Comment Response Sheet (CRS)
Project Title

Van Phong 1 BOT Thermal Power Plant Project

Document Title

METHOD STATEMENTS FOR DREDGING WORKS

Document Type

For Approval

Document No

VP1-0-L4-C-GEN-10019

Returned Status

AC

Prepared by

CRS No

VP1-0-L4-C-GEN-10019-D-CRS

CRS Issued Date

08-Jun-2020


Engineer

Construction

Review
Date

Status O/C *

Remarks

27-03-2020

Open

08-05-2020

Closed

21-05-2020

Closed

No.

Section/
Page

1


Page 1

Owner’s Comment
General comment:
(i) Please clarify elevation system is NDL or CDL where
mention elevation number
(ii) All dredging equipment have to install Automatic
Identification System (AIS) and video camera according
to Decree 159/2018 ND-CP.

08-05-2020
Noted
Lot-4 please submit documents related to AIS
before start working.

Response to Comment

L4

(i) Elevation system is NDL
(ii) DHI will be applied for hopper barge and THSD
only, all Clamshell and Flat Barge did not applied.

19-05-2020
Noted

21-05-2020
Closed

Page 1 of 14



Comment Response Sheet (CRS)
2

Page 2
(1) Please make clear whether all dredged materials
are suitable for use in reclamation and how about the
unsuitable materials?
(2) The temporary tide gauges shall be installed to give
immediate visual measurements of sea level. Please
describe more detail.
(3) How can Contractor to ensure there are no localized
high spots of the dredged areas before acceptance of
the final levels by the Owner. Please describe more.

(1) Based on EIA report which has been approved by
government, all dredged material can be reuse for
landfill.

08-05-2020
(1)&(2): Agreed
(3) Multi-beam echo sounder is not clear. Please
reflect in the ITP also.

19-05-2020
(3) ITP has been issued according to multi-beam eco
sounder method, multi-beam eco sounder is common
method to ensure that these are no localized high
spots of the dredged areas


27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

27-03-2020

Open

08-05-2020


Closed

(2) DHI has revised on MS (section 2.1.2)
(3) For Post survey and Final survey, the Contractor
shall do the survey with 10m interval lines and multibeam echo sounder to obstruction detecting

21-05-2020
Noted
3

Page 3
Please point out where are construction buoys and
specification of them?

DHI has revised on MS (section 2.1.1)

08-05-2020
Open: please describe construction buoys which
will issued maritime notice by Port Authority as
well.

19-05-2020
Navigation buoys is requested to marine notice
by Port Authority that described on the Marine
Safety Assurance Plan

21-05-2020
Closed
4


Page 3
Please clarify design and slope protection of this area.

08-05-2020
Closed

Slope is mention on drawing deign which will be
submitted separately document

Page 2 of 14


Comment Response Sheet (CRS)
5

Page 4

Please consider Vietnam has a series of international
conventions governing maritime safety agreement, it
should be referred on this MS

08-05-2020
There is not any convention added such as
MarPOL 73/78 for oil prevention, SOLAS-74 for
safety of life at sea, STCW convention for training
certification and watching for seafarers, etc.

6


Page 4

DHI has revised on MS (section 1.3.3)

19-05-2020
DHI has revised on MS (section 1.3.3

27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open


08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020


Open

08-05-2020

Closed

21-05-2020
Closed
"Described"
DHI has revised on MS (section 1.4)

08-05-2020
Closed
7

Page 4
EL (NDL)?

Elevation system is NDL

08-05-2020
8

Page 4

Closed
4,0mCD according to design drawing.

DHI has revised on MS (section 1.4)


08-05-2020
Closed
9

Page 4

How many m3 per hour?

DHI has revised on MS (section 1.5)

08-05-2020
Closed
10

Page 5

How many m3 per hour?

DHI has revised on MS (section 1.5)

08-05-2020
Closed
11

Page 5

How many m3 per hour?

08-05-2020


DHI has revised on MS (section 1.5)

Closed

Page 3 of 14


Comment Response Sheet (CRS)
12

Page 5

(i) Please add the recuse boat, passenger boat and tug
boat (if any) to the list
(ii) All marine equipments have to be obtained permit
from Port Authority before work in the Project.

(i) DHI has revised on MS (section 1.5)
(ii) All marine equipment’s will be obtained permit from
Port Authority before work in the Project

27-03-2020

Open

08-05-2020

Closed


27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020


Closed

27-03-2020

Open

08-05-2020

Closed

08-05-2020
13

Page 6

Closed
Please describe, here, this is subcontractor EHS
manager right? where is EHS supervisor???

DHI has revised on MS (section 1.6)

08-05-2020
14

Page 7

Closed
- Supplement the circle duration of each equipment.
- Supplement the estimated capacity of each equipment
per day, required q'ty per day and number of equip. to

be assigned at each location to assure schedule.

DHI has revised on MS (section 2.2 and 2.3)

08-05-2020
15

Page 8

Closed
(i) Please clarify where is tide gauge station? The tide
gauge have to comply with Article 9.2.6.2 in
specification.
(ii) Please describe frequency, line interval of postsurvey
(iii) Final survey should be mentioned as well.

08-05-2020
16

Page 9

Closed
Font

(i) DHI has mention on section 2.1.2, location will be
confirmed later
(ii) DHI has revised on MS (section 2.2.4) and it will be
complied with ITP which will submit separate
document.
(iii) DHI has revised on MS (section 2.2.5) and it will be

complied with ITP which will submit separate
document.
DHI has revised MS

08-05-2020
Closed
17

Page 9

This sentence is not clear, please explain

08-05-2020

DHI has corrected and deleted it, it’s not applied.

Closed

Page 4 of 14


Comment Response Sheet (CRS)
18

Page 11

Please explain how the trucks can run on landfill without
getting bogged down?

08-05-2020

Noted
Lot-4 please pay more attention on safety matter
during construction stage.

The truck is transporting dredged material to the
Landfill and dumping, method is same with site
development method which was approved by Owner

27-03-2020

Open

08-05-2020

08-05-2020

Closed

21-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed


27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020


Closed

27-03-2020

Open

08-05-2020

Closed

DHI noted

21-05-2020
19

Page 12

Closed
the depth is lower than -6.0m, it means EL. <= -6.0m?
Please correct it.

Yes, it means EL <=-6.0M

08-05-2020
20

Page 12

Closed
English please


DHI has revised MS (section 2.2.1)

08-05-2020
Closed
21

Page 13

English please

DHI has revised MS (section 2.2.1)

08-05-2020
Closed
22

Page 14

This figure is not clear.

DHI has revised MS (section 2.2.1)

08-05-2020
Closed
23

24

Page 14


Page 15

Can Cutter Suction Dredger make the slope ( 1: 4 ) ?
Please state how the slope
is constructed.
08-05-2020
Closed
Please provide silt protector in this drawing.

08-05-2020

DHI will use Clamshell to make the slope

DHI has revised MS (section 2.2.1)

Closed

Page 5 of 14


Comment Response Sheet (CRS)
25

Page 15

Where is it? Please provide detail design drawing of
temporary jetty.

DHI has revised MS (section 2.1.4)

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Open

08-06-2020


Closed

27-03-2020

Open

08-05-2020

Closed

08-05-2020
26

27

Page 15

Page 16

Closed
When Intake canal is dredged by Clamshell, Silt Curtain
may be needed to prevent diffusion of dredged material.
Please state how the slope (1: 1.5) is constructed.
08-05-2020
Closed
Any fall free prevention here?

08-05-2020
OPEN
Please reflect it in this document for site implementation

21-05-2020
OPEN.
There is no reflection at the section 2.1.4

DHI will prepare the silt-protector frame standby for
diffusion of dredged material, any slope will be done
by clamshell.

DHI will install the Curb to prevention fall free
19-05-2020
DHI has revised on MS rev C(section 2.1.4)
26-05-2020
DHI has revised on MS rev D(section 2.1.5)

08-06-2020
Closed
28

Page 19
It is recommended to classify the oil spills based on real
site condition, and detail the resources against oil spill
in response to article 6 and article 8 of decision No
02/2013/QD-TTg which did not mention in the "Plan of
Safety Marine assurance" document and "Oil spill
prevention plan".

DHI has explain in meeting with Owner/consultant,
Please see more detail on attachment 03:
Countermeasure to prevent oil leaks during dredging


08-05-2020
Closed

Page 6 of 14


Comment Response Sheet (CRS)
29

Page 19

There is no information for "Dredging plan including
mitigation measure and monitoring", no information of
"Waterway Traffic Safety Management Plan for
Dredging Activity", no information of as EPC's
commitment in the "EPC plan for detail HSE
documents"

Mitigation measure and monitoring has mention on MS
(section 4.4.1)
Other document will be submitted separately by DHI’s
EHS department.

27-03-2020

Open

08-05-2020

Open


21-05-2020

Open

08-06-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Open

08-06-2020


Closed

08-05-2020
OPEN
It is recommended to submit pertaining to this
document.

19-05-2020
Noted, but the MS cannot mention all document in
case

21-05-2020
OPEN
L4 has committed in the "EPC plan for detail HSE
documents" that These contents will be included
Method Statement for Dredging work plan.

26-05-2020
Mitigation measure and monitoring has mention on MS
(section 4.4.1), please refer to attachment 05 for water
way traffic safety management.

08-06-2020
30

Page 19

Closed
Is this sufficient?????


DHI has revised on MS (section 4)

08-05-2020
Closed
31

Page 19

Lifeboat will be inspected base on which code &
standard? Please describe detail

08-05-2020
OPEN
There is nothing revised
21-05-2020
OPEN
There is not any information, specification for
rescue boat at the attachment #3
08-06-2020

DHI has corrected its name and revised on MS
(section 4.1.3)

19-05-2020
Rescue boat is replaced for life boat in case,
recuse boat is mention on attachment #3
26-05-2020
Life boat will not use in this project, Passenger
boat is arranging to rescue in this time but DHI will

mobilize addition Speed boat prior Coal jetty piling
work start.

Closed

Page 7 of 14


Comment Response Sheet (CRS)
32

Page 20

How long will be placed ring buoy

Ring buoy will placed with 5-10m

08-05-2020
OPEN
Please reflect it in this document

19-05-2020
DHI has revised on MS rev C(section 4.2.3)

21-05-2020
33

Page 20

Closed

Please describe standard rescue boat

08-05-2020
OPEN
Please refer to attachment 04 for detail comment

21-05-2020
OPEN
Please clarify the standard, specification for the rescue
boat. There was no confirm from Owner management
team for L4's proposal in the meeting.

DHI has explain in meeting with Owner/consultant,
Please see more detail on attachment 03 :
EMERGENCY RESCUE BOAT PLAN
19-05-2020
DHI has provide on attachment #03
26-05-2020
Please see attachment o6 for this comment.

27-03-2020

Open

08-05-2020

Open

21-05-2020


Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Open

08-06-2020

Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open


08-05-2020

Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

08-06-2020
34

Page 21

Closed
Please describe all scenario of emergency response
here

DHI has revised on MS (section 4.1.8.2)

08-05-2020
35


Page 21

Closed
Who is report incident/accident to EHS officer?

DHI has revised on MS (section 4.1.8.2)

08-05-2020
Closed
36

Page 23

What the standard, please list out, project requirement
should be addressed

DHI will comply with document Health, Safety and
Environment Plan (VP1-0-EPC-H-GEN-10511) which
has been submitted separately to Owner/Consultant

08-05-2020
OPEN
Please reflect it in this document for site implementation

21-05-2020

19-05-2020
Noted but MS could not mention all document incase,
any relation document will be shared to parties for site
implement


Closed

Page 8 of 14


Comment Response Sheet (CRS)
37

Page 23

What is necessary PPE?

DHI has revised on MS (section 4.2.2)

08-05-2020

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020


Closed

27-03-2020

Open

08-05-2020

Closed

27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

27-03-2020

Open

08-05-2020

Closed


27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

Closed
38

Page 26

Please determined where is mooring area in case of
bad weather abnormal weather and describe more
detail on this ms

DHI has revised on MS (section 4.3.2)

08-05-2020
39

Page 27

Closed

What is countermeasure to minimized diesel spill
response prevention?

DHI has mention on attachment 02:
COUNTERMEASURE TO PREVENT OIL LEAKS
DURING DREDGING

08-05-2020
40

Page 27

Closed
Which training course will be delivered?

DHI will train/guider worker how to classify waste
material and put it in the right place

08-05-2020
OPEN
Please reflect it detailed in this document for site
implementation

19-05-2020
Noted, this scope will be guide to worker in general
safety induction course what is held for new worker

21-05-2020
41


Page 27

Closed
It is sea, not river

DHI has been revised on MS

08-05-2020
Closed
42

Page 27

According to EIA, suspended solids near the dredging
area or surrounding fixed points will be monitored
during the dredging process. Please detail describe this
activity.

This activity will be done by third party(EIA) and detail
plan will be submit in separately document

08-05-2020
Noted. But name of third party is EIA. Is that correct?
Detail of monitoring plan has to be get approved before
start dredging work.

19-05-2020
Noted, name of third party correctly is IE

21-05-2020

Closed

Page 9 of 14


Comment Response Sheet (CRS)
43

Page 1 of 2

It seem no review from Doosan's HSE team on this
document. the content of this risk assessment is too
meager and not comply with risk assessment
procedure. it is requested to revise.

All safety activity will be under review by DHI’s EHS
team, and DHI has been revised risk assessment on
attachment 04

08-05-2020
OPEN
As confirmed from DHI that Doosan's HSE team has
revised the risk assessment why the risk assessment
on attachment 02 is not in line with Doosan's risk
assessment procedure? Please check and revise
accordingly.

19-05-2020
Noted


27-03-2020

Open

08-05-2020

Open

21-05-2020

Closed

08-05-2020

Open

21-05-2020

Closed

08-05-2020

Open

21-05-2020

Closed

08-05-2020


Open

21-05-2020

Closed

08-05-2020

Open

21-05-2020

Closed

21-05-2020
44

Page 10

Closed
08-05-2020
Warning light is recommended to install on top of
buoys and anchor buoys for night time observation.

19-05-2020
This is marking buoy for dredge area only, it will not
make damage/affect with others thing(if any), warning
light available on each dredge equipment

21-05-2020

Closed
45

Page 10

08-05-2020
Please point out construction buoys which shall be
issued maritime notice by Port Authority?

19-05-2020
DHI has revised on MS rev C (section 2.1.1)

21-05-2020
46

Page 16

Closed
08-05-2020
Lot-4 please ensure that has no obstruction between
both jetty during construction stage.

19-05-2020
Noted, DHI is ensure that it has no obstruction
between both jetty during construction stage.

21-05-2020
47

Page 17


Closed
08-05-2020
Anchor buoy with warning light is recommended

21-05-2020

19-05-2020
DHI is noted

Closed

Page 10 of 14


Comment Response Sheet (CRS)
48

Page 21

08-05-2020
Regarding silt curtain: Lot-4 please provide specification
of silt curtain, such as open size of silt curtain, grab
frame type, etc...to ensure silt curtain can minimize
turbidity spread out surrounding sea area.

19-05-2020
DHI has revised on MS rev C(section 2.2.1)

08-05-2020


Open

21-05-2020

Closed

08-05-2020

Open

21-05-2020

Open

08-06-2020

Closed

21-05-2020
49

Page 27

Closed
08-05-2020
General comments: Please note that AIS track records
and video record is part of inspection record data. It is
required to submit frequency.
21-05-2020

OPEN
Please find further comment on page 29 of 46.

50

Attachment 4
Page 1

08-06-2020
Noted.
(i) Owner/consultant will do inspection of AIS and Video
recorder installation before put it on operation.
(ii) AIS account have to share to Owner/Consultant to
supervise purpose.
08-05-2020
Please clarify what is the specification for the rescue
boat? are there any reference for owner's information?
21-05-2020
OPEN
There is not any specification for rescue boat in the
attachment 03.

19-05-2020
Noted, DHI will submit to Owner as soon as possible
26-05-2020
AIS track records and video record is installed on
hopper barge and on tug boat which will pulling flat
barge

10-06-2020

Noted

Closed
19-05-2020
Please see attachment for clarify (attachment 03)
19-05-2020
Please see attachment to clarify this
comment(attachment 06)

08-05-2020

Open

21-05-2020

Open

08-06-2020

Closed

08-06-2020
Closed

Page 11 of 14


Comment Response Sheet (CRS)
51


Attachment 4
Page 1

08-05-2020
1. How to rescue the victim in some case where the tug
boat can not be approached due to the sunken bottom
the tug boat is too deep.
2. How to move the victim who has broken bones from
the see to tug boat when it is too height from the
surface of water lever.
3. In the emergency case the time is limited, so it is not
sufficient for tug boat operation, moreover, the tug boat
shall be operated with high speed in the emergency
case and there contain many blind area, big wave.
4. With above three analysis. It is recommended to use
the professional rescue boat which mentioned in
SOLAS Convention which Vietnam is a member or any
other reasonable specification suggested by EPC
contractor for VPCL's review
21-05-2020
OPEN
Please refer to attachment 3 for detail comment.

19-05-2020
DHI has changed the rescue boat (attachment 03)
Occupied the hard type bed and other facilities as
below,

08-05-2020


Open

21-05-2020

Open

08-06-2020

Closed

21-05-2020

Open

08-06-2020

Closed

26-05-2020
Offshore Rescue Drill has been conducted one time to
exercise rescue if any accident/incident happen, this
activity will be held on 2~3 month one time. Passenger
boat is arranging to rescue in this time but DHI will
mobilize addition Speed boat prior Coal jetty piling
work start.

08-06-2020
52

5


Closed
21-05-2020
Please revise the volume according to DONRE
consent.

26-05-2020
DHI has revised on MS rev D (section 1.4)

08-06-2020
Closed

Page 12 of 14


Comment Response Sheet (CRS)
53

24

21-05-2020
This route is not in line with approved maritime safety
assurance plan.

26-05-2020
DHI has confirmed with PA NT that We can update/
supplement again when MS approval.

08-06-2020


10-06-2020
DHI has deleted this route on Ms rev E

OPEN. Not only Maritime Safety Assurance Plan, but
EIA also should be updated new route and get
approval, otherwise the route will be not approved by
Owner.
54

29

21-05-2020
According to Decree No. 159-ND/CP-2018, all
equipment’s which transport dredged material have to
install AIS and video recorder.

21-05-2020

Open

08-06-2020

Open
Closed

26-05-2020
AIS track records and video record is installed on
hopper barge and on tug boat which will pulling flat
barge


21-05-2020

Open

08-06-2020

Closed

26-05-2020

21-05-2020

Open

Offshore Rescue Drill has been conducted one time to
exercise rescue if any accident/incident happen, this
activity will be held on 2~3 month one time. Passenger
boat is arranging to rescue in this time but DHI will
mobilize addition Speed boat prior Coal jetty piling
work start.

08-06-2020

Closed

08-06-2020
Closed
55

Emergency

Rescue Boat
Page 1

21-05-2020
1. How to rescue the victim in some case where the
boat DU LICH 36 can not be approached due to the
sunken bottom the tug boat is too deep.
2. How to move the victim who has broken bones from
the see to boat DU LICH 36 when it is too height from
the surface of water lever.
3. In the emergency case the time is limited, so it is not
sufficient for boat DU LICH 36 operation, moreover, the
tug boat shall be operated with high speed in the
emergency case and there contain many blind area, big
wave.
4. With above three analysis. It is recommended to use
the professional rescue boat which mentioned in
SOLAS Convention which Vietnam is a member or any
other reasonable specification suggested

08-06-2020
Closed

Page 13 of 14


Comment Response Sheet (CRS)
58

59


11

25

08-06-2020
Assessment negative impact to environment in
this revision compared with previous revision to be
compared with approved one before execution.

08-06-2020
Assessment negative impact to environment in
this revison compared with previous revision to be
compared with approved one before execution.

10-06-2020
Noted, from Ms rev A, DHI has mention that
when tide down and at shallow area excavate
method by excavator is conducted directly, this
step is dispatched to more improvement any
negative impact to environment.
10-06-2020
DHI has deleted this route on Ms rev E

08-06-2020

Open

Noted


08-06-2020

Open

Noted

Additional Notes (if any)
* O - Open, C – Closed

Page 14 of 14


AP

APPROVED
Approved

AC

APPROVED WITH COMMENT
Contractor to revise the correction and resubmit

NOT APPROVED
For Approval

NA

Revise the correction and resubmit before proceeding

RE


REVIEWED
Information acknowledged with no comment

RC

REVIEWED WITH COMMENT
Information acknowledged with comments

Note: Approval or comment does not relieve the Contractor of
all obligations covered under contract

E

10-Jun-2020

D

For Approval

KS KIM

ET KIM

27-May-2020

JH CHOI
Discipline: Civil
18 Jun
20

For Approval Date:
JH CHOI

KS KIM

ET KIM

C

19-May-2020

For Approval

JH CHOI

KS KIM

DS YU

B

25-Apr-2020

For Approval

JH CHOI

KS KIM

DS YU


A

13-Mar-2020

For Approval

JH CHOI

KS KIM

ET KIM

REV

DATE

DESCRIPTION

Approved

Checked

Prepared

OWNER

VAN PHONG POWER COMPANY LIMITED
PROJECT


Van Phong 1 BOT Thermal Power Plant Project
Status
□Approved
□Approved with Comment
□Not Approved
□Reviewed

OWNER’S ENGINEER
Pöyry Switzerland Ltd.
EPC CONTRACTORS

IHI–TESSC–CTCI–DHI CONSORTIUM

PROJECT DOCUMENT No

REV

VP1-0-L4-C-GEN-10019

E

DOCUMENT TITLE

METHOD STATEMENTS FOR DREDGING WORKS
EPC

EPC DOCUMENT No.
VP1-0-L4-C-GEN-10019

Doosan Heavy Industries and Construction


REV
E

Page | 1


METHOD STATEMENTS FOR DREDGING WORKS

TABLE OF CONTENTS
1
1.2
1.3
1.3.2
1.3.3
1.4
1.5
1.6
1.7
1.8
2
2.1
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
2.2
2.2.1

2.2.2
2.2.3
2.2.4
2.2.5
2.3
2.3.1
2.3.2
3
3.1
3.2
3.3
3.4
4
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.1.8
4.2
4.2.1
4.2.2
4.2.3
4.3
4.3.1

GENERAL .............................................................................................................. 4

Purpose .................................................................................................................... 4
Reference documents .............................................................................................. 4
Technical Documents .............................................................................................. 4
Codes and Standards .............................................................................................. 5
Scope of work .......................................................................................................... 5
The equipment mobilization plan: .......................................................................... 5
Site Organization Chart .......................................................................................... 7
Sequence of work .................................................................................................... 8
General schedule ..................................................................................................... 8
METHOD OF CONSTRUCTION WORKS .......................................................... 9
Site preparatory work ............................................................................................. 9
Setting of construction buoy ................................................................................... 9
Onshore excavation and dredging work ............................................................... 10
Tide gauge installation .......................................................................................... 10
Pre-dredging Survey ............................................................................................. 11
Landfill Area & Temporary Jetty......................................................................... 13
Anchors and moorings .......................................................................................... 18
Work method ........................................................................................................ 18
Dredging area planning......................................................................................... 18
Depth dredging control: ........................................................................................ 24
Interim dredging survey ....................................................................................... 25
Post-dredging survey ............................................................................................. 25
Final survey ........................................................................................................... 25
Dredging productivity ........................................................................................... 25
Productivity of Clamshell...................................................................................... 25
Productivity of TSHD ........................................................................................... 26
MANAGEMENT OF WORK ............................................................................ 28
Dredging tolerance .............................................................................................. 28
Site Coordinates and Elevation Control ............................................................ 28
AIS system (applied for hopper barge disposal only)....................................... 28

Inspection and Test Plan ..................................................................................... 29
HEALTH, SAFETY AND ENVIRONMENT ORGANIZATION ....................... 30
General Safety Procedures ................................................................................. 30
Floating Plant & Equipment .............................................................................. 30
Marine Safety Assurance Plan ........................................................................... 30
Inspection of safety equipment ........................................................................... 30
Marine Works ...................................................................................................... 30
Work Over Water................................................................................................ 31
Housekeeping ....................................................................................................... 31
Fire Precautions ................................................................................................... 32
Site Situation Response and Emergency Response........................................... 32
Safety Practice Rules ........................................................................................... 34
Marine work......................................................................................................... 34
Personal Protection equipment (PPE) ............................................................... 34
Risk Assessments ................................................................................................. 36
Maritime Safety Assurance................................................................................. 38
Maritime Safety Assurance................................................................................. 38

P a g e |2


METHOD STATEMENTS FOR DREDGING WORKS

Gathering of construction equipment when suspended ................................... 38
Plan for coordinated implementation ................................................................ 39
Studying, training, inspection and supervision of traffic safety ...................... 40
Environmental considerations ............................................................................ 40
Mitigation measures ............................................................................................ 40
5
ATTACHMENT ................................................................................................... 42

ATTACHMENT 01: SCHEDULE FOR DREDGING WORKS ......................................................... 43
ATTACHMENT 02: COUNTERMEASURE TO PREVENT OIL LEAKS DURING DREDGING . 44
ATTACHMENT 03: EMERGENCY RESCUE BOAT PLAN ............................................................ 45
ATTACHMENT 04: RISK ASSESSMENT ......................................................................................... 46
ATTACHMENT 05: Transportation and Traffic Mitigation .............................................................. 47
ATTACHMENT 06: LSA Rescue Boat Requirement .......................................................................... 48
4.3.2
4.3.3
4.3.4
4.4
4.4.1

P a g e |3


METHOD STATEMENTS FOR DREDGING WORKS

1

GENERAL
1.2
Purpose
The Van Phong 1 BOT Thermal Power Plant is located in Van Phong bay and contiguous to
My Giang transshipment and petrol intrepot warehouse area.
The purpose of this Method Statement is to describe the methodology involved in dredging
works at the approved area in accordance with the technical standard and EHS requirements
of Van Phong 1 BOT Thermal Power Plant Project.

DREDGING AREA 2
Discharge Canal

(EL-4.1m)

LANDFILL
Disposal Area

DREDGING AREA 3
Unloading Ramp
(EL-5.6m)
DREDGING AREA 1
Coal Jetty Front
(EL-18.3m)
DREDGING AREA 4
Intake Canal
(EL-5.1m)

Figure 1. General plan of Dredging works
1.3

Reference documents
1.3.2
Technical Documents
Drawing:
-

VP1-0-L4-C-GEN-00101 to 00109

Documents:
-

VP1-0-L4-C-GEN-00001_Soil Investigation Report (Rev.C);

Part III-2 Exhibit B1 Tech Spec Section 9;
P a g e |4


METHOD STATEMENTS FOR DREDGING WORKS

1.3.3

1.4

Report on changed items from immersion at sea to landfill by dredged material for Van
Phong 1 BOT Thermal Power Plant project.
Codes and Standards

-

TCVN 4055-85

Construction Plan;

-

TCVN 2287 1978

Construction Safety Standard System. Basic Regular

-

TCVN 4447-2012


Earth works. Rules for the construction and acceptance

-

Decision 24/QD-KT4 Process of working acceptance of dredging work for waterway
transportation by mechanical means.

-

TCVN 9401-2012
Technical Standard of GPS Survey and Processing for
Construction geodetic

-

Decree 46/2015/NĐ-CP: Quality Control and Maintenance of Project Construction

-

TCVN 5674-1992

-

Vietnam Maritime Code dated 2015

-

Decree No. 58/2017/NĐ-CP dated 10 May, 2017 of the Government regulating in
details some Article of Vietnam Maritime Code about marine operation management;


-

Decree 159/2018/NĐ-CP: Management of Dredging Activities in The Water Areas of
Seaports And Inland Waterways

-

International Convention for the Safety of Life at Sea (SOLAS),1974- LSA – Code
International Life – Saving appliance Code (MSC.48(66))

-

International Convention for the Prevention of Pollution from Ships (MARPOL 73/78)
(Appendix I, IV, V)
Scope of work

Finishing work for Project Construction.

This method statement described the work sequence, manpower and equipment for dredging work
in coal jetty, unloading ramp front area, and intake and discharge canal area.
The dredging works will be carried out by designed suitable equipment and disposal will be
dump on the Landfill.
The Contractor will carry out the following dredging work with it estimated volume
No.

1
2
3
4
5

1.5

Table 1. Dredging works summary
Dredging work
Bottom
Volume
Elevation
(Estimation)
(NDL)
Coal Jetty Front Area
EL.-18.3m
141,369
Unloading ramp front Area
EL.-5.6m
139,346
Intake Canal
EL.-5.1m
29,807
Discharge Canal
EL.-4.0m
105,051
Landfill
415,573 m2

The equipment mobilization plan:
Table 2. Equipment mobilization for Dredging
P a g e |5


METHOD STATEMENTS FOR DREDGING WORKS


No.
1

Equipment name
Trailing Suction Hopper Dredger

Capacity

Quantity

4500 HP -

1

Remarks

Hopper 1500m3
2

Floating pump station equipped 02
pump machines

3

2 x 400 HP

1

3


320m /h
Bucket 6-8m3

Clamshell

4

216m3/h
4

Transportation Barge

600-1000m3

6

5

Tug boat

450HP

2

6

Unloading excavator

Bucket 1.2-1.4m3


4

7

Truck

15m3

04

8

Land excavator

Bucket 1,2m3

02

9

Bull-dozer

D300

01

10

Emergency boat


20 HP

01

11

Rescue boat (by Tugboat)

Note: Certificates and insurances for the above equipment shall be separately submitted to the
Employer before mobilization to the Site. And All marine equipment shall be obtained permit from
Port Authority before work in the Project
Table 3. Plan of Equipment mobilization for Dredging
S/N

2020

Descriptions
Duration

1.1

Dredging work

1.1.1

CW Unloading ramp

5M


1.1.2

CW intake & discharge canal

4M

1.1.3

Coal unloading jetty

3M

2.1

Landfilling work

2.1.1

Preparation & maintenance of landfill area

2.1.2

Leveling and compaction on landfill area

S/N
1

Description
Trailing Suction Hopper Dredger


3

Floating pump station equipped 02 pump
machines, D200 pump pipe
Clamshell

4

Material Transportation Barge

2

Capacity

3

4

5

6

7

8 9

10

11


12

Equipment
-Month

4500HP
1,500 m3

3

1

1

1

2x400HP

3

1

1

1

60 Tons

18


2

4

4

4

4 2

600-1000m3

28

2

6

6

6

6 2

P a g e |6


METHOD STATEMENTS FOR DREDGING WORKS

S/N


2020

Descriptions
Duration

5

Tug boat

6

Unloading excavator

7

Truck

8

Land excavator

9

Bull Dozer

10

450HP


3

10

4

1.2-1.4m3

6

7

8 9

2

2

2

2 1

4

4

4

4


4

4

4 2

1

1

1 1

1

1

1 1

15 m3

20

2

4

Bucket 1.2m3

9


2

2

D300

9

1

Rescue boat

1.6

5

1

1

10

11

1

12

1


Site Organization Chart

DHI

OFFSHORE TEAM

SUBCONTRACTOR

OF DHI

OEC

Site Manager

EHS MANAGER

QA/QC MANAGER

CONTROL ENGINEER

SURVEY & QUANTITY SURVEY TEAM

MECHANICAL ENGINEER

EHS SUPERVISOR

DREDGE TEAM

CONSTRUCTION
SUPERVISOR


DISPOSAL & LANDFILL TEAM

Figure 2. Site Organization Chart

P a g e |7


METHOD STATEMENTS FOR DREDGING WORKS

1.7

Sequence of work

Preparation work & Pre-survey

Setting out of dredging areas; disposal area
(LANDFILL), temporary jetty, floating pump
station and dredged material transport routes…

Moving equipment to dredging areas

Daily Dredging

Transport to Floating Pump Station

NOT

OK
Interim survey


OK
Final survey and Inspection

Demobilization

Figure 3. Dredging Sequence
1.8

General schedule

Please see ATTACHMENT 01: SCHEDULE FOR DREDGING WORKS

P a g e |8


METHOD STATEMENTS FOR DREDGING WORKS

2

METHOD OF CONSTRUCTION WORKS
2.1
Site preparatory work
2.1.1
Setting of construction buoy
The dredging areas shall be set out before commencement of work. Each dredging area shall
be located on site layout by construction buoys (marking buoys). For the navigation buoys, it
is installed as showed on the Marine Safety Assurance Plan.

Figure 4. Navigation buoys system


Figure 5: Marking position buoys plan for dredging area
P a g e |9


METHOD STATEMENTS FOR DREDGING WORKS

2.1.2

Onshore excavation and dredging work
Between onshore excavation and dredging works will be set up a divide boundary and
temporary cofferdam is constructed prior commencement of excavation in order to keep
dry condition, this location is termination point and it will be carry out by on-shore
contractor, specific:

<Discharge canal>

<Intake canal>

<Temp. Unloading Ramp>

< Section of temporary cofferdam (by onshore)>

-

2.1.3
Tide gauge installation
In order to control the vertical of the work, the tide gauge shall be installed to comply with the
requirement.


-

The tide gauges shall be installed at strategic locations around the Site. The temporary tide
gauges shall be installed to give immediate visual measurements of sea level. They shall be
constructed vertically and firmly fixed on rigid supports at locations agreed and shall be leveled
and fixed to give tidal readings within an accuracy of ±20mm. Temporary tide gauges shall be
made of 50mm thick hardwood and shall be at least 150mm wide and established with 0.0m at
the Chart Datum. The gauges shall be painted on the marked faces with alternate 100mm stripes
P a g e | 10


METHOD STATEMENTS FOR DREDGING WORKS

in red and white and shall be marked and numbered in black at 0.5m intervals over the tidal
range. The painting applied shall consist of one primary coat, two undercoats and one finishing
coat. [Please refer to figure 6]
TEMPORARY TIDE GAUGE
Hardwood (50mm thick, 250mm wide)
SECTION A-A
250

50

Steel Pipe D250mm, L5.0 m

Steel Pipe D250mm, L2.0 m

Red paint
White paint


A

Hardwood (T50mm, W250mm), L5.0m

A

Figure 6: Temporary Tide gauge
2.1.4
Pre-dredging Survey
• Survey equipment shall be inspected with full calibration document.
Table 3. Table of Survey Equipment
Equipment name

Capacity

Unit

Quantity

200 KHz

set

01

DGPS 110

set

02


Garmin map Cs 60

Set

04

Survey Boat

30 HP

set

02

Total Station

± 5PPM

set

01

± 3MM/KM

set

01

Echo Sounder

DGPS
GPS

Auto Level

Remarks



Permanence of bench marks will be set up, it is frequency checked and clarified by certified
surveyor or third party and it will be submitted to owner/consultant for approval in separate
document.



The dredging area will be surveyed by using echo sounder method.
P a g e | 11


×