Chapter 9
Project Management
Operations
Operations Management
Management -- 66thth Edition
Edition
Roberta Russell & Bernard W. Taylor, III
Copyright 2009 John Wiley & Sons, Inc.
Beni Asllani
University of Tennessee at Chattanooga
Lecture Outline
Project Planning
Project Scheduling
Project Control
CPM/PERT
Probabilistic Activity Times
Microsoft Project
Project Crashing and Time-Cost
Trade-off
Copyright 2009 John Wiley & Sons, Inc.
9-2
Project Management Process
Project
unique, one-time operational activity or effort
Copyright 2009 John Wiley & Sons, Inc.
9-3
Project Management Process
(cont.)
Copyright 2009 John Wiley & Sons, Inc.
9-4
Project Management Process
(cont.)
Copyright 2009 John Wiley & Sons, Inc.
9-5
Project Elements
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
Copyright 2009 John Wiley & Sons, Inc.
9-6
Project Team and Project Manager
Project team
made up of individuals from various areas and
departments within a company
Matrix organization
a team structure with members from functional
areas, depending on skills required
Project manager
most important member of project team
Copyright 2009 John Wiley & Sons, Inc.
9-7
Scope Statement and Work
Breakdown Structure
Scope statement
a document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project
Work breakdown structure (WBS)
breaks down a project into components,
subcomponents, activities, and tasks
Copyright 2009 John Wiley & Sons, Inc.
9-8
Work Breakdown Structure for Computer Order
Processing System Project
Copyright 2009 John Wiley & Sons, Inc.
9-9
Responsibility Assignment Matrix
Organizational
Breakdown
Structure (OBS)
a chart that
shows which
organizational
units are
responsible for
work items
Responsibility
Assignment
Matrix (RAM)
Copyright 2009 John Wiley & Sons, Inc.
shows who is
responsible for
work in a
project
9-10
Global and Diversity Issues in
Project Management
In existing global business environment,
project teams are formed from different
genders, cultures, ethnicities, etc.
In global projects diversity among team
members can add an extra dimension to
project planning
Cultural research and communication are
important elements in planning process
Copyright 2009 John Wiley & Sons, Inc.
9-11
Project Scheduling
Steps
Define activities
Sequence
activities
Estimate time
Develop schedule
Techniques
Gantt chart
CPM/PERT
Microsoft Project
Copyright 2009 John Wiley & Sons, Inc.
9-12
Gantt Chart
Graph or bar chart with a bar for each
project activity that shows passage of
time
Provides visual display of project
schedule
Slack
amount of time an activity can be delayed
without delaying the project
Copyright 2009 John Wiley & Sons, Inc.
9-13
Example of Gantt Chart
0
|
2
|
Month
4
|
6
|
8
|
10
Activity
Design house
and obtain
financing
Lay
foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
1
3
Month
5
Copyright 2009 John Wiley & Sons, Inc.
7
9
9-14
Project Control
Time management
Cost management
Quality management
Performance management
Earned Value Analysis
a standard procedure for numerically measuring a
project’s progress, forecasting its completion date and
cost and measuring schedule and budget variation
Communication
Enterprise project management
Copyright 2009 John Wiley & Sons, Inc.
9-15
CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand (1956)
Deterministic task times
Activity-on-node network construction
Project Evaluation and Review Technique
(PERT)
US Navy, Booz, Allen & Hamilton
Multiple task time estimates; probabilistic
Activity-on-arrow network construction
Copyright 2009 John Wiley & Sons, Inc.
9-16
Project Network
Activity-on-node (AON)
nodes represent activities,
and arrows show
precedence relationships
Node
Activity-on-arrow (AOA)
arrows represent activities
and nodes are events for
points in time
Event
completion or beginning
of an activity in a project
1
2
3
Branch
Dummy
two or more activities
cannot share same start
and end nodes
Copyright 2009 John Wiley & Sons, Inc.
9-17
AOA Project Network for
a House
Lay
foundation
1
3
Design house
and obtain
financing
2
3
2
Dummy
0
1
Order and
receive
materials
4
Select
paint
Build
house
6
3
1
1
Finish
work
1
7
Select
carpet
5
Copyright 2009 John Wiley & Sons, Inc.
9-18
Concurrent Activities
Lay foundation
2
Lay
foundation
3
Order material
(a) Incorrect precedence
relationship
3
Dummy
2
0
1
2
4
Order material
(b) Correct precedence
relationship
Copyright 2009 John Wiley & Sons, Inc.
9-19
AON Network for House
Building Project
Lay foundations
Build house
4
3
2
2
Start
Finish work
7
1
1
3
Design house
and obtain
financing
3
1
Order and receive
materials
5
1
6
1
Select carpet
Select paint
Copyright 2009 John Wiley & Sons, Inc.
9-20
Critical Path
4
3
2
2
Start
7
1
1
3
3
1
A:
B:
C:
D:
1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
6
1
5
1
Critical path
Copyright 2009 John Wiley & Sons, Inc.
Longest path
through a network
Minimum project
completion time
9-21
Activity Start Times
Start at 5 months
4
3
2
2
Start
Finish at 9 months
7
1
1
3
3
1
Start at 3 months
5
1
Finish
6
1
Start at 6 months
Copyright 2009 John Wiley & Sons, Inc.
9-22
Node Configuration
Activity number
Earliest start
Earliest finish
1
0
3
3
0
3
Latest finish
Activity duration
Latest start
Copyright 2009 John Wiley & Sons, Inc.
9-23
Activity Scheduling
Earliest start time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
Forward pass
starts at beginning of CPM/PERT network to
determine earliest activity times
Earliest finish time (EF)
earliest time an activity can finish
earliest start time plus activity time
EF= ES + t
Copyright 2009 John Wiley & Sons, Inc.
9-24
Earliest Activity Start and
Finish Times
Lay foundations
Build house
2
Start
3
5
4
2
5
8
3
1
0
3
7
1
Design house
and obtain
financing
8
9
1
6
3
3
4
1
Order and receive
materials
6
7
Finish work
1
5
5
6
1
Select carpet
Select pain
Copyright 2009 John Wiley & Sons, Inc.
9-25