2
Project Management
PowerPoint Slides
by Jeff Heyl
For Operations Management, 9e by
Krajewski/Ritzman/Malhotra
© 2010 Pearson Education
2–1
Projects
Projects are an interrelated set of activities
with a definite starting and ending point,
which results in a unique outcome from a
specific allocation of resources
Projects are common in everyday life
The three main goals are to:
Complete
Not
the project on time
exceed the budget
Meet
the specifications to the satisfactions of
the customer
2–2
Projects
Project management is a systemized,
phased approach to defining, organizing,
planning, monitoring, and controlling
projects
Projects often require resources from
many different parts of the organization
Each project is unique
Projects are temporary
A collection of projects is called a program
2–3
Defining and Organizing Projects
Define the scope, time frame, and resources
of the project
Select the project manager and team
Good project managers must be
Facilitators
Communicators
Decision
makers
Project team members must have
Technical
competence
Sensitivity
Dedication
2–4
Organizational Structure
Different structures have different
implications for project management
Common structures are
Functional
Pure
project
Matrix
2–5
Planning Projects
There are five steps to planning projects
1.
Defining the work breakdown structure
2.
Diagramming the network
3.
Developing the schedule
4.
Analyzing the cost-time trade-offs
5.
Assessing risks
2–6
Work Breakdown Structure
A statement of all the tasks that must be
completed as part of the project
An activity is the smallest unit of work
effort consuming both time and resources
that the project manager can schedule and
control
Each activity must have an owner who is
responsible for doing the work
2–7
Work Breakdown Structure
Relocation of St. John’s Hospital
Organizing and Site Preparation
Level 0
Physical Facilities and Infrastructure
Select administration staff
Purchase and deliver equipment
Site selection and survey
Construct hospital
Select medical equipment
Develop information system
Prepare final construction plans
Install medical equipment
Bring utilities to site
Train nurses and support staff
Interview applicants for
nursing and support staff
Level 1
Level 2
Figure 2.1
2–8
Diagramming the Network
Network diagrams use nodes and arcs to
depict the relationships between activities
Benefits of using networks include
1.
Networks force project teams to identify and
organize data to identify interrelationships
between activities
2.
Networks enable the estimation of completion
time
3.
Crucial activities are highlighted
4.
Cost and time trade-offs can be analyzed
2–9
Diagramming the Network
Precedent relationships determine the
sequence for undertaking activities
Activity times must be estimated using
historical information, statistical analysis,
learning curves, or informed estimates
In the activity-on-node approach, nodes
represent activities and arcs represent the
relationships between activities
2 – 10
Diagramming the Network
AON
S
Activity Relationships
T
U
S
U
T
S precedes T, which
precedes U.
S and T must be
completed before U
can be started.
Figure 2.2
2 – 11
Diagramming the Network
AON
Activity Relationships
T
T and U cannot
begin until S has
been completed.
S
U
S
U
T
V
U and V can’t begin
until both S and T
have been completed.
Figure 2.2
2 – 12
Diagramming the Network
AON
Activity Relationships
S
U
T
V
S
T
U
V
U cannot begin until
both S and T have been
completed; V cannot
begin until T has been
completed.
T and U cannot begin
until S has been
completed and V cannot
begin until both T and U
have been completed.
Figure 2.2
2 – 13
Developing the Schedule
Schedules can help managers achieve the
objectives of the project
Managers can
1.
Estimate the completion time by finding the
critical path
2.
Identify start and finish times for each activity
3.
Calculate the amount of slack time for each
activity
2 – 14
Critical Path
The sequence of activities between a
project’s start and finish is a path
The critical path is the path that takes the
longest time to complete
2 – 15
St. John’s Hospital Project
Activity
Immediate
Predecessors
Responsibility
Kramer
ST. JOHN’S HOSPITAL PROJECT
0
START
ORGANIZING and SITE PREPARATION
Activity Times
(wks)
Stewart
START
12
START
9
Taylor
A
10
Adams
Select medical equipment
B
10
Taylor
D.
Prepare final construction plans
B
24
Burton
E.
Bring utilities to site
A
10
Johnson
F.
Interview applicants for nursing and
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE C
35
Walker
G. Purchase and deliver equipment
D
40
Sampson
H.
Construct hospital
A
15
Casey
I.
Develop information system
J.
Install medical equipment
K.
Train nurses and support staff
A.
Select administrative staff
B.
Select site and survey
C.
FINISH 2.1
Example
Johnson
E, G, H
4
Murphy
F, I, J
6
Pike
K
0
Ashton
2 – 16
St. John’s Hospital Project
Activity
Immediate
Predecessors
ST. JOHN’S HOSPITAL PROJECT
START
Completion Time
Activity
IP
Time
ORGANIZING
and
SITE PREPARATION
A A. Select
STARTadministrative
12
staff
A
B
START
9
12
site and
C B. Select
A
10 survey
D C. Select
B
10 equipment
medical
E
B
24
D.
Prepare
final
F
A
10construction plans
Start
G E. Bring
C
35to site
utilities
H
D
40
F. Interview applicants for nursing and
I
A
support
staff15
J
E, G, H
4
B
PHYSICAL
FACILITIES
and
INFRASTRUCTURE
K
F, I, J
6
9
G. Purchase and deliver equipment
H.
Construct hospital
I.
J.
Develop information system
Figure 2.3
Install medical
equipment
K.
Train nurses and support staff
FINISH 2.1
Example
Activity Times
(wks)
Responsibility
I
15
F
10
K
6
C
10
G
35
D
10
H
40
Finish
J
4
E
24
2 – 17
Estimated Time (weeks)
St.
John’s
Hospital
Project
A–I–K
33
Path
A–F–K
Activity
28
A–C–G–J–K
67
B–D–H–J–K
Completion
69 Time
Immediate
Predecessors
ST. JOHN’S HOSPITAL PROJECT
START
Activity Times
(wks)
Responsibility
I
15
B–E–J–K
43
ORGANIZING and SITE PREPARATION
A.
Select administrative staff
B.
Select site and survey
C.
Select medical equipment
D.
Prepare final construction plans
Start
Bring utilities to site
E.
A
12
Interview applicants for nursing and
support staff
B
PHYSICAL FACILITIES and INFRASTRUCTURE
9
G. Purchase and deliver equipment
F
10
K
6
C
10
G
35
D
10
H
40
Finish
F.
H.
Construct hospital
I.
J.
Develop information system
Figure 2.3
Install medical
equipment
K.
Train nurses and support staff
FINISH 2.1
Example
J
4
E
24
2 – 18
Estimated Time (weeks)
St.
John’s
Hospital
Project
A–I–K
33
Path
A–F–K
Activity
28
A–C–G–J–K
67
B–D–H–J–K
Completion
69 Time
Immediate
Predecessors
ST. JOHN’S HOSPITAL PROJECT
START
Activity Times
(wks)
Responsibility
I
15
B–E–J–K
43
ORGANIZING and SITE PREPARATION
A.
Select administrative staff
B.
Select site and survey
C.
Select medical equipment
D.
Prepare final construction plans
Start
Bring utilities to site
E.
A
12
Interview applicants for nursing and
support staff
B
PHYSICAL FACILITIES and INFRASTRUCTURE
9
G. Purchase and deliver equipment
F
10
K
6
C
10
G
35
D
10
H
40
Finish
F.
H.
Construct hospital
I.
J.
Develop information system
Figure 2.3
Install medical
equipment
K.
Train nurses and support staff
FINISH 2.1
Example
J
4
E
24
2 – 19
Application 2.1
The following information is known about a project
Activity
Activity Time (days)
Immediate
Predecessor(s)
A
7
—
B
2
A
C
4
A
D
4
B, C
E
4
D
F
3
E
G
5
E
Draw the network diagram for this project
2 – 20
Application 2.1
Activity
Activity Time (days)
Immediate
Predecessor(s)
A
7
—
B
2
A
C
4
A
D
4
B, C
E
4
D
F
3
E
G
5
E
B
2
Start
A
7
F
3
D
4
C
4
E
4
Finish
G
5
2 – 21
Project Schedule
The project schedule specifies start and
finish times for each activity
Managers can use the earliest start and
finish times, the latest start and finish
times, or any time in between these
extremes
2 – 22
Project Schedule
The earliest start time (ES) for an activity is the
latest earliest finish time of any preceding
activities
The earliest finish time (EF) is the earliest start
time plus its estimated duration
EF = ES + t
The latest finish time (LF) for an activity is the
latest start time of any preceding activities
The latest start time (LS) is the latest finish time
minus its estimated duration
LS = LF – t
2 – 23
Early Start and Early Finish Times
EXAMPLE 2.2
Calculate the ES, EF, LS, and LF times for each activity in the
hospital project. Which activity should Kramer start
immediately? Figure 2.3 contains the activity times.
SOLUTION
To compute the early start and early finish times, we begin at
the start node at time zero. Because activities A and B have no
predecessors, the earliest start times for these activities are
also zero. The earliest finish times for these activities are
EFA = 0 + 12 = 12 and EFB = 0 + 9 = 9
2 – 24
Early Start and Early Finish Times
Because the earliest start time for activities I, F, and C is the
earliest finish time of activity A,
ESI = 12, ESF = 12, and ESC = 12
Similarly,
ESD = 9 and ESE = 9
After placing these ES values on the network diagram, we
determine the EF times for activities I, F, C, D, and E:
EFI = 12 + 15 = 27, EFF = 12 + 10 = 22, EFC = 12 + 10 = 22,
EFD = 9 + 10 = 19, and EFE = 9 + 24 = 33
2 – 25