Comment Response Sheet (CRS)
Project Title
Van Phong 1 BOT Thermal Power Plant Project
Document Title
METHOD STATEMENT FOR CONCRETE
REPAIRING WORK
Document Type
For Approval
Document No
VP1-0-L4-C-GEN-10025
Returned Status
NA
Prepared by
CRS No
VP1-0-L4-C-GEN-10025-A-CRS
CRS Issued Date
13/05/2020
Engineer
Construction
Remarks
No.
Section/
Page
Owner’s Comment
Response to Comment
Review
Date
Status O/C *
1
3
Supplement item "Classification of the concrete
defects and its reason" so that can propose a
proper repair method (Voids, Honeycomb,
Scaling, Crack, Cold joint, Damaged)
Lot4 addition in revision B
13/05/2020
Closed
O
2
3
Before stepping the repair procedure for each
defect, please provide summary table as below.
Noted and addition in revision B
13/05/2020
Closed
O
3
4
It needs to be assessed if there is any other
underlying damage before the repair methods
described in this document can be applied.
Lot4 will proposal method case by case
specifically and addition in revision B
13/05/2020
4
4
The cause of the crack needs to be assessed.
Noted and addition in revision B
13/05/2020
Closed
O
5
4
Please delete the information of 40mm in all
content.
Lot4 revised in revision B
13/05/2020
Closed
O
6
4
material shall be same strength with base
concrete at least.
The material strength at least equal concrete
strength. Addition in revision B
13/05/2020
7
4
The repaired surface needs to be re-examined
after a specified amount of time to check if the
crack has reappeared.
The repair surface will re-checking after repaired
24 hour, if appear crack must be re-repair as
described in this MS (revised in revision B).
13/05/2020
L4
O
Closed
Closed
O
O
Closed
Page 1 of 3
Comment Response Sheet (CRS)
8
5
Not agreed since consider the material strength in
case air void is serious.
Lot4 change material as revision B
13/05/2020
Closed
O
9
5
Cement slurry will make crack due to strong
shrinkage, recommend to use Sika Refit 2000 or
cement mortar with Sika latex.
Lot4 will use Sika Refit 2000 or GPS mota 16
13/05/2020
Closed
O
10
5
Specify maximum depth of chipping for which this
treatment can be applied.
Maximum depth of chipping for this treatment is
20mm.
13/05/2020
Closed
O
11
6
Specify maximum depth of chipping for which this
treatment can be applied. What will be done if the
reinforcement bars are reached/exposed?
Maximum depth of chipping for this treatment is
50mm.
13/05/2020
Closed
O
12
6
Before apply Monotop R, recommend to use Monotop
Lot4 revised in revision B
13/05/2020
Closed
O
610 as primer layer.
13
6
Before any remedial measure the cause of the
crack needs to be assessed.
Lot4 revised in revision B
13/05/2020
O
Closed
14
7
Missing method to repair crack for the floor for
example in building floor when through crack.
Base on assessed actual reason and width of
crack Lot4 will propose method for case by case
specification.
13/05/2020
15
8
Water leak test is needed after treatment. Please
add
Lot4 revised in revision B
13/05/2020
16
11
Supplement repair method for Scaling concrete,
Cold joint and Damaged.
Lot4 added in revision B
13/05/2020
Closed
O
17
11
It needs to be checked if the reinforcement bars
have moved so that they might be closer to the
repaired surface than the prescribed cover.
Unsuitable placement of reinforcement might
require more extensive repair including complete
removal and reconstruction.
Lot4 noted and addition in revision B
13/05/2020
O
Closed
O
Closed
O
Closed
Page 2 of 3
Comment Response Sheet (CRS)
Additional Notes (if any)
* O - Open, C – Closed
Page 3 of 3
AP
APPROVED
Approved
AC
APPROVED WITH COMMENT
Contractor to revise the correction and resubmit
NA
NOT APPROVED
Revise the correction and resubmit before proceeding
RE
REVIEWED
Information acknowledged with no comment
For Approval
RC
REVIEWED WITH COMMENT
Information acknowledged with comments
Note: Approval or comment does not relieve the Contractor of
all obligations covered under contract
Discipline: Civil
30 May 20
Date:
B
20-May-2020
For Approval
J.H CHOI
K.S KIM
D.H Jeong
A
08-May-2020
For Approval
J.H CHOI
K.S KIM
D.H Jeong
REV
DATE
DESCRIPTION
Approved
Checked
Prepared
OWNER
VAN PHONG POWER COMPANY LIMITED
PROJECT
Van Phong 1 BOT Thermal Power Plant Project
Status
□Approved
□Approved with Comment
□Not Approved
□Reviewed
OWNER’S ENGINEER
Pöyry Switzerland Ltd.
EPC CONTRACTORS
IHI–TESSC–CTCI–DHI CONSORTIUM
PROJECT DOCUMENT No
REV
VP1-0-L4-C-GEN-10025
B
DOCUMENT TITLE
METHOD STATEMENT FOR CONCRETE REPAIRING WORK
EPC
EPC DOCUMENT No.
VP1-0-L4-C-GEN-10025
Doosan Heavy Industries and Construction
REV
B
B
B
B
Revise material according
to item 5.1; 5.2
B
B
B
B
B
B