Tải bản đầy đủ (.pdf) (80 trang)

General report of frontage road and bridge - Mekong Delta Transport Infrastructure Development project (MDTIDP)

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (4.39 MB, 80 trang )

Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

1



CONTENTS
CONTENTS 1
TABLES LIST 3
FIGURES LIST 4
GENERAL SYMBOL 5
I. GENERAL INTRODUCTION 7
I.1
OVERALL ABOUT PROJECT 7
I.1.1
NATIONAL WATERWAY CORRIDOR NO. 2 (CORRIDOR 2)
7

I.1.2 NATIONAL WATERWAY CORRIDOR NO. 3 (CORRIDOR NO. 3)
8

I.2
BASIS FOR DESIGN 9
I.2.1
LEGAL BASIS
9

I.2.2


APPLICABLE CODES AND STANDARDS
10

II. NATURAL CONDITIONS 11
II.1
TOPOGRAPHICAL AND GEOMORPHOLOGICAL CONDITIONS 11
II.1.1
TOPOGRAPHICAL CONDITIONS OF CORRIDOR NO. 2
11

II.1.2
TOPOGRAPHICAL CONDITIONS OF CORRIDOR NO. 3
11

II.2
GEOLOGICAL CONDITIONS 12
II.2.1
OVERALL OUTLOOK ABOUT GEOLOGICAL ENGINEERING CONDITIONS
12

II.2.2
GEOLOGICAL ENGINEERING CONDITIONS OF CORRIDOR NO. 2
13

II.2.3
GEOLOGICAL ENGINEERING CONDITIONS OF CORRIDOR NO. 3
14

II.3
METEOLOGICAL – HYDROLOGICAL CONDITIONS 15

II.3.1
METEOLOGICAL CONDITIONS
15

II.3.2
WATER TABLE
17

III. STATUS OF CURRENT ROADS AND SCOPE OF REPLACEMENT
CONSTRUCTION 20
III.1
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT
CORRIDOR NO 2 20
III.2
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT
CORRIDOR NO 2 21
III.3
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT
CORRIDOR NO 3 21
III.4
THE STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT
CORRIDOR NO 3 22
III.4.1
STATUS OF BRIDGE NO 1 UNDER NW12 PACKAGE, CORRIDOR 3
24

III.4.2
STATUS OF BRIDGE NO 2 UNDER NW12 PACKAGE, CORRIDOR 3
24


III.4.3
STATUS OF BRIDGE NO 3 UNDER NW12 PACKAGE, CORRIDOR 3
25

III.4.4
STATUS OF BRIDGE NO 4 UNDER NW12 PACKAGE, CORRIDOR 3
25

III.4.5
STATUS OF BRIDGE NO 5 UNDER NW13 PACKAGE, CORRIDOR 3
26

III.4.6
STATUS OF BRIDGE NO 6 UNDER NW13 PACKAGE, CORRIDOR 3
27

III.4.7
STATUS OF BRIDGE NO 7 UNDER NW13 PACKAGE, CORRIDOR 3
27

III.4.8
STATUS OF BRIDGE NO 8 UNDER NW13 PACKAGE, CORRIDOR 3
28

III.4.9
STATUS OF BRIDGE NO 9 UNDER NW13 PACKAGE, CORRIDOR 3
28

III.4.10
STATUS OF BRIDGE NO 10 UNDER NW13 PACKAGE, CORRIDOR 3

29

III.4.11
STATUS OF BRIDGE NO 11 UNDER NW13 PACKAGE, CORRIDOR 3
29

III.4.12
STATUS OF BRIDGE NO 12 UNDER NW13 PACKAGE, CORRIDOR 3
30

III.4.13
STATUS OF BRIDGE NO 13 UNDER NW13 PACKAGE, CORRIDOR 3
30

III.4.14
STATUS OF BRIDGE NO 14 UNDER NW13 PACKAGE, CORRIDOR 3
31

III.4.15
STATUS OF BRIDGE NO 15 UNDER NW13 PACKAGE, CORRIDOR 3
31

III.4.16
STATUS OF BRIDGE NO 16 UNDER NW13 PACKAGE, CORRIDOR 3
32

III.5
THE STATUS OF DRAINAGE CULVERTS AND DITCHES ALONG ROADS 32
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2

General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

2
III.6
COMMENTS AND EVALUATION ON THE CURRENT STATUS 32
III.7
SCOPE OF REPLACEMENT BRIDGES 32
IV. DESIGN SOLUTION 38
IV.1
WORKS GRADE 38
IV.2
TECHNICAL STANDARDS OF TRAFFIC ROADS 38
IV.2.1
GENERAL PARAMETERS
38

IV.2.2
DESIGNED LOAD 38

IV.2.3
LEVEL OF ROAD SURFACE
39

IV.2.4
CROSS SECTION OF FRONTAGE ROADS
40

IV.2.5
ROAD PAVEMENT STRUCTURES FROM TOP DOWNWARD

40

IV.3
TECHNICAL SPECIFICATIONS OF RURAL BRIDGES 43
IV.3.1 GROUP OF BRIDGES TYPE A
43

IV.3.2
BRIDGES TYPE B
46

IV.3.3
BRIDGES TYPE C GROUP
49

IV.3.4
BRIDGES TYPE D GROUP
52

IV.3.5
BRIDGES TYPE E GROUP
55

IV.4
TECHNICAL SPECIFICATIONS OF DRAINAGE SYSTEM 57
IV.4.1 TECHNICAL SPECIFICATIONS OF DRAINAGE TROUGH
57

IV.4.2
TECHNICAL SPECIFICATIONS OF DISCHARGE CULVERT

59

IV.4.3
EXECUTION METHOD
62

IV.5
TRAFFIC ASSURANCE. 63
IV.5.1
ROADWAY TRAFFIC.
63

IV.5.2
WATERWAY TRAFFIC.
63

IV.6
CONSTRUCTION MATERIALS – TECHNICAL SPECIFICATION 64
IV.7
GENERAL NOTES 65
V. APPENDIX 66





Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :


3


TABLES LIST

Table II.1: Frequency of water table hour - (2000 – 2009) over corridor no. 2 17
Table II.2: Frequency of water table hour - (2000 – 2009) over corridor no. 3 18
Table III.1: The status of current roads that must be demolished and cleared at corridor
No 2 20
Table III.2: The status of current roads that must be demolished and cleared at corridor
No 3 21
Table III.3: The number of demolished bridges 23
Table III.4: Details of demolished bridges and proposed bridges 33
Table IV.1: The level of traffic roads on anti-flood dike peak inn the Southern bank of
Nguyen Van Tiep canal 39
Table IV.2: comparisons and conclusions design top level combines public roads 40
Table IV.3: Quantity of rural roads need to be refurbished for corridor no. 2 41
Table IV.4: Quantity of rural roads need to be refurbished for corridor no.3 41
Table IV.5: Drainage ditch of pavement building replacement corridor 2 58
Table IV.6: Drainage ditch of pavement building replacement corridor 3 58
Table IV.7: Summary table of culvert through the corridor 2 59
Table IV.8: Summary table of culvert through the corridor 3. 61
Table IV.9: Comparison of quantity of excavated and filled soil. 62
Table V.1: NW9 corridor 2: coordinates of cross section of frontage roads 66
Table V.2: NW10 corridor 2: coordinates of cross section of frontage roads 66
Table V.3: NW12 corridor 3: coordinates of cross section of frontage roads 72
Table V.4: NW13 corridor 3: coordinates of cross section of frontage roads 75




Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

4

FIGURES LIST

Figure I-1: Map of corridor no. 2 7
Figure I-2: Map of corridor no. 3 – Stage 2 9
Figure II-1: Arrangement diagram of water table monitoring stations – corridor no. 2 17
Figure II-2: Arrangement diagram of water table monitoring stations – corridor no. 3 18
Figure III-1: Bridge No 18-Xang Don bridge 21
Figure III-2: Bridge No. 1 - Cong Xi Ruu bridge 24
Hình III-3: Bridge No.2 – Kham Tam bridge 25
Figure III-4: Bridge No. 3-Mr/Ms Trang Thuy bridge 25
Figure III-5: Bridge No. 4-Tra Kha bridge 26
Hình III-6: Bridge No. bridge 5 - Dan Xay 02 bridge 26
Figure III-7: Bridge No. 6- Huynh Cong Bang arch bridge 27
Figure III-8: Bridge No. 7-Nguyen Thanh Ky arch bridge 27
Figure III-9: Bridge no. 8- Cai Tram 02 bridge 28
Figure III-10: Bridge no. 9- Mr. Luc bridge 28
Figure III-11: Bridge No. 10-Son Tranh bridge 29
Figure III-12: Bridge No. 11- Quoc Truong bridge 29
Figure III-13: Bridge No.12- Ms. Van bridge 30
Figure III-14: Bridge No.13-Son Lam bridge 30
Figure III-15: Bridge No. 14- Vinh My bridge 31
Figure III-16: Bridge No. 15- Nam Nghi bridge 31

Figure III-17: Bridge No. 16- Hai Trai bridge 32
Figure IV-1: Load for non-motorized vehicles 38
Figure IV-2: Typical cross section of frontage roads 40
Figure IV-3: Longitudinal section of bridges type A 43
Figure IV-4: Cross section of bridges approach roads type A 45
Figure IV-5: Longitudinal section of bridges type B 46
Figure IV-6: Cross section of bridges approach roadstype B 48
Figure IV-7: Longitudinal section of bridges type C 49
Figure IV-8: Cross section of bridges approach roads type C 51
Figure IV-9: Longitudinal section of bridges type D 52
Figure IV-10: Cross section of road 54
Figure IV-11: Longitudinal section of bridges type E 55
Figure IV-12: Cross section of road 57


















Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

5





GENERAL SYMBOL
Symbol

Remark
NW8
:
The parkage for the corridor no. 2 From Km0+000 to Km37+000
NW9
:
The parkage for the corridor no. 2 From Km37+000 to Km50+500
NW10
:
The parkage for the corridor no. 2 From Km50+000 to Km80+000
NW11
:
The parkage for the corridor no. 3 From Km207+000 to Km248+500
NW12
:
The parkage for the corridor no. 3 From Km248+500 to Km290+000

NW13
:
The parkage for the corridor no. 3 From Km290+000 to Km310+000
BER
BTCT
:
:
The bid eluavation report
Reinforcemnt concrete
Consultants
:
Consultant contracter DHV BV
CSM
:
Construction Supervision Manual
DOT
:
Transportation department
EA
:
Execution Agency
EIA
:
Environmental Impact Assessment
EMP
:
Environmental Monitor Plan
EMP
:
Environmental Management Plan

EP
:
Environmetal Plan
FS
:
FEASIBILITY STUDY
GoV
:
Government of Viet Nam
GPS
:
Global Positioning System
HCMC
:
Ho Chi Minh City
ICB
:
International Competitive Bidding
LCB

Domestic Competitive Bidding
IMA
:
Independent Monitoring Agency
IWT
:
Inland waterway transportation
MARD
:
Ministry of Agriculture and Rural Development

MDTIDP
:
Mekong Delta Transport Infrastructure Development project
ME
:
Monitoring and Evaluation
MOM
:
Minutes of Meetings
MOT
:
Ministry of Transport
MTR
:
Mid-Term Review, mission of the World Bank
NW
:
Package
OM
:
Operation and Maintenance
PM
:
Project Manager
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

6

PMU-SIW
:
Project Manager Unit of Southern Inland Waterways
PP
:
Kế họach đấu thầu
PPC
:
Ủy ban nhân dân tỉnh
RCC
:
Reinforced cement concrete
RP
:
Resettlement Plan
TOR
:
Terms Of Reference
VAPO
:
Vietnam Association of Port - Waterway - Offshore Engineering
VESDI
:
Vietnam Enviroment & Sustainable Development Institute
VIWA
:
Vietnam Inland Waterway Administration
WB
:
World Bank

HHWL
:
Highest water level
HWL
:
High Water Level
LW
:
Mean level
LWL
:
Low Water Level
ND
:
National Datum
Max.
:
Maximum
Min.
:
Minimum
mm
:
Millimeter (s)
m
:
Meter (s)

Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2

General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

7
I. GENERAL INTRODUCTION
I.1
OVERALL ABOUT PROJECT
Mekong Delta Transport Infrastructure Development Project MDTIDP - (Project WB5) conducted by
Vietnamese Government under sponsorship of World Bank (WB). The project shall comprise of four integral
parts as follows:
 Integral part A: Investment for national roads.
 Integral part B: Investment for national waterway corridors.
 Integral part C: Investment for provincial road networks and local waterways.
 Integral part D: Technical assistance given to Ministry of Transportation and provinces included in
Mekong delta region.
Of integral part B – Investment for national waterway corridors in Mekong Delta region shall comprise of
Local waterway corridor no. 2 (Corridor 2) and Local waterway corridor no. 3 (Corridor 3), where:
 Stage 1 of integral part B it is ongoing with investment and construction of Local waterway corridor no.
2 (Corridor 2) for section from Km80+00 to Km253+00, of construction and erection packages i.e.
NW1; NW2; NW3 and NW4.
 Stage 2 of integral part B shall be about design consultancy for improvement of remaining section of
corridor 2 from section Km000+000 to Km80+000 and end section of corridor 3 from section
Km207+000 to Km310+000, of packages i.e. NW8; NW9 etc.
I.1.1
NATIONAL WATERWAY CORRIDOR NO. 2 (CORRIDOR 2)

I.1.1.1 Scope of local waterway
 Start point: Start from Ho Chi Minh city at KM 0+000
 End point: At KM 253+000 – Vam Ray (At junction of Rach Gia Ha Tien canal and Tam Ngan canal).
 Length of section shall account for 253km. Construction site: Ho Chi Minh City, provinces: Long An,

Tien Giang, Dong Thap, An Giang and Kien Giang.

Figure I-1: Map of corridor no. 2

 This corridor shall crosses some major canals such as Kenh Te, Kenh Doi, Cho Dem Ben Luc river,
Vam Co Dong river, Thu Thua canal, Vam Co Tay river, Rach Chanh creek, Nguyen Van Tiep canal
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

8
(Thap Muoi no. 2 canal), Tien river, Vam Nao river, Hau river, Tri Ton Hau Giang canal, Tam Ngan
canal connecting to Rach Gia Ha Tien canal. Total waterway length of this section shall account for
253km. Waterway transport system over corridor no. 2 shall comprise of 4 sections as follows:
 Section connecting Sai Gon river with Vam Co Dong river from KM 0+000 to KM 32+000 with total
length of 32km which shall across Te canal, Doi canal, and Cho Dem Ben Luc river.
 Section connecting Vam Co Dong river with Vam Co Tay river from KM 32+000 to KM 51+120 with
total length of 19.12km over Vam Co Dong river, Thu Thua canal and Vam Co Tay river.
 Section connecting Vam Co Dong river and Tien river from KM 51+120 to KM 143+800 with total
length of 92.68km over Rach Chanh creek, Nguyen Van Tiep canal to Tien river.
 Section connecting Tien river and Hau river from KM 143+800 to KM 190+000 with total length of
46.20km over Cu Lao Tay branch river – Vam Nao river – Hau river.
 Section connecting Hau river to Rach Gia Ha Tien canal from KM 190+000 to KM 252+700 with total
length of 62.70 km over Tri Ton Hau Giang canal and Tam Ngan canal.
The all line shall be upgrade and expanded to to meet the technical standards for inland waterway
class III
I.1.1.2 Construction scale of resident roads and rural roads in corridor 2 – phase 2
NW8: Commenced point at Km000+000 and end point at Km37+000 (as per alignment of waterway),
total length shall be of 37.0km, total length subject to site clearance shall be from Km18+000 to

Km32+500. There shall appear no traffic roads and bridges for rural transport system which shall
be damaged during dredging works.
NW9: Commenced point at Km37+700 and end point at Km50+700 (as per alignment of waterway),
total length shall be of 13.5km, total length subject to site clearance shall be from Km40+700 to
Km46+800 of which from Km42+400 – Km43+300 which shall subject to dredging and
destruction of road along right bank (north bank) with total length of resident roads refurbished
shall be of 594.54m
NW10: Commenced point at Km51+800 and end point at Km80+000 (as per alignment of waterway),
total length shall be of 28.2km,
Total length subject to site clearance shall be from Km51+800 to Km80+000 of which from Km58+250 –
Km68+650 which shall subject to dredging and destruction of roads and bridges along left bank
including one resident bridge which shall be refurbished and with total length of resident roads
refurbished shall be of 9617.38m.
I.1.2 NATIONAL WATERWAY CORRIDOR NO. 3 (CORRIDOR NO. 3)

I.1.2.1 Scale of local waterway
Corridor no. 3 shall have total length of 450km, starting from Ho Chi Minh city crossing some regions i.e.
My Tho – Tra Vinh – Ca Mau – Rach Soi and ending at Thailand gulf. This corridor shall be parallel to
coastal strip toward the south which shall cross Ca Mau province, then further developing to the north of
Rach Gia.
For stage 2, construction shall be undertaken for section connecting from Hau river to Ca Mau crossing
Dai Ngai creek, Phu Huu Bai Xau canal, Du Tho river, Co Co river, Vam Leo Bac Lieu river, Bac Lieu Ca
Mau canal to Ca Mau and connecting to Ganh Hao river. Of which section from Bac Lieu Ca Mau canal
to Ganh Hao river shall account for about 7km which have been dredged included in Project of
upgrading of two waterways routines i.e. the southern waterway and Can Tho harbor. Total design
length of stage 2 of corridor no. 2 shall be of 103km.

The all line shall be upgrade and expanded to to meet the technical standards for inland waterway
class III
Mekong Delta Transport Infrastructure Development project (MDTIDP)

Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

9

Figure I-2: Map of corridor no. 3 – Stage 2
I.1.2.2 Construction scale of resident roads and rural roads in corridor 3 – phase 2
NW11: Commenced point at Km207+000 and end point at Km248+500 (as per alignment of waterway),
total length shall be of 41.5km, total length subject to dredging shall be from Km220+500 to
Km238+000. There shall appear no traffic roads and bridges for rural transport system which
shall be damaged during dredging works.
NW12: Commenced point at Km248+500 and end point at Km290+000 (as per alignment of waterway),
total length shall be of 41.5km, total length subject to dredging shall be from Km264+500 to
Km290+000; total length subject to site clearance shall be from Km285+400 – Km290+000.
Commenced point at Km282+500 to the end at Km287+575, Bac Lieu province has the project
tittled “Embankment on the two sides of Bac Lieu river. If this project is conducted before WB5
project, pedestrian roads along this section will not necessarily re-built because WB5 project lies
in the area of the Embankment project.
Accordingly, the scope of construction for pedestrian roads will be the construction of 2,479 m of
pedestrian roads and re-building of 2 padestrian bridges.
Because the clearance area lies on the Southern bank and big funding requirement for
“Embankment on the two sides of Bac Lieu River” project, Bac Lieu province currently has
insufficient funding. The duration for the embankment project is not clearly fixed, especially when
the Southern bank is allowed by the province to be complete later than the Northern bank.
Therefore, in the design report for WB5 project, re-construction of bridges and roads is still
mentioned. The scope of construction for pedestrian bridges from Km282+500 to Km287+575
will be:
From Km285+400 – Km290+000 at left bank (south bank), including 05 rural bridges to rebuild
and total length of resident roads refurbished shall be of 3.823km;

NW13: Commenced point at Km290+000 and end point at Km310+000 (as per alignment of waterway),
total length shall be of 20.0km, total length subject to dredging shall be from Km290+000 to
Km309+750 of which from Km290+000 – Km301+000 which shall subject to dredging and
destruction of roads and bridges along left bank including 11 resident bridges which shall be
refurbished and with total length of resident roads refurbished shall be of 8.380km.
I.2
BASIS FOR DESIGN
I.2.1
LEGAL BASIS
 Pursuant to Law of Construction no. 16/2003/QH11 dated 26/11/2003 promulgated by National
Assembly;
 Pursuant to Decree no. 12/2009/ND-CP dated 10/02/2009 issued by the Government in regard of
management of investment and construction of works;
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

10
 Pursuant to Decree no. 209/2004/ND-CP dated 16/12/2004 in regard of management of quality of
construction works;
 Base on Decision no. 741/QD-BGTVT dated 06/4/2007 issued by Ministry of Transport for its approval
of Mekong Delta Infrastructure Development Project.
 Base on bidding assignment contract namely “Consultancy service for surveying and design, stage 2”
included in Mekong Delta Infrastructure Development Project dated 9/5/2007 between Management
Board of waterway project (PMUW) and DHV.BV (Netherland);
 Base on bidding assignment contract namely “Consultancy service for surveying and design, stage 2”
included in Mekong Delta Infrastructure Development Project no. …. dated … /2010 in between
DHV.BV (Netherland) and Hong Hung Consultancy and construction Co., Ltd.;
 Base on Feasibility Study report prepared by Louis Berger Group, Inc. in cooperation with ROYAL

HASKONING for Mekong Delta Infrastructure Development Project – by June 2006.
 Base on design document for dredging works of shipline performed by Hong Hung Consultancy and
construction Co., Ltd. In January 2011.
I.2.2
APPLICABLE CODES AND STANDARDS

Application of standard system which have been approved by Ministry of Transportation via. Decision no.
2406/QD-BGTVT dated 9/11/2006 regarding approval of “Standard system applicable to design investigation
for project WB5”. Of which standards are applied to design of dredging works, resident roads and bridges
shall consist of:
 Vietnam Construction Codes.
 Vietnam construction standards book.
 Standard TCVN 5664 - 1992 about Technical classification of Vietnam waterway issued in connection
with Decision no. 347/QD of the State Science Committee dated 23.05.1992.
 Standard TCVN 5664 - 2009 about Technical classification of Vietnam waterway issued in connection
with Decision no. 3082/QD-BKHCN of the State Science Committee dated 31.12.2009.
 Technical standard for traffic works.
 Standard TCVN 4447 : 1987 about Earthwork – Code of construction and acceptance
 Design standard for traffic roads in rural areas 22TCN 210-1992.
 Piling foundation – Design standard TCVN 205-1998.
 Design standard for bridge 22TCN 272-05.
 Design standard for structures and steel reinforcement concrete TCXDVN 356-2005.
 Regulations on roadway signs/warnings 22TCN 237-01.
 Regulation on signs of Vietnam local waterway 22TCN 269-2000.
 Decision no. 11/2005/QD-BGTVT dated 17/01/2005 issued by Minister of Transportation regarding:
“Amendment and supplement of sectional standard 22TCN 269-2000”.
 Design procedure for soft road pavement 22TCN 211-06.
 Design standard for truck road TCVN 4054-2005.
 Procedure for construction and acceptance of prestressing truck bridges beams 22TCN 247-98.
 Standards for roadway 22TCN 273-01.

Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

11
II. NATURAL CONDITIONS
II.1
TOPOGRAPHICAL AND GEOMORPHOLOGICAL CONDITIONS
General description of the topography of the two corridors is given specifically in the Description on
dredging design. In this description on pedestrian roads, only topographical and geomorphological
features at river and canal sections that need site clearance and re-construction of previous roads are
given.
II.1.1
TOPOGRAPHICAL CONDITIONS OF CORRIDOR NO. 2
Waterway corridor No 2 is divided into sections, depending on the location and is specifically described
as bellows:
Section NW8. From Km00+000 to Km37+000 – Te canal
 Km00 is the location where Te canal connects with Sai Gon river leading to Doi canal, Tau Hu canal,
Cho Dem river, Ben Luc river to Vam Co Dong river. This section is dredged and cleared. However,
this section does not contain any pedestrian roads, just some temporary ways that are not considered
to be as roads. Moreover, this section will be built with anti-tide dikes. Therefore, no pedestrian roads
will be formed here.
Section NW9. From Km37+000 to Km50+700 - Thu Thua canal
 Ending part crossing Vam Co Tay river. It shall be in Thu Thua district – Long An province. It shall be
densely covered with resident houses and works along both banks in Thu Thua town area, apart from
this there shall be quite low densed coverage of houses and construction works. There shall be many
wild coconut trees in some parts along both banks of canal. This part of canal shall be in rural area,
there shall have areas for rice feeding, farming. Several rural roads appear along both banks.
 Width of river shall be varies in within (45 - 55)m, average bottom level shall be about from -3.00m to -

5.0m, quite straight and no bending parts of routine can be encountered.
 There appear several berths for goods intaking and ships. Some parts shall have embankment. There
shall be 3 over-river bridges, underground works and power wiring over river.
 Clearance and construction of traffic roads will be within Northern bank. Currently, there is a road
route from Km42+410 to Km43+273 running along the canal edge over a length of 863 m. The width
of this road is 2,0 m on average. The average level of the surface is between +1,8 to +2,4m
 Current structure of the road is soil structure
 There is a traffic road whose structure is illustrated in Chapter 3 of this report.
Section NW10. From Km50+800 to Km80+000.
 Not too many resident houses and construction works along both banks. There shall be many traffic
roads in some parts along both banks of canal. This part of canal shall be in rural area, there shall
have areas for rice feeding, farming. Several rural roads appear along both banks. National road shall
be located on the north bank of canal.
 Width of river shall be varies in within (42 - 55)m, average bottom level shall be about from -3.00m to -
4.5m, quite straight and no bending parts of routine can be encountered.
 The area for site clearance is located in the Southern bank. Dikes and traffic roads within this area can
be summarized as follow:
 Average width of the traffic road is 2.0 m and of dike surface being 2.5 m;
 The level of dike peak is from +1,6 to +3,2m;
 Current roads are of soil structure.
 Materials for dike embankment are soil in the local area
 There are 6 bridges. Two of them must be re-built.
II.1.2
TOPOGRAPHICAL CONDITIONS OF CORRIDOR NO. 3

Waterway corridor No 3 is divided into sections, depending on the location and is specifically described
as bellows:
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13

Paper :

12
Section NW11. The starting point is at Km207+000 and the end point is at Km248+500 (according to
the waterway station), making a total length of 41,5km;
 No need to re-construction of traffic along this section;
Section NW12. The starting point is at Km248+500 and the end point is Km290+000; (according to the
waterway station), making a total length of 41,5km;
 Area that needs site clearance is mainly close to and within Bac Lieu city
 In Bac Lieu city, houses are built densely along two banks of canals. On-land location has the level of
1.5m with lots of dikes and on-water houses
 The area for site clearance is located in the Southern bank. Dikes and traffic roads within this area can
be summarized as follow:
 Average width of traffic roads is 2,0 m and that of sike surface being 3,0 m;
 The level of road surface is from +1,6m to +2,0m;
 Roads are of aggregate crushed stone
 Materials for road filling are soil in the local area
 There are 6 bridges. Five of them must be re-built.
Section NW13. The section commences from Km290+000 and the end point is at Km310+000, making
a total length of 20,0 km.
 This shall be end section of stage 2 (Km310). Canal shall have width of 40 – 60m. Average bottom
level shall be varies from - 3,50m to – 2,50m, low density of floral coverage over both river banks. This
part of canal shall be in rural area, there shall have areas for rice feeding, farming. There shall be one
rural roadway along canal in the southern bank. National roadway no. 1 shall be parallel with the
northern bank and in adjacent at some parts of canal.
 High density of houses and buildings along both canal banks, at locations without resident houses
shall be in vicinity with National roadway no. 1 and rural roads. Topography on the banks shall have
average level of 1.5m. There appear several embankments, berths and houses over river face; This
section shall have some over-river bridges. As per design alignment of this shipline, rural roads and
bridges must be refurbished

 Dredged channel length From Km290+000 to Km309+750.
 Repaid building of rural roads From Km290+000 – Km301+000 in the left bank, and total length of
rural roads must be repaid is 8.380km
 The status of rural road can be summarized as follows
 Average pavement width is 2,0m; of dike is 3,0m;
 Road surface elevations From +1,5m to 2,0m;
 The structure of pavement is asphalt concrete
 Filling material is soil
 Total resident bridge of this section is 13 bridges , in which to rebuild 11 bridges.
II.2
GEOLOGICAL CONDITIONS
II.2.1
OVERALL OUTLOOK ABOUT GEOLOGICAL ENGINEERING CONDITIONS

Geological investigation works utilized for design works of shipline for corridors 2 and 3 shall be carried out
in accordance with following scales:
 Bore holes for shipline shall be performed at an average interval of 1.000m. Bore holes located in high
bank shall be at an average interval of 1000m which shall be located alternately with bore holes of
shipline (average interval of 500m of bore hole under water or over the banks).
 Bore holes’ depth of shipline shall be of 7m and of 15m for high bank. At locations where appear near-
river construction works, at convex parts of river and canal banks with bending radius of less than 300
shall subject to further investigation with shipline bore holes of 10m deep and 20m for high bank bore
holes.
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

13
 The field penetration test shall be performed in alternatively with locations of probe drillings. Total of

264 points shall be applied for SPT tests.
 Along probe drilling soil sample shall be taken for every 2m for soil physical properties analysis for 09
criteria.
 Testing criteria shall comprise of:
+ Grain size/composition.
+ Natural moisture content - W (%).
+ Natural density -

w (g/cm3).
+ Dry density -

c (g/cm3).
+ Density -

(g/cm3).
+ Saturation - G (%).
+ Porosity - n (%).
+ Porosity index - e.
+ Tensile strength - Wch (%).
+ Adhesive strength - Wd (%).
+ Plastic index - Id (%).
+ Consistency - B.
+ Adhesive force - C (Kg/cm2).
+ Internal friction angle -

(deg.).
+ Respose angle of sandf -

(dry and saturated).
+ Compressibility coefficient - a1-2 (cm2/Kg).

+ Deformation module - E1-2(Kg/cm2).
+ Natural shear strength T(Kg/cm2).

II.2.2
GEOLOGICAL ENGINEERING CONDITIONS OF CORRIDOR NO. 2
Quantity for geological investigation shall include probe drilling and field shear vane test:
 Probe drilling for shipline 65 bore holes with designation from HKL-01 to HKL-66, drilling depth shall
be varies from 5m to 7m.
 Probe drilling for high bank 61 bore holes with designation from HKB-01 to HKB-66, drilling depth shall
be varies from 10m to 15m.
 Number of locations for shear vane test at clay substrates shall comprise of 84 points.
 Formations of geological terrains if surveyed area shall be young sediments at ages of Holocen and
Pleistocen, including soil layers and scopics as follows:
 Layer 1: Clay mixed with organic matter (OH) dark grey, blue grey, in melting conditions, this layer
shall take large part of substrates of investigation extent, distributed from surface of natural
topography; soil shall have main composition of powder clay. This shall be weak soil layer, hence,
special care shall be taken in design, execution and construction of works.
 Layer 2: Plastic clay (CL), white grey, blue grey, soft stiff status. This layer locally distributed over the
entire area with moderate to weak physical properties.
 Layer 3: Clay mixed with fine sand (CL), red brown, yellow brown, blue grey, stiff to hard status. This
layer shall be evenly distributed over the entire area with quite good physical properties.
 Layer 4: Fine sand mixed with high content of clay (SC), white grey, blue grey, poor to moderate
compacted density. This layer shall locate in the lowermost part of substrates and lightly over the
surveyed area with moderate physical property.
 Furthermore, there appear quite restricted thin scopics of plastic clay mixed with fine sand, gravel
including 2a, 3a, 3b.
 Underground water table included in the surveyed area distributed at depth of 0.3m/0.6m from existing
ground surface. Standing water and underground water shall be all corrosive to concrete and metal.
 As per length of entire area, based on geological extent, topographical condition and geological
engineering investigation results. Surveying alignment shall be divided into 6 sections as follows:

Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

14
 Section 1 – HL2: Te and Doi canals with total length of about 12.5km (from Km0 to Km 12+500).
 Section 2 – HL2: Cho Dem Ben Luc canal with total length of about 20.5km (from Km 12+500 to Km
33).
 Section 3 – HL2: Vam Co Dong river with total length of about 4.3km
 Section 4 – HL2: Thu Thua canal with total length of about 10.8km (from Km 37+250 to Km 48+000).
 Section 5 – HL2: Vam Co Tay river with total length of about 5km.
 Section 6 – HL2: Rach Chanh creek – Nguyen Van Tiep canal with total length of about 27 km (from
Km 53+000 to Km 80+000).
II.2.3
GEOLOGICAL ENGINEERING CONDITIONS OF CORRIDOR NO. 3
Quantity for geological investigation shall include probe drilling and field shear vane test:
 Probe drilling for shipline 65 bore holes with designation from HKL-01 to HKL-66, drilling depth shall
be varies from 5m to 7m.
 Probe drilling for high bank 61 bore holes with designation from HKB-01 to HKB-66, drilling depth shall
be varies from 10m to 15m.
 Number of locations for shear vane test at clay substrates shall comprise of 89 points.
 Formations of geological terrains if surveyed area shall be young sediments at ages of Holocen,
including soil layers and scopic as follows:
 Layer 1: Plastic clay mixed with organic matter (OH) dark grey, blue grey, in melting conditions, this
layer shall take large part of substrates of investigation extent, distributed from surface of natural
topography; soil shall have main composition of powder clay. This shall be weak soil layer, hence,
special care shall be taken in design, execution and construction of works.
 Scopic 1b with composition of extreme plastic clay mixed with organic matters (OH), soft and plastic
status evenly distributed at upper part of layer 1. At starting end of alignment scopes shall have

thickness which shall be varies from 0.5m to 2.5m, middle and ending part of alignment shall have
average thickness of 0.5m.
 Fine sand scopics including 1a (SC-SM) and 1c (SC) shall be distributed rarely at starting parts of
alignment.
 Layer 2: Plastic clay mixed with fine sand (CL), plastic soft status shall be limited in some bore holes
at the central of alignment (section 5).
 Underground water table included in the surveyed area distributed at depth of 0.3m/0.6m from existing
ground surface. Standing water and underground water shall be all corrosive to concrete and metal.
 As per length of entire area, based on geological extent, topographical condition and geological
engineering investigation results. Surveying alignment shall be divided into 8 sections with their length
shall vary from 8km to 24km as follows:
 Section 1 – HL3: Dai Ngai creek and Phu Huu – Bai Xau canal (Dai Ngai gate – Tan Thanh bridge)
with total length of about 13 km (from Km 207 to Km 220).
 Section 2 – HL3: Phu Huu – Bai Xau canal (Tan Thanh bridge to Thanh Loi bridge) with total length of
about 9 km (from Km 220 to Km 229).
 Section 3 – HL3: Dua Tho creek (from Tan Thanh bridge to junction of Nhu Gia – Ba Xuyen creek)
with total length of about 8 km (from Km 229 to km 237).
 Section 4 – HL3: Ba Xuyen creek (from Dua Tho creek to Co Co junction) with total length of about 9.5
km (from Km 237 to Km 246.5).
 Section 5 – HL3: Co Co river (from junction of Co Co river to Vam Leo river) with total length of about
17.5 km (from Km 246.5 to Km 264).
 Section 6 – HL3: Bac Lieu canal to Vam Leo (from junction of Co Co river toward Bac Lieu) with total
length of about 8.6 km (from Km 264 to Km 273).
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

15
 Section 7 – HL3: Bac Lieu canal to Vam Leo (further crossing Bac Lieu city to Tra Kha) with total

length of about 13.66 km (from Km 273 to km 286).
 Section 8 – HL3: Bac Lieu canal to Ca Mau (from Tra Kha to Gia Rai) with total length of about 24 km
(from Km 286 to Km 310).
II.3
METEOLOGICAL – HYDROLOGICAL CONDITIONS
II.3.1
METEOLOGICAL CONDITIONS
Documents collected from the Southern Meteological and Hydrological Station shall indicate major features
about meteology of construction site as follows:
II.3.1.1
Air temperature

Annual average temperature shall be account for 27.1
o
C; high peak one of 34.7
o
C, low peak one of 18.6
o
C;
The hottest month shall be May and the coldest month shall be January. There shall be not so high variation
of annual average temperature (from 26.8
o
C to 27.2
o
C). Peak temperature shall be varies from 34.0
o
C to
40.0
o
C and low peak temperature shall be varies from 14.8

o
C to 19.7
o
C. There shall be three periods in
within a year:
+ From January to April: Temperature is drastically increased during this period. Average increasing in
air temperature shall be from (25 ÷ 26)oC to (28 ÷ 29)oC.
+ From May to November: Temperature is stable during this period. Air temperature shall be lightly
decreased from (28 ÷ 29)oC down to (26 ÷ 27)oC.
+ From June to January of year after: Temperature is drastically decreased during this period. Average
decreasing in air temperature shall be from (26 ÷ 27)oC down to (25 ÷ 26)oC.
II.3.1.2 Evaporation from ground surface
Annual average evaporation shall be of 1.000 ÷ 1.400 mm, maximum rate within the year shall be of 1.414
mm. Evaporation shall reach to 91.8 ÷ 143.4mm during months of dry season and 49.8 ÷ 90.9 mm during
rainy season.
II.3.1.3 Sunny hours in within the year
During months of dry season from November to May it shall exceed 200 hours/month. The least sunny
months shall be of June and September equivalent to two peaks of rainfall and cloudy time. Average annual
sunny hours in the year shall be of 2551 hours.
II.3.1.4 Air humidity
Humidity regime shall have close relation to rain regime and wind regime in the region. Months with the
highest average humidity shall be May (31,1 mb), and the lowest month shall be January (24,5 mb).
Average annual humidity shall be 28.4 mb. The lowest relative humidity shall be of 21% (February 1974)
and the highest one 100% (in each month), average humidity shall reach to 78%.
II.3.1.5 Rainy regime
Wind recovery regime has been traced yearly into two main season i.e. rainy and dry season, dry season
shall be coincident with monsoon season.
+ Rainy season shall be coincident with the Southwest wind regime, rainfall shall be concentrated for
over 90% of total annual rainfall. Total average annual rainfall shall be varies from 1.455 ÷ 2.007mm.
The annual high peak rainfall shall be of 2.709mm and low peak rainfall shall be of 638mm. During

rainy season peak rainfall shall normally be in June and in October (rainfall of October shall be higher
than that of June).
+ July and end of August and beginning of September shall be months with the highest possibility of
lowest rainfall (draught); more severe draught during July.
+ There shall be about 90 ÷ 130 rainy days during rainy season. So, monthly average rainy days shall
be of more than 15 days.
+ Dry season shall commence from November or December and until April of the year after.
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

16
II.3.1.6 Wind regime
Construction site shall be in within area which subject to monsoon regime. Dry season shall mainly subject
to the northeast monsoon and by southwest monsoon for rainy season. Quite good of far vision up to 20km
(decreased by up to 5km during December).
Two wind seasons shall be in within the year:
+ Dry season shall commence since November until April of the year after with major wind direction is
east (normally up to 70% ).
+ Rainy season shall commence since June and end in September with two most common wind
directions i.e. west and southwest. Combined frequency of these two directions shall normally account
for 70- 80 %.
+ May and October shall be transition periods of these two wind seasons as above.
II.3.1.7 Typhoon/hurricane
This area shall, as per statistic figures, have several hurricanes (average of 243 hours of hurricane per year
and 110 days having hurricane per year), hurricanes shall normally appear at the beginning of rainy season,
and wind speed shall reach to level 7 – 8 during hurricanes;
Storms shall rarely appear in this area. From 1911 to 2009 there appeared 10 typhoons arrived to the
southern. Low frequency of typhoons which shall be lower than 11 grade, and normally during October and

November.
II.3.1.8 Tidal regime
Two corridors shall subject to tidal regime from East sea i.e. half-day tidal regime. It shall also subject to
flood from Mekong river, however, corridor no. 3 shall be impacted lightly only.
Corridor no. 2: It shall subject to tidal regime via. network of rivers i.e. Sai Gon, Vam Co and Tien rivers.
These rivers shall have average tidal variation of sea estuaries shall be about 3.0 – 3.5 m during high tidal
period. Maximum tidal variation shall be of more than 4.0 m.
 In Tan Chau (220 km away from sea estuary) tidal variation shall be from 5 cm (during flood season)
to 100 cm (during dry season).
 In My Tho (49 km away from sea), maximum tidal variation during tide up period shall be of 3.50 m
and 1.50 m during tide down period.
 Average maximum tidal water level in My Thuan shall account for about 1.80 – 1.90 m;
 During flooding season impacts for tide to areas far away from Tien river shall be null particularly of
high flood such as in Tan Phuoc districts and northern areas of districts i.e. Cai Be, Cai Lay and Chau
Thanh.
Corridor 3 It shall severely subject to impacts of half-day tidal regime of East Sea. Tide shall be transmitted
to alignment through river estuaries of Tran De river, My Thanh river, Ganh Hao river and through canals i.e.
Ho Phong; Cai Cung; Nha Mat, etc. The commence part adjacent to Tran De river shall have higher variation
of tidal regime in comparison with that of end alignment due to impact of tide from Ganh Hao and Ho Phong;
Cai Cung canals;
 During flood season commence part of alignment shall subject to floods from Mekong river, however,
it shall be light impacts in comparison with that of tide.
II.3.1.9 Seasonal flood

Flood season shall normally appear since end of June last until end of December and shall be divided
into three stages. During stage 1, from July to August, flooding water shall flow into natural canals and
creeks of Dong Thap Muoi and Tu Giac Long Xuyen regions. Flooding peak shall occur during stage 2
when water table of Tien river in Tan Chau is over 4.2 m, and the one of Hau river in Chau Doc is
exceed 3.5 m. Stage 3: water table shall be steadily lowered until end of December.
Water shall rise steadily accounting for about 10 – 15 cm/day. Flooding water flow shall be slow of about

60 –70 km/day. In case of tide up, the lower flooding water flow can be encountered. Flooding extent
shall be indicated as per side photo.
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

17
Corridor no. 2 shall have area which directly subject to flood which shall extended from Binh Chanh
(Cho Dem canal) to end of alignment in Kien Giang (Tam Ngan canal).
Corridor no. 3 shall also subject to flood but unremarkably as it located in flooded area and branches of
rivers and canals connecting to plains of Hau Giang, Can Tho regions of salinity prevention system.
II.3.2
WATER TABLE
Due to impacts arising due to tide and flood, water table over corridor shall be varies complicated particularly
for section from Cho Dem canal to end of corridor no. 2. In within scope from Rach Chanh creek to Dong
Thap Muoi which shall have several salinity prevention works, particularly Rach Chanh creek culvert which
shall result in complicated water table variation.
For finalization of water table as per frequency of service hours for transport purposes, hydrological
investigation has been performed/monitored at 21 stations at the same time for measuring water table in 2
corridors for 16 consecutive days. Of which water table in Rach Chanh creek has been measured at
upstream and downstream of culvert during dry season (May 2010) when Rach Chanh culvert gate was
closed for salinity prevention.

Figure II-1: Arrangement diagram of water table monitoring stations – corridor no. 2
: Sign of location of water table monitoring station; : Sign of location of basis hydrological
monitoring station.
In combination of hydrological document at basis stations, relative calculation to monitoring stations.
Water table shall be equivalent to frequency hours of 10 years at monitoring location in corridor no. 2 as
follows:

Table II.1: Frequency of water table hour - (2000 – 2009) over corridor no. 2
Frequency (%)
1
5
95
98
100
Km
TV1
Shallow
150
135
-100
-130
-200
Km0+00
Flood
162
150
-93
-120
-180
TV2
Shallow
150
136
-95
-120
-190
Km04+00

Flood
161
150
-88
-113
-180
TV3
Shallow
152
136
-78
-99
-150
Km10+00
Flood
174
160
-53
-80
-140
TV4
Shallow
146
130
-68
-88
-140
Km18+00
Flood
169

153
-45
-70
-130
Bến lức
Shallow
143
128
-68
-87
-140
Km32+00
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

18
Frequency (%)
1
5
95
98
100
Km
Flood
165
150
-46
-70

-130
TV5
Shallow
145
129
-60
-79
-120
Km37+00
Flood
168
152
-25
-50
-100
TV6
Shallow
130
118
-45
-62
-110
Km47+00
Flood
153
138
-17
-35
-90
TV7

Shallow
132
118
-61
-80
-120
Km51+00
Flood
157
140
-30
-52
-110
Rạch Chanh
Shallow
100
88
40
33
0
Km51+300
Flood
157
140
-30
-65
-110
TV8
Shallow
78

68
21
15
-20
Km62+00
Flood
193
172
-16
-35
-87
TV9
Shallow
69
57
2
-5
-40
Km73+00
Flood
211
188
5
-11
-53
TV10
Shallow
58
45
-19

-27
-40
Km81+00
Flood
229
203
24
13
-20


Figure II-2: Arrangement diagram of water table monitoring stations – corridor no. 3
: Sign of location of water table monitoring station; : Sign of location of basis hydrological
monitoring station.
In combination of hydrological document at basis stations, relative calculation to monitoring stations.
Water table shall be equivalent to frequency hours of 10 years at monitoring location in corridor no. 3 as
follows:
Table II.2: Frequency of water table hour - (2000 – 2009) over corridor no. 3
ID
Frequency
(%)
Dai
Ngai
TV11
TV12
TV13
TV14
TV15
TV16
TV17

TV18
TV19
TV20
1
1
160
173
150
150
165
172
150
143
130
150
162
2
5
133
148
129
128
141
150
128
125
116
134
142
20

95
-130
-108
-75
-74
-82
-88
-63
-53
-18
-29
-93
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

19
ID
Frequency
(%)
Dai
Ngai
TV11
TV12
TV13
TV14
TV15
TV16
TV17

TV18
TV19
TV20
21
98
-150
-130
-92
-90
-100
-107
-78
-68
-29
-41
-112
22
100
-200
-180
-130
-130
-140
-140
-120
-120
-60
-70
-160
Section (Km)

Km207
Km211
Km216
Km229
Km238
Km249
Km260
Km269
Km286
Km302
Km310
Note:

Water table level: As per National level network;

Details of monitoring data, calculation of water table shall be indicated in hydrological investigation
report performed by Hong Hung Consultancy and Construction Co., Ltd. In cooperation with the Southern
Hydrological Sub-institute during period of 4/2010 – 7/2010.
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

20
III. STATUS OF CURRENT ROADS AND SCOPE OF REPLACEMENT
CONSTRUCTION
III.1
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT CORRIDOR
NO 2
Table III.1: The status of current roads that must be demolished and cleared at corridor No 2

No.
Station
Location
Length (m)
Width (m)
Level of road
center
Current
structure
Code
NW9 corridor 2
Thủ Thừa canal
H




1
From km42+425
to km42+475
Tân Thành-Thủ Thừa-Long An
68.29
1,5÷2,0
+1,8 ÷ +2,4
Soil road
DDS1
2
From km42+650
to km42+850
Tân Thành-Thủ Thừa-Long An

203.75
1,5÷2,0
+1,8 ÷ +2,4
Soil road
DDS2
3
From km42+925
to km43+275
Tân Thành-Thủ Thừa-Long An
322.5
1,5÷2,0
+1,8 ÷ +2,4
Soil road
DDS3
NW10 corridor 2
Nguyễn Văn Tiếp canal
9617.38




1
From km58+265
to km58+822
Hưng Thạnh-Tân Phước-Tiền
Giang
557
1,2÷1,8
+1,6 ÷ +3,1
Soil road

DDS4
2
From km58+862
to km59+749
Hưng Thạnh-Tân Phước-Tiền
Giang
887
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS5
3
From km59+975
to km60+939
Hưng Thạnh-Tân Phước-Tiền
Giang
964.47
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS6
4
From km60+987
to km64+344
Hưng Thạnh-Tân Phước-Tiền
Giang
3357.00
1,2÷1,8
+1,6 ÷ +3,1
Soil road

DDS7
5
From km64+406
to km65+411
Hưng Thạnh-Tân Phước-Tiền
Giang
1005.26
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS8
6
From km65+425
to km66+728
Tân lập-Tân Phước-Tiền Giang
1303.42
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS9
7
From km67+125
to km67+782
Phước lập-Tân Phước-Tiền
Giang
657
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS10

8
From km67+815
to km68+631
Phước lập-Tân Phước-Tiền
Giang
816.24
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS11
9
From km72+325
to km72+395
Mỹ Phước-Tân Phước-Tiền
Giang
70
1,2÷1,8
+1,6 ÷ +3,1
Soil road
DDS12
 DDS1÷DDS3 road lies on the Northern bank of Thu Thua canal. The road is of soil structure and has a
width of (1,5÷2,0) m. The gradient changes slightly. Mainly motorbikes and padestrians travel along
the road. This road plays no role in preveting tide and flood.
 DDS4÷DDS12 road lies on the Southern bank of Nguyen Van Tiep canal. The road is of soil structure
and has a width of (1,2÷1,8) m. The gradient changes slightly. Mainly motorbikes and padestrians
travel along the road. This road is built on anti-flood dike for southern area of Nguyen Van Tiep canal.
Soil in the local area is used to fill the road.
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13

Paper :

21
III.2
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT CORRIDOR
NO 2
At the corridoe No 2, two bridges of Package NW10 will be demolished. Bridge No.17 (Cong Tuong
brigde) is located at Km58+850 in Hung Thanh commune, Tan Phuoc District of Tien Giang province.
Bridge No.18 (Xang Don brigde) is located at Km64+355 in Hung Thanh commune, Tan Phuoc District
of Tien Giang province.
 Bridge No.17 & No.18: has wooden surface on iron beams supported on steel enforced concrete
abutments. Each abutment is supported by 3 steel reinforced square piles.
 This bridge is 16 m long on 3 different spans of 4m, 8 m and 4 m respectively on Xang Don canal
whose width is 15 m. The clearance of the bridge is 1,5 m. It is mainly used for on land traffic and
some local waterway going underneath the bridge.

Figure III-1: Bridge No 18-Xang Don bridge
III.3
STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT CORRIDOR
NO 3
Table III.2: The status of current roads that must be demolished and cleared at corridor No 3
No
Station
Location
Length
(m)
Width
(m)
Level of road
center

Current
structure
Code
NW12 corridor 3
Bac Lieu-Ca Mau canal
3,823.00




1
From km285+375 to
km285+513
Ward 2- Bac Lieu city-Bac
Lieu province
138.00
1,8÷2,5
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS1
2
From km285+627 to
km287+129
Ward 8- Bac Lieu city-Bac
Lieu province
1502
1,8÷2,5
+1,6 ÷ +2,0
Aggregate

crushed stone
DDS2
3
From km287+475 to
km287+492
Ward 8- Bac Lieu city-Bac
Lieu province
17
1,8÷2,5
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS3
4
From km287+570 to
km287+735
Ward 8- Bac Lieu city-Bac
Lieu province
165
1,8÷2,0
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS4
5
From km287+809 to
km288+878
Ward 8- Bac Lieu city-Bac
Lieu province
1,069.00

1,8÷2,0
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS5
6
From km288+950 to
km289+882
Ward 8- Bac Lieu city-Bac
Lieu province
932.00
1,8÷2,0
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS6
NW13 corridor 3
Bac Lieu-Ca Mau canal
8,380.00




Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

22
No

Station
Location
Length
(m)
Width
(m)
Level of road
center
Current
structure
Code
1
From km290+000 to
km290+044
Long Thanh commune, Vinh
Loi District- Bac Lieu province
44
1,8÷2,0
+1,6 ÷ +2,0
Aggregate
crushed stone
DDS7
2
From km290+200 to
km291+096
Long Thanh commune, Vinh
Loi District- Bac Lieu province
896.00
1,8÷2,0
+1,5 ÷ +2,0

Aggregate
crushed stone
DDS8
3
From km291+159 to
km292+375
Long Thanh commune, Vinh
Loi District- Bac Lieu province
1,216.00
1,8÷2,0
+1,5 ÷ +2,0
Aggregate
crushed stone
DDS9
4
From km292+489 to
km293+535
Long Thanh commune, Vinh
Loi District- Bac Lieu province
1,046.00
1,8÷2,0
+1,5 ÷ +2,0
Aggregate
crushed stone
DDS10
5
From km293+750 to
km294+285
Hoa Binh town, Vinh Loi
District- Bac Lieu province

535.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS11
6
From km294+335 to
km294+514
Hoa Binh town, Vinh Loi
District- Bac Lieu province
179.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS12
7
From km294+566 to
km294+880
Hoa Binh town, Vinh Loi
District- Bac Lieu province
314.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS13
8
From km294+995 to

km295+467
Hoa Binh town, Vinh Loi
District- Bac Lieu province
472.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS14
9
From km295+542 to
km295+685
Hoa Binh town, Vinh Loi
District- Bac Lieu province
143.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS15
10
From km295+736 to
km296+415
Hoa Binh town, Vinh Loi
District- Bac Lieu province
679.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete

DDS16
11
From km297+050 to
km298+028
Hoa Binh town, Vinh Loi
District- Bac Lieu province
978.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS17
12
From km298+142 to
km298+690
Vinh My A commune, Vinh Loi
District- Bac Lieu province
548.00
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS18
13
From km299+010 to
km299+200
Vinh My A commune, Vinh Loi
District- Bac Lieu province
190
1,8÷2,0

+1,5 ÷ +2,0
Asphaltic
concrete
DDS19
14
From km299+475 to
km300+110
Vinh My A commune, Vinh Loi
District- Bac Lieu province
635
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS20
15
From km300+180 to
km300+269
Vinh My A commune, Vinh Loi
District- Bac Lieu province
89
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS21
16
From km300+275 to
km300+605
Vinh My A commune, Vinh Loi

District- Bac Lieu province
330
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS22
17
From km300+875 to
km300+961
Vinh My A commune, Vinh Loi
District- Bac Lieu province
86
1,8÷2,0
+1,5 ÷ +2,0
Asphaltic
concrete
DDS23
 DDS1÷DDS10 traffic road lies in the Southern bank of Bac Lieu-Ca Mau canal. The road is of
aggregate cushed stone structure with a width of 1,8m to 2,5 m. The gradient changes slightly.
Motorbikes and pedestrians are main vehicles on the road.
 DDS11÷DDS23 traffic road lies in the Southern bank of Bac Lieu-Ca Mau canal. The road is of
aggregate cushed stone structure with a width of 1,8m to 2,0 m. The gradient changes slightly.
Motorbikes and pedestrians are main vehicles on the road.
III.4
THE STATUS OF CURRENT ROADS THAT MUST BE DEMOLISHED AND CLEARED AT
CORRIDOR NO 3
Total number of demolished bridge is 16. Five belongs to NW12 package and 11 belongs to NW13
package. The name, station and location of these bridges are described in the following table:


Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

23

Table III.3: The number of demolished bridges
Package
No.
bridge
code
Name of bridge
Station
Location of construction
NW12
1
Bridge 1
Cong Xi Ruu bridge
Km285+575
Ward 2, Bac Lieu town, Bac Lieu province
2
Bridge 2
Kham Tam bridge
Km287+525
Ward 8, Bac Lieu town, Bac Lieu province
3
Bridge 3
Mr/Ms Trang Thuy bridge
Km287+775

Ward 8, Bac Lieu town, Bac Lieu province
4
Bridge 4
Tra Kha bridge
Km288+900
Tra Kha B, Ward 8, Bac Lieu town, Bac Lieu
province
5
Bridge 5
Dan Xay 02 bridge
Km289+950
Long Thanh commune, Vinh Loi District- Bac Lieu
province
NW13
1
Bridge 6
Huynh Cong Bang arch
bridge
Km291+100
Phuoc Thanh 2, Long Thanh commune, Vinh Loi
District- Bac Lieu province
2
Bridge 7
Nguyen Thanh Ky arch
bridge
Km292+425
Cai Tram A2, Long Thanh commune, Vinh Loi
District- Bac Lieu province
3
Bridge 8

Cai Tram 02 bridge
Km293+575
Long Thanh commune, Vinh Loi District- Bac Lieu
province
4
Bridge 9
Mr Luc bridge
Km294+300
Cai Tram B, Hoa Binh town, Vinh Loi District-
Bac Lieu province
5
Bridge 10
Son Tranh bridge
Km294+525
Cai Tram B1, Hoa Binh town, Vinh Loi District-
Bac Lieu province
6
Bridge 11
Quoc Truong bridge
Km294+925
Cai Tram B, Hoa Binh town, Vinh Loi District-
Bac Lieu province
7
Bridge 12
Ms Van bridge
Km295+500
Cai Tram B, Hoa Binh town, Vinh Loi District-
Bac Lieu province
8
Bridge 13

Son Lam bridge
Km295+700
Cai Tram B, Hoa Binh town, Vinh Loi District-
Bac Lieu province
9
Bridge 14
Kenh Sau bridge
Km298+100
My Vinh A commune, Vinh Loi district, Bac Lieu
province
10
Bridge 15
Nam Nghi bridge
Km298+975
My Vinh A commune, Vinh Loi district, Bac Lieu
province
11
Bridge 16
Hai Trai bridge
Km300+125
My Vinh A commune, Vinh Loi district, Bac Lieu
province
Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

24
III.4.1
STATUS OF BRIDGE NO 1 UNDER NW12 PACKAGE, CORRIDOR 3

The name of the bridge is Cong Xi Ruu bridge whose surface is of wooden slabs on iron beams
supported by abutments and steel reinforced piles. Each abutment is reinforced by square steel
reinforced piles.
The bridge is 10 m long with only one span of 10 m long. The width of the bridge is 1,6m spanning over
a canal of 6m wide. The bridge is only used for walking and for drainage, not for waterway vehicles.


Figure III-2: Bridge No. 1 - Cong Xi Ruu bridge
III.4.2
STATUS OF BRIDGE NO 2 UNDER NW12 PACKAGE, CORRIDOR 3
This bridge is named Kham Tam bridge whose surface is made by steel reinforced concrete slabs over
steel reinforced beams supported by abutments. Each abutment is reinforced by square steel concrete
piles.
This bridge has a length of 19 m with 5 spans with dimensions being 3m + 4m + [5m] + 4m + 3m. It is
2,4 m wide over a canal of 16 m wide. The clearance is 1,5m and it is mainly used for on land traffic and
for small local waterway vehicles.

Mekong Delta Transport Infrastructure Development project (MDTIDP)
Main Waterway Corridors Improvements Phase 2 plus Supervision of Phase 1+2
General report of frontage road and bridge - NW9, NW10, NW12, NW13
Paper :

25

Hình III-3: Bridge No.2 – Kham Tam bridge
III.4.3
STATUS OF BRIDGE NO 3 UNDER NW12 PACKAGE, CORRIDOR 3
This bridge is named Mr./Ms Trang Thuy bridge whose surface is made by steel reinforced concrete
slabs over steel reinforced beams supported by abutments. Each abutment is reinforced by 3 square
steel concrete piles.

This bridge has a length of 14 m with 3 spans with dimensions being 5m + [4m] + 5m. It is 2 m wide over
Giong Tra canal of 7 m wide. The clearance is 1,5m and it is mainly used for on land traffic and for small
local waterway vehicles.

Figure III-4: Bridge No. 3-Mr/Ms Trang Thuy bridge

III.4.4
STATUS OF BRIDGE NO 4 UNDER NW12 PACKAGE, CORRIDOR 3

This bridge is named Tra Kha bridge whose surface is made by steel reinforced concrete slabs over
steel reinforced beams supported by abutments. Each abutment is reinforced by 2 square steel concrete
piles.

×