)
11 April 2003
Nguyễn Như Phong
TAKT TIME
Fundamental concept
Regular, uniform rate of progression of products
through all stages from RM 2 cust.
The drumbeat cycle of the rate of prod. flow
Fundamental 2 flow & mapping of L operation
11 April 2003
Nguyễn Như Phong
3
8/13/2018
Takt Time
Available work time (/d) / average demand (/d)
Available time:
Actual time – planned stoppages
Maintenance,
team briefings,
breaks
Demand: average sales rate
Spare parts, extra, anticipated scrap
11 April 2003
Nguyễn Như Phong
Takt Time
Demand changes,
Maintain the same TT
by adjusting the available work time
Multiple parts
Demand – the total no. parts
11 April 2003
Nguyễn Như Phong
4
8/13/2018
Takt Time
Seasonal / variable demand
Important selection of the period of estimated demand
Longer period
Build 2 order
11 April 2003
Nguyễn Như Phong
Takt Time
Longer period
Stabilize build rate
More supermarket 2 smooth out the bumps
Build 2 order
Reducing the time horizontal
More frequent TT
Lines rebalanced, operators involved
More lean & flexible
11 April 2003
Nguyễn Như Phong
5
8/13/2018
Takt Time
Not cycle time
CT > TT constraint
Parallel proc / additional shift
Several TTs
Parallel proc
Eg. No. parts per prod
Several TTs in a plant
Overall synchronization
11 April 2003
Nguyễn Như Phong
PITCH TIME
Pitch
TT * C
Container quantity / convenient multiple of parts
15 – 30 m
The time
required 2 fill the standard container
11 April 2003
Nguyễn Như Phong
6
8/13/2018
Pitch Time
The pitch increment
Basic time slot used in Heijunka sys.
Material hander fit in the pitch time
Vital sys. drumbeat
forcing regularity, visibility & flow
11 April 2003
Nguyễn Như Phong
ACTIVITY TIMING & WORK ELEMENTS
The IE / time & motion study task
determining the duration of work elements
Essential input
Cell balance boards
VS maps
Scheduling
Costing
Best done by operators rather than IEs
Sort out & standardize the motions before timing them
11 April 2003
Nguyễn Như Phong
7
8/13/2018
Activity Timing & Work Elements
Video making better than live recording
Back tracking & avoid the stress
At least 10 cycles / s
Variation bw. operators
Standard work
Nguyễn Như Phong
11 April 2003
Activity Timing & Work Elements
Method
Break down work sequence into work elements
Record manual, walk, wait machine times in
separate columns
Make a list of activities
Some manual times – NVA / NVAU
Cell balancing
11 April 2003
Reduce / eliminate wait & walk times
Reduce NVA / NVAU steps
Nguyễn Như Phong
8
8/13/2018
Activity Timing & Work Elements
At least 10 good cycles
Nothing goes wrong
Discard outliers
Nearest whole sec
Lowest more frequently occurring time
Not add allowance 4 PR&D –
personal, rest, delay.
More frequent breaks
11 April 2003
Nguyễn Như Phong
5S
The basic housekeeping for lean, quality &
safety
Apply in office & SF equally
Working better & feeling better in tidy room.
Mindset
Not be done by outsider
11 April 2003
Nguyễn Như Phong
9
8/13/2018
5S
Sort
Simplify / Set in order / Straighten
Sweep / Shine / Scrup
Standardize / Stabilize
Sustain / Self discipline
11 April 2003
Nguyễn Như Phong
5S
Sort
Throw out what not used
Classify everything by frequency
Do w. the team
Touch item systematically
Done regularly
11 April 2003
Nguyễn Như Phong
10
8/13/2018
5S
Simplify / Set in order / Straighten
Locate what used in the best place
A place 4 everything
Everything in its place
Spaghetti diagram
Ergonomic principles & audit
11 April 2003
Nguyễn Như Phong
5S
Sweep / Shine / Scrub
Keep up the good work
Physical tidy up on an ongoing basis
Visual sweeping
Who response 4 what
What standard
Cleaning is checking
11 April 2003
Nguyeãn Nhö Phong
11
8/13/2018
5S
Standardize / Stabilize
Standard work
Bottom line 4 5S
5S standards maintained
Standard 4 3S
11 April 2003
Nguyễn Như Phong
5S
Sustain / Self discipline
5S ongoing basis
Participation & improvement
Audits regularly
Award 4 achievement
11 April 2003
Nguyễn Như Phong
12
8/13/2018
5S
6S = 5S + Safety
An aspect of each 5S
Safety procedure & standard developed,
maintained & audited
Unsafe conditions integral to 5S
11 April 2003
Nguyễn Như Phong
5S
CANDO
Cleanup
Arrange
Neatness
Discipline
Ongoing improvement
11 April 2003
Nguyễn Như Phong
13
8/13/2018
5S
In fact doing 2S sporadically
Waste
Increasing effort 2 re-energize
Real productivity & quality benefit on S4, 5
5S audit & scoring sys
Nguyễn Như Phong
11 April 2003
STANDARD WORK
Deming
Improvement – moving from standard 2 standard
Juran
Holding the gains
by establishing standards following improvement
Standard Work a pillar of the TPS
11 April 2003
Nguyễn Như Phong
14
8/13/2018
Standard Work
Ohno
Achievement of standardized work
w. min variance
essential ingredient
to allow OPF & JIT production
Nguyễn Như Phong
11 April 2003
Standard Work
Henry Ford
Standardize a method –
choose out of many methods the best one & use it
Today standardization –
11 April 2003
the foundation 4 tomorrow improvement
Nguyeãn Nhö Phong
15
8/13/2018
Standard Work
Peter Wickens
Standard operations – the property of
Western – management / eng. Department
Japan – people doing the job
Prepare, do, improve
Contrary to Taylor
Combine thinking & doing
High level of involvement & commitment
Nguyeãn Nhö Phong
11 April 2003
Standard Work
Standard & Davies –
3 key aspects of SW
Not static,
Support stability & reduce variation
easily recognized
Essential for continuous improvement –
11 April 2003
updated procedure when better way found
better standard
Nguyễn Như Phong
16
8/13/2018
Standard Work
Cover 3 aspects
Work time –
Both TT & CT recorded
Work sequence
Standard WIP
Nguyễn Như Phong
11 April 2003
Standard Work
Moden 5 steps SOP development
1.
2.
Determine the TT
Determine the production capacity
3.
Determine the NOO
4.
Sum of work element / TT
Define the standard procedure
5.
Net work time / ( proc time + CO)
First remove waste, develop layout, standard location
Write the SOP chart
11 April 2003
Nguyễn Như Phong
17
8/13/2018
Standard Work
SOP
contains
TT
Detailed work sequence steps
w. time taken for each step
Standard inventory quantity / kanban quantity
Color coded to match the product
Keeping up to date & in the work place
Nguyễn Như Phong
11 April 2003
Standard Work
3 forms
The SW combination chart
The SW analysis chart
Gantt chart – sequence of step against time bar
Cell view showing standard route
The SW element sheet
11 April 2003
Steps, time & photograph
Nguyeãn Nhö Phong
18
8/13/2018
Standard Work
Yamazumi board
Cellular manu established / TT change
Operators rebalance the line
change work standards to the new TT
Nguyễn Như Phong
11 April 2003
Standard Work
Robert Hall 3-stages standardization
Outcome only
Standardized processes
Standard established in a plan / drawing
High level of variation
Variance reduced by standardized methods
Supported by eg. SPC, pokayoke
Standardized predictive methods
11 April 2003
High level of consistency achieved
Using standardized processes
Nguyễn Như Phong
19
8/13/2018
TOTAL PRODUCTIVE MAINTENANCE TPM
Integral to lean
No lean implementation success
w. high breakdown level
11 April 2003
Nguyễn Như Phong
Total Productive Maintenance - TPM
TPM
Beyond breakdown issues
Cover
availability,
performance,
quality,
safety,
capital investment
Making best use & extending the life of equipment
11 April 2003
Nguyễn Như Phong
20
8/13/2018
Total Productive Maintenance - TPM
Equipment life cycle
Failure rate – time
Bathtub curve
11 April 2003
High in the burning period
Low in plateau period
High in wear-out period
Nguyễn Như Phong
TPM
Addresses & reduces break down
in all parts of the curve
Burning period
Plateau period
Wear-out period
11 April 2003
Nguyễn Như Phong
21
8/13/2018
TPM
Burning period
early equipment maintenance
improved equipment usage understanding
Plateau period
Extend the life of equipment
Autonomous maintenance AM
The Japanese Institute of Plant Maintenance - JIPM
Wear-out period
Predictive & planned maintenance
11 April 2003
Nguyễn Như Phong
The 6 big losses
Widely used concept in TPM
Divided into 3 categories
Availability
Performance
Quality
11 April 2003
Nguyễn Như Phong
22
8/13/2018
The 6 big losses
Availability
Break down losses
Unplanned stoppages requiring repair
> 10m
CO & adjustment losses
11 April 2003
Nguyễn Như Phong
The 6 big losses
Performance
Minor stop & idling
<10m
Difficult 2 measure often ignored
So frequent the most significant loss
Activity sampling
Reduced speed losses
m/c running at less than the design speed
11 April 2003
Nguyễn Như Phong
23
8/13/2018
The 6 big losses
Quality
Defects –
Scrap / rework
Start up losses –
Scrap / rework during CO
Nguyễn Như Phong
11 April 2003
Overall Equipment Effectives OEE
OEE = Availability * Performance * Quality %
Availability = Actual working time / Working time
Actual working time = WT – BT - COT
11 April 2003
Working time –
Breakdown time –
CO time
Nguyễn Như Phong
24
8/13/2018
Overall Equipment Effectives OEE
OEE = Availability * Performance * Quality %
Performance = Producing time / Actual working time
Quality = No. good part produced / No. part produced
11 April 2003
Nguyễn Như Phong
Overall Equipment Effectives OEE
Each OEE elements
graphed
Keep at Gemba
Fishbone diagram showing possible causes
11 April 2003
Nguyễn Như Phong
25