Comment Response Sheet (CRS)
Project Title

Van Phong 1 BOT Thermal Power Plant Project

Document Title

METHOD STATEMENT FOR BOILER
FOUNDATION UNIT 1

Document Type

For Approval

Document No

VP1-1-L4-C-HBA-10046

Returned Status

AC

Prepared by

CRS No

VP1-1-L4-C-HBA-10046-A-CRS

CRS Issued Date

08/05/2020



Engineer

Construction

Review
Date

Status O/C *

Remarks

08/05/2020

Closed
O

No.

1

Section/
Page
0

Owner’s Comment

Response to Comment

This MS is behind from MS for TG foundation. Is

the sub-contractor different from the subcontractor of STG foundation ?
Does the sub-contractor has experience of Boiler
foundation of same size ? Especially keeping
method for quality control of massive concrete.
DHI is the prime contractor and has to manage
strictly sub-contractors to keep the same quality of
design, MS and construction work, although
different sub-contractors. Did DHI check this MS
really ?

-The sub-contractor of Boiler foundation is
different to TG foundation.

L4

-The sub-contractor has been built some Boiler
foundations which similar to this one in past. For
example: Duyen Hai 3 extension thermal power
plant, Qty=10000m3; Nghi Son 2 thermal power
plant, Qty=12778m3.
-DHI sincerely reviewed MS and has full
responsibility of quanlity.

2

0

How about Unit 2 ?

The method statement for boiler foundation unit 2

will be submitted by another submission

08/05/2020

Closed
O

3

5

Stage 3 ~ 6 concrete volume is 2100 ~2700 m3
which is huge. These stages should be divided in
two stages to easily manage the measures for
mass concrete like TG foundation.

DHI has calculated the concrete supply as well
as checked with capacity of concrete batching,
besides other method statements have been
prepared to make sure the quality of massive
concrete

08/05/2020

Closed
O

Page 1 of 6



Comment Response Sheet (CRS)
4

5

This staging of pouring concrete is not adequate.
Stage 1, 2 and 3 is OK, but the last Stage 6
concrete is restricted by Stage 3 and 4 concrete.
Then there must arise tension force and possibly
cracked by shrinkage during hardening of massive
concrete.
This is the common sense.

DHI has updated new procedure as following
comments and sequence of Anchor bolts
installation plan which is belonged to IHI

08/05/2020

Closed
O

5

7

Can not find de-watering system. Please note that
the buoyancy checking at +2.0mNDL, dewatering
system is very important especially for SCC sump
construction.


DHI will set up the ditch to collect water and
arrange water pump

08/05/2020

Closed
O

6

7

This space is very narrow.
How can Re-bar & Formwork be constructed ?

The vertical lean concrete will be cast before the
next activities such as rebar and formwork
installation

08/05/2020

Closed
O

7

7

Is thickness of Lean concrete 50mm? If anchor

frame for anchor bolts is fixed with lean concrete,
50mm is too thin.
Tolerance of excavated surface will be ± 20mm
and thinnest lean concrete will be less than
30mm.

The thickness of lean concrete follows design
drawing is 50mm, DHI makes sure the thickness
which will be constructed (minimum 50mm)

08/05/2020

Closed
O

8

8

Who will approve this and how will the approval
request be submitted?

DHI revised

08/05/2020

O
Closed

9


8

Is support bar re-bar ? Re-bar is not enough
stiffness and unstable.
Steel sections should be used for support. This is
also HSE mater.

DHI uses proper chair bar which retain safety
and enough capacity stiffness and stable.

08/05/2020

10

9

If thickness of 3m and 1.5m foundation is poured
concrete continuously, how is this portion
constructed ? Please show the detail.

The lean concrete in the shape of chamfer will be
cast in advance of rebar and formwork.

08/05/2020

Note O
Please provide chair bar in the
bar bending schedule


Closed
O

Page 2 of 6


Comment Response Sheet (CRS)
Method of installation of Anchor bolts for Boiler
structure is not shown.
These anchor bolts are very important for Boiler
structure.
Please show it on detailed drawing.

Method statement of Bolts installation will be
submitted by another contractor(IHI). DHI will
coordinate to IHI for this matter on site

08/05/2020

Closed
O

10

This support rebar is very flexible and must be
moved during concreting. Steel sections is better.

DHI has updated in method, the anchors will be
added to make sure stable.


08/05/2020

Closed
O

13

12

How is this support bar fixed at the bottom ?
Please show the detail.

DHI has updated in method drawing

08/05/2020

Closed
O

14

14

To provide thermal calculation for the specific
mass concrete block
How to control the valued - cooling system inside
the block is recommended and what will
constructor do if the real temperature exceed 70
deg. C


Please consider there is high difficulty to

08/05/2020

11

9

12

calculate exact heat of hydration. DHI is all
responsible to control concrete temperature as
following related specification.

OPEN O
Because the Contractor do not assign a
cooling system after pouring, request the
Contractor to supplement the heat check
of mix design to ensure the limitation of
maximum temperature otherwise nothing
can be done after casting.

15

14

How is Metal mesh treated at the top re-bar,
before new concrete pouring ?

At top of rebar layer, DHI will use formwork to

make the construction joint, when casting
concrete next time, Contractor will chip the
concrete to make rough surface.

08/05/2020

Closed
O

16

14

Additional condition, the difference temperature
between 2 points at 1m distance must be less
than 50 deg (refer Art. 6.6 - TCXDVN 305 for
Mass concrete). How to check and control it?

DHI has updated, the method of monitoring for
temperature has been showed into method

08/05/2020

Closed
O

Page 3 of 6


Comment Response Sheet (CRS)

17

14

Show that concrete temperature will not raise
more than 40C.

the concrete
is placed there isOvery limited options to act if
08/05/2020
Please consider there is high difficultyOnce
to check
concrete temperature rises excessively. ACI for example has
exact heat of hydration. DHI is all responsible to
methodologies to calculate the temperature increase. Heat of
hydration
might be available from the cement supplier or can be
control concrete temperature as following
related
estimated based on the chemical composition of the cement.
specification.

18

14

These 2 conditions mean that the surface
temperature may increase to 50C. This is unlikely
to be possible, especially with the water
application during curing.


Cover top of surface by foam thickness 3cm,
keep the side formwork until the temperature
differential between the middle of concrete mass
and any outer surface is under controlled.

08/05/2020

O

Closed

19

14

side vibration on formworks is recommended

DHI has updated

08/05/2020

Closed
O

20

14

There is no statement about production,

transportation , pump car, agitating truck and etc.
for 2000 ~2700m3 concrete.

The calculation of concrete supply, transportation
will be attached as an attachment 3.

08/05/2020

Closed
O

21

16

Show a calculation that tis assumption is correct.
It is very unlikely that the center of the foundation
will be at air temperature after 7 days.

DHI revised

08/05/2020
Closed

22

16

How long does the thermal monitoring take ?
Please describe more for the thermal monitoring

process

DHI has updated

08/05/2020

23

16

Provide a calculation showing the temperature
increase and then decrease of the mass concrete
to ensure that it does not create a delay due to
excessive temperatures.

DHI revised

08/05/2020

24

16

Lack of other works to complete the foundation
such as coating, backfilling..

Coating work, backfilling will be submitted by
other submissions to get approval.

08/05/2020


O

Closed
O

Closed

O

Closed
O

Page 4 of 6


Comment Response Sheet (CRS)
25

16

Measures for Massive concrete of Boiler
Foundation (2,000~2500 m3) is different from TG
foundation Ð1500 m3). DHI should manage the
sub-contractors for the same measures of
massive concrete.
Casting time for each stage of Boiler foundation
must be more than 20 hours and then Temporary
Tent should be used for sudden rain and direct
sunshine.


-The calculation of concrete supply,
transportation will be attached as an attachment
3.

08/05/2020

Closed
O

-Plastic cover will standby near concreting area.

26

16

It is not acceptable because risk assessments
used to assess based on method statement of
each task, difference method means difference
risk. how come the risk assessment from general
concrete work can cover all the risk for the boiler
foundation activities? EPC to prepare the risk
assessment for boiler foundation activities as
project requirement.

DHI has updated

08/05/2020

OPEN

Please O
refer to section 8.1 for detail
comment

27

17

1. Please describe detail risk assessment as per
circular 07/2016/TT-BLĐTBXH required.
Please noted that we do not want to repeated
every single MS to asking about risk assessment,
Please do your job properly then VPCL is not your
consultant
2. The job safety analysis was not in line with DHI
risk management procedure.
3. It's repeated again, It's seems that no one from
DHI's EHS team review this MS before submitted
to VPCL

DHI has updated

08/05/2020

OPEN
O
Please refer to section 8.2 for detail
comment

28


33

How about Unit #2 - will we have different MS ?

The method statement for boiler foundation unit 2
will be submitted by another submission

08/05/2020

Closed
O

Page 5 of 6


Comment Response Sheet (CRS)
29

41

Present the lighting arrangement, team of worker
for each shifts
Additional Notes (if any)
* O - Open, C – Closed
30

41

Please provide the calculation for concrete

supplier/transfer. backup plan to ensure the
pouring concrete will be carry out continually.
Time schedule must be estimated properly

The calculation of concrete supply, transportation
will be attached as an attachment 3.

08/05/2020

Closed
O

DHI has updated, the worker will arrange
appropriately in accordance with site activities

08/05/2020

Closed
O

Page 6 of 6


AP

APPROVED
Approved

AC


APPROVED WITH COMMENT
Contractor to revise the correction and resubmit

NA

NOT APPROVED
Revise the correction and resubmit before proceeding

RE

REVIEWED
Information acknowledged with no comment
For Approval

RC

REVIEWED WITH COMMENT
Information acknowledged with comments

Note: Approval or comment does not relieve the Contractor of
all obligations covered under contract

Discipline:
Date:

Civil
07 Jul 20

B


22-Jun-2020

For Approval

J.H CHOI

K.S KIM

D.H JEONG

A

23-Apr-2020

For Approval

J.H CHOI

K.S KIM

D.H JEONG

REV

DATE

DESCRIPTION

Approved


Checked

Prepared

OWNER

VAN PHONG POWER COMPANY LIMITED
PROJECT

Van Phong 1 BOT Thermal Power Plant Project
Status
□Approved
□Approved with Comment
□Not Approved
□Reviewed

OWNER’S ENGINEER
Pöyry Switzerland Ltd.
EPC CONTRACTORS

IHI–TESSC–CTCI–DHI CONSORTIUM

PROJECT DOCUMENT No

Document title is unit 1,
then attached construction
drawing is unit 2?

REV


VP1-1-L4-C-HBA-10046

B

DOCUMENT TITLE

METHOD STATEMENT FOR BOILER FOUNDATION UNIT 1
EPC

EPC DOCUMENT No.
VP1-1-L4-C-HBA-10046

Doosan Heavy Industries and Construction
1|Page

REV
B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

Table of Contents
1.

PREFACE ............................................................................................................ - 3 -

2.

REFERENCE ...................................................................................................... - 3 2.1 Applicable Code and Standard ............................................................................................................... - 3 2.2 Drawing and Method Statement ............................................................................................................. - 4 -


3.

MANPOWER & EQUIPMENT .......................................................................... - 4 -

4.

RESPONSIBILITIES .......................................................................................... - 5 -

5.

PROCEDURE AND SEQUENCE .................................................................... - 6 -

6.

CONSTRUCTION WORK ................................................................................. - 9 6.1

Excavation and disposal ..................................................................................................................... - 9 -

6.2

Lean concrete ....................................................................................................................................... - 10 -

6.3

Reinforcement work ........................................................................................................................... - 10 -

6.4

Installation of embedded plate, box out (if any) ...................................................................... - 13 -


6.5

Please supplement the concrete
surface finishing method with
Formwork ...............................................................................................................................................
- 14
and/or without
hardener

6.6

Concrete work ...................................................................................................................................... - 17 -

6.6.1

Construction Joint. ......................................................................................................................... - 17 -

6.6.2

Massive concrete. .......................................................................................................................... - 19 -

7. INSPECTION AND TESTING .................................................................................... - 24 8. ENVIRONMENT, HEALTH AND SAFETY (EHS) ................................................... - 24 8.1 Risk assessment ....................................................................................................................................... - 25 8.2 Job Safety Analysis .................................................................................................................................. - 54 Attachment #1 : Calculation sheet for Formwork .................................................................................. - 64 Attachment #2 : Method Drawing ............................................................................................................... - 65 Attachment #3 : Calculation for concrete supply ................................................................................... - 66 -

- 2 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT

PROJECT

1.

PREFACE
The purpose of this method is to describe the methodology involved in construction work for the Boiler
foundation item and to detail out the steps to be taken in order to meet the technical requirements of
VP1 BOT Thermal Power Plant.
 Project

Van Phong 1 BOT Thermal Power Plant

 Company/Owner

Van Phong Power company limited(VPCL)

 Contractor

DHI

 ITEM

2.

Boiler Foundation Unit 1

REFERENCE
2.1 Applicable Code and Standard



ACI 347-Guide to formwork for concrete



ACI 304-Guide for measuring, mixing, transporting, and placing concrete



ACI 301-Specifications for structural concrete for buildings.



ACI 318-Building Code Requirements for Structural Concrete.



ACI-305R-Guide to hot weather concreting.



ASTM C33: Standard specification for concrete aggregate



ASTM C94: Standard specification for Ready-mix concrete



ASTM C150: Standard specification for Portland cement




ASTM C494: Standard specification for Chemical admixture for Concrete.



TCVN 1651:2008: Concrete reinforcement



Part III-2 Exhibit B1 Tech Spec Section 8.



Part III-2 Exhibit B1 Appendix G Civil/Structure Technical Guideline.

• VP1-0-EPC-H-GEN-10511-Health, Safety and Environment Plan
• VP1-C-L4-H-GEN-00003- HSE Risk Management
• VP1-C-L4-H-GEN-00005- HSE accident and incident
• VP1-C-L4-H-GEN-00009- Working at height
• VP1-C-L4-H-GEN-00012- Lifting operations
• VP1-C-L4-H-GEN-00020- Scaffolding
• VP1-C-L4-H-GEN-00024- Hot work
• VP1-C-L4-H-GEN-00026- Excavation
• VP1-C-L4-H-GEN-00027- Permit to work
- 3 - | Page

Rev B



VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

2.2 Drawing and Method Statement

3.



VP1-C-L4-C-HBA-17501_ Boiler excavation drawing.



VP1-0-L4-A-UYX-00201_ General Rebar Standards.



VP1-C-L4-C-HBA-17101_ Boiler foundation plan drawing.



VP1-C-L4-C-HBA-17102_ Boiler foundation section drawing



VP1-C-L4-C-HBA-17103_ Boiler foundation detail drawing



VP1-C-L4-C-HBA-17301_ Boiler foundation reinforcement drawing.




VP1-0-L4-C-GEN-10007_ Method statement for General concrete work.



VP1-0-L4-C-GEN-10008_ Method statement for Excavation and backfilling work.

MANPOWER & EQUIPMENT
• Manpower mobilized for construction of the Boiler are listed as followings:
No.

Position

Quantity

1

Site Manager

01

2

Site engineer

06

3


Safety supervisor

01

4

Surveyor

02

5

Crane operator

02

6

Roller operator

01

7

Worker

100

• Equipment mobilized for construction of the Boiler are listed as followings:

No.

Equipment

Unit

Quantity

1

Total station

nos

02

2

Auto level

nos

02

3

Crane

nos


02

4

Excavator

nos

02

4

Roller

nos

02

5

Rammer

nos

05

6

Plate compactor


nos

02

7

Cutting machine

nos

05

8

Bending machine

nos

02

- 4 - | Page

Remark

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT


9

Welding machine

nos

10

10

Concrete pump truck

nos

03

11

Concrete mixer truck

nos

12

12

Concrete vibrator

nos


12

13

Water pump

nos

05

14

Troweling machine

nos

01

15

Light

nos

20

4. RESPONSIBILITIES
• It is overall responsibility of Site Manager to organize resources prior to perform construction activities
as per project specification in compliance with the quality, schedule & safety requirements.
• EHS Manager will ensure in coordination with Site Engineer that all measure/construction taken shall be

maintained till completion of job.
• It is the responsibility of Construction Manager/Site Engineer that construction activities are executed
according to the relevant project specification in compliance with the quality, schedule & safety
requirements.
• Contractor will ensure that all works are performed safely according to the attachment.
• The relevant contractor Supervisor will ensure that the work is carried out in accordance with this method
statement and project specification.
• The QC Inspector will ensure that the work is executed according to the requirements of quality dossier
are fulfilled.

- 5 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

5. PROCEDURE AND SEQUENCE
General Plan



Due to the large dimension of foundation, detail of reinforcement, different of Bottom of foundation
contractor shall divide foundation into 07 stage to ensure safety condition and quality of concrete
(massive concrete): Vertical construction joint will be arranged between Stage [3], Stage [5], Stage
[6], Stage [7]; Isolation joint surround Stage [1], Stage [2], Stage [4].

Method statement for Fan


will be separate and submit late

- 6 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

1.3

1.2

1.4

1.1
1.5

B

1.6

1.7



The stage from 2 to 7 will be carried out to follow the schedule of Anchor Bolts installation,
Contractor will arrange enough manpower and equipment to conduct these stages. Besides,
the calculation of concrete supply has to prepare to make sure the eligible condition for cast

concrete.



Between each stage, the Hy-rib permanent formwork will be used to avoid crack and so forth
between construction joints.

- 7 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

B

Construction Stage 1: SCC, Oil sump: 04 Phase

- 8 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

Construction Stage 2, 3, 4, 5, 6: Massive concrete, Maximum thickness: 3m
• Vertical construction joint will be arranged between Stage [3], Stage [4], Stage [5], Stage [6] And
Massive concrete will be describing in section 6.6 Concrete work.

6. CONSTRUCTION WORK
6.1 Excavation and disposal
• The ratio 1:0.5 shall be applied for the slope of foundation, Typical section for excavation is shown in
picture below. Dimension of pit lager than dimension of foundation 2m for all direction for Scaffolding,
formwork.

B

Typical of dewatering for SCC sump
- 9 - | Page

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT



In case of heavy rain, Contractor will use some water pumps to dewater; in addition, making
trenches to collect water need to carry out. The layout of trench will be depended on the
actual condition on site, particularly, avoid obstructing other activities and easily collect water.

6.2 Lean concrete
• Subgrade of foundation must be well compacted unless surface is rock and cleaned up to ensure the
quality of lean concrete. Any marshy ground position must be removed and compacted by good material.
Lean concrete plan will depend on the construction step.
• Lean concrete thickness 50mm (as design drawing), grade: 15Mpa.

B


• Lean concrete is casted before next activities such as rebar or formwork installation.
6.3Reinforcement work
• Steel bars shall be stored on the site on racks or supports of sufficient height to keep the bars clear of
the ground and steel bar shall be covered by plastic sheet in order to prevent corrosion by the sea
environment.
• Bar bending schedule shall be submitted before commencement of work.
• Fabricating, installing foundation rebar comply with the approved design, project specification, ACI 117
and ACI 318, approved BBS. Lap splicing method shall be used for rebar connection, the lap length
shall comply with the approved design drawing and applied standard.
• Any kind of hot cutting and bending rebar shall not be allowed
• Fabricated rebar will be transported from the workshop to construction site by lorry crane.
• Rebar shall be erected such as to form a rigid cage within the formwork, with every intersection being
bound together with appropriate binding wire.
• Specified concrete cover shall be maintained by the use of precast concrete spacer blocks of the same
- 10 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

grade as the concrete in which they are to be used.
• Black annealed steel binding wire of 1mm thickness shall be used for fixing the reinforcing bars. The
binding wire will be double folded to ensure the firmness of the connection.
• Concrete spacer shall be made by same grade concrete as structural grade.
• In practicable, the subcontractor could use extra method such as steel tube frame, cables,
turnbuckles… to keep the rebar stable before carry out the next steps
• Inspection of rebar installation shall be conformed to design drawing and approved method statement,

such as grid space, lap length, elevation…



B

Support bars/rebar chairs are installed to make sure the enough safety and stable for rebar frame
against dead load of top rebar and live load of workers, equipment and casting concrete.

- 11 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

B

HANDRAIL

WORKING PLATFORM

DETAIL A
DETAIL A

TOP LAYER BAR

TUBE Ø48


1500

600

SUPPORT BAR

3000

SUPPORT BAR

B

600

600 3000 600

SIDE BAR

LEAN CONCRETE

250

1
0.5
BOTTOM LAYER BAR

SECTION

- 12 - | P a g e


Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

8
7

B

6
5

3

400

2

400

4

1

The order of casting concrete will be followed from 1 to 8
6.4 Installation of embedded plate, box out (if any)
• The embedded plate/box out shall be erected in the exact position as specified in the designed drawings.
• The characteristics of embedded items (supplied by Contractor) must confirm to specification, approved

design drawing such as type, size, and be approved before using
• Fixing method is suggested by wire tie and/or welding to fix stable anchoring frames. Welding to main
rebar is prohibited
• Typical method for installation is shown in figure below. (Method statement of Bolts installation will be

B

submitted by another contractor. Contractor will coordinate to IHI for this matter on site)
• Contractor must ensure the clean condition of embedded items, stability and firmness, position and
elevation, plumpness… before pouring concrete.

B

- 13 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

6.5 Formwork
• Formwork kind shall be considered as mass concrete curing method
• Forms shall conform to the shapes, lines and dimensions of the structure according to the drawings.
• The formwork shall ensure good finished surface of concrete, and shall be sufficiently firmly and tight
for the method of placing and compacting and for preventing loss of grout from the concrete.
• Prior to reuse formwork, all dust and mortar, debris on the surface shall be removed.
• Working platforms for inspection and erection shall be provided.
• Contractor is using total station leveling machine to remark the reference point which the formwork is
fixed. Check elevation of rebar grid and add the concrete spacer where necessary and make alignment

to proper elevation specified of FC drawings
• Install the concrete spacer to ensure the protection cover thickness are achieved, Concrete spacer shall
be made by same grade concrete as structural grade.
• Connecting the formwork panel by connection pins and clips. Checking elevation, position, and
plumpness of panels. Using the support pipes, steel-box, scaffold clips to fix the formwork
• Formwork must ensure close to prevent leakage of cement laitance at inspection time.
• Space of pipe support, tie rod is 800mm.
• In height of foundation h=3m, arrange 3 layers for Pipe support, 5 layers of tie rod.
• In height of foundation h=1.5m, arrange 2 layers for Pipe support, 3 layers of tie rod.

- 14 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

Typical formwork panel

- 15 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

Typical detail of formwork for Boiler foundation


B
BOTTOM LAYER BAR

DETAIL 1

The support bars must be bent and fixed with bottom layer bar

- 16 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

Please supplement the concrete
surface finishing method with
and/or without hardener

6.6 Concrete work

• Reference Method statement: “VP1-0-L4-C-GEN-10007_ Method statement for General concrete work”
for requirement and describe of concrete work.
• This method statement mention for construction joint, massive concrete.
6.6.1 Construction Joint.
• Horizontal Construction joint: The concrete surface shall be roughened by air-water jet, after it has
reached its final set but not more than 12 hours after its placing was completed, so as to expose the
aggregate. In the case of more than 12 hours, use a handheld device to chipping. When fresh concrete
is to be placed on set concrete, a layer of mortar (water and cement only) shall be applied by spray/brush
on the dry surface before the fresh concrete is placed.


The mortar shall contain the same proportions

of cement as the concrete mix.
• Vertical construction joint shall be place as picture below:
• Metal mesh will be installed, replace the formwork at construction joint. Support system for formwork in
construction joint same in other side. if conduit, angle steel, etc... going through construction joint, metal
mesh shall be made shape follow it.

- 17 - | P a g e

Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

• When pouring new concrete stage, do not dismantle metal mesh, it will lay inside of concrete permanent.
a layer of mortar (water and cement only) shall be applied by spray/brush on the dry surface before the
fresh concrete is placed.

The mortar shall contain the same proportions of cement as the concrete

mix.
• At top of rebar layer, Contractor will use formwork to make the construction joint, when casting concrete
next time, Contractor will chip the concrete to make rough surface.


- 18 - | P a g e


Rev B


VAN PHONG 1 BOT THERMAL POWER PLANT
PROJECT

6.6.2 Massive concrete.

a) Pouring concrete
Mass concrete center temperature shall not exceed 70℃ and must be less than 50℃ per meter
Difference of temperature in center and surface of the concrete not exceed 20℃. The method of curing

B

the concrete will be complied with item b (see below).
Contractor will send a technical service team to provide peak temperature and
differential temperature monitor during the foundation casting and construction process so
that timely technical data could be provided to control and minimize the risk of thermal
cracks.

The following guidelines shall be followed;
• Concrete slump shall conform to approved mix design
• Concrete temperature at pouring time shall not exceed 30°C
• Sampling from trucks shall be advised by the Engineer/As per Site Inspection and Test Plan.
• Concrete shall be placed in position using the pump and flexible hose shall be connected at the end of
the concrete pump by clamping. Such hose shall be placed inside the pouring area to control the height
of pouring the concrete, Contractor will make plan for location of hose through top rebar layer. Concrete
shall be placed 400mm horizontal layers till reaching the required height bottom.
• Concrete should be discharged smoothly in coordination between vibrating person and discharging
person. Side vibration on formwork will be used if necessary.

• Concrete should not be dumped in several locations at a time nor discharged in large hips and moved
horizontally until final position.
• The concrete casting shall be performed layer by layer, preventing the formation of cold joints. The
layers shall be separated with heights not greater than 2/3 of the vibrator length.

- 19 - | P a g e

Rev B


×