Tải bản đầy đủ (.ppt) (58 trang)

Operation management 6e by russel and taylor ch09

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (2.14 MB, 58 trang )

Chapter 9
Project Management
Operations
Operations Management
Management -- 66thth Edition
Edition
Roberta Russell & Bernard W. Taylor, III

Copyright 2009 John Wiley & Sons, Inc.

Beni Asllani
University of Tennessee at Chattanooga


Lecture Outline








Project Planning
Project Scheduling
Project Control
CPM/PERT
Probabilistic Activity Times
Microsoft Project
Project Crashing and Time-Cost
Trade-off


Copyright 2009 John Wiley & Sons, Inc.

9-2


Project Management Process
 Project


unique, one-time operational activity or effort

Copyright 2009 John Wiley & Sons, Inc.

9-3


Project Management Process
(cont.)

Copyright 2009 John Wiley & Sons, Inc.

9-4


Project Management Process
(cont.)

Copyright 2009 John Wiley & Sons, Inc.

9-5



Project Elements









Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
Copyright 2009 John Wiley & Sons, Inc.

9-6


Project Team and Project Manager
 Project team


made up of individuals from various areas and

departments within a company

 Matrix organization


a team structure with members from functional
areas, depending on skills required

 Project manager


most important member of project team
Copyright 2009 John Wiley & Sons, Inc.

9-7


Scope Statement and Work
Breakdown Structure
 Scope statement


a document that provides an understanding,
justification, and expected result of a project

 Statement of work


written description of objectives of a project


 Work breakdown structure (WBS)


breaks down a project into components,
subcomponents, activities, and tasks

Copyright 2009 John Wiley & Sons, Inc.

9-8


Work Breakdown Structure for Computer Order
Processing System Project

Copyright 2009 John Wiley & Sons, Inc.

9-9


Responsibility Assignment Matrix
 Organizational
Breakdown
Structure (OBS)


a chart that
shows which
organizational
units are
responsible for

work items

 Responsibility
Assignment
Matrix (RAM)


Copyright 2009 John Wiley & Sons, Inc.

shows who is
responsible for
work in a
project
9-10


Global and Diversity Issues in
Project Management
 In existing global business environment,
project teams are formed from different
genders, cultures, ethnicities, etc.
 In global projects diversity among team
members can add an extra dimension to
project planning
 Cultural research and communication are
important elements in planning process

Copyright 2009 John Wiley & Sons, Inc.

9-11



Project Scheduling
 Steps






Define activities
Sequence
activities
Estimate time
Develop schedule

 Techniques




Gantt chart
CPM/PERT
Microsoft Project

Copyright 2009 John Wiley & Sons, Inc.

9-12



Gantt Chart
 Graph or bar chart with a bar for each
project activity that shows passage of
time
 Provides visual display of project
schedule
 Slack


amount of time an activity can be delayed
without delaying the project
Copyright 2009 John Wiley & Sons, Inc.

9-13


Example of Gantt Chart
0

|

2

|

Month
4

|


6

|

8

|

10

Activity
Design house
and obtain
financing
Lay
foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work

1

3

Month


5

Copyright 2009 John Wiley & Sons, Inc.

7

9

9-14


Project Control





Time management
Cost management
Quality management
Performance management


Earned Value Analysis


a standard procedure for numerically measuring a
project’s progress, forecasting its completion date and
cost and measuring schedule and budget variation


 Communication
 Enterprise project management
Copyright 2009 John Wiley & Sons, Inc.

9-15


CPM/PERT
 Critical Path Method (CPM)




DuPont & Remington-Rand (1956)
Deterministic task times
Activity-on-node network construction

 Project Evaluation and Review Technique
(PERT)




US Navy, Booz, Allen & Hamilton
Multiple task time estimates; probabilistic
Activity-on-arrow network construction
Copyright 2009 John Wiley & Sons, Inc.

9-16



Project Network
 Activity-on-node (AON)


nodes represent activities,
and arrows show
precedence relationships

Node

 Activity-on-arrow (AOA)


arrows represent activities
and nodes are events for
points in time

 Event


completion or beginning
of an activity in a project

1

2

3


Branch

 Dummy


two or more activities
cannot share same start
and end nodes
Copyright 2009 John Wiley & Sons, Inc.

9-17


AOA Project Network for
a House
Lay
foundation

1

3
Design house
and obtain
financing

2

3
2


Dummy
0

1
Order and
receive
materials

4
Select
paint

Build
house

6

3
1

1

Finish
work
1

7

Select
carpet


5

Copyright 2009 John Wiley & Sons, Inc.

9-18


Concurrent Activities
Lay foundation

2

Lay
foundation

3

Order material

(a) Incorrect precedence
relationship

3
Dummy
2

0
1


2

4

Order material
(b) Correct precedence
relationship

Copyright 2009 John Wiley & Sons, Inc.

9-19


AON Network for House
Building Project
Lay foundations

Build house

4
3

2
2
Start

Finish work

7
1


1
3

Design house
and obtain
financing

3
1

Order and receive
materials

5
1

6
1
Select carpet

Select paint

Copyright 2009 John Wiley & Sons, Inc.

9-20


Critical Path
4

3

2
2
Start

7
1

1
3
3
1

A:
B:
C:
D:

1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months

6
1


5
1

 Critical path




Copyright 2009 John Wiley & Sons, Inc.

Longest path
through a network
Minimum project
completion time
9-21


Activity Start Times
Start at 5 months

4
3

2
2
Start

Finish at 9 months


7
1

1
3
3
1
Start at 3 months

5
1

Finish

6
1
Start at 6 months

Copyright 2009 John Wiley & Sons, Inc.

9-22


Node Configuration
Activity number

Earliest start

Earliest finish


1

0

3

3

0

3
Latest finish

Activity duration

Latest start

Copyright 2009 John Wiley & Sons, Inc.

9-23


Activity Scheduling
 Earliest start time (ES)



earliest time an activity can start
ES = maximum EF of immediate predecessors


 Forward pass


starts at beginning of CPM/PERT network to
determine earliest activity times

 Earliest finish time (EF)




earliest time an activity can finish
earliest start time plus activity time
EF= ES + t

Copyright 2009 John Wiley & Sons, Inc.

9-24


Earliest Activity Start and
Finish Times
Lay foundations
Build house

2

Start

3


5
4

2

5

8

3
1

0

3

7

1
Design house
and obtain
financing

8

9

1
6

3

3

4

1
Order and receive
materials

6

7

Finish work

1
5

5

6

1

Select carpet

Select pain

Copyright 2009 John Wiley & Sons, Inc.


9-25


×