Tải bản đầy đủ (.ppt) (26 trang)

Project management a managerial approach chapter 08

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (186.04 KB, 26 trang )

Project Management: A
Managerial Approach
Chapter 8 – Scheduling
© 2006 John Wiley


Overview





WBS to Schedule Process
PERT
Schedule Types
CPM

© 2006 John Wiley


Scheduling
• A schedule is the conversion of a project
action plan into an operating timetable
• It serves as the basis for monitoring and
controlling project activity
• Taken together with the plan and budget,
it is probably the major tool for the
management of projects
© 2006 John Wiley

Chapter 8-1




Simple Schedule – Gantt Chart

© 2006 John Wiley


Network Techniques: PERT and CPM
• With the exception of Gantt charts, the most
common approach to scheduling is the use of
network techniques such as PERT and CPM
• The Program Evaluation and Review Technique
(PERT) was developed by the U.S. Navy in 1958
• The Critical Path Method (CPM) was developed
by DuPont, Inc during the same time period

© 2006 John Wiley

Chapter 8-7


Scheduling Terminology
• Activity - A specific task or set of tasks that are
required by the project, use up resources, and take
time to complete
• Event - The result of completing one or more
activities. An identifiable end state occurring at a
particular time. Events use no resources.
• Network - The combination of all activities and
events define the project and the activity

precedence relationships
© 2006 John Wiley

Chapter 8-9


Scheduling Terminology
• Path - The series of connected activities (or
intermediate events) between any two events
in a network
• Critical - Activities, events, or paths which, if
delayed, will delay the completion of the
project. A project’s critical path is understood
to mean that sequence of critical activities that
connect the project’s start event to its finish
event
© 2006 John Wiley

Chapter 8-10


Scheduling Terminology
• An activity can be in any of these conditions:
– It may have a successor(s) but no predecessor(s) starts a network
– It may have a predecessor(s) but no successor(s) ends a network
– It may have both predecessor(s) and successor(s) - in
the middle of a network

• Interconnections from horizontal links in vertical
WBS

© 2006 John Wiley


Hypothetical Network
3
13

1

30

16

2

5
20

6

4
Calculate t(e) and Z for this network……
© 2006 John Wiley

5

6
TE=64



Activity and Project Frequency Distributions
ACTIVITY

a

PROJECT

m

b
(A)

© 2006 John Wiley

TE
(B)


PERT Activity Calculation
t(e) = a + 4m + b
6

a = Most Optimistic (MO)
m = Most Likely (ML)
b = Most Pessimistic (MP)
t(e) = Activity Duration

When a single estimate for activity time is not sufficient!

© 2006 John Wiley



PERT Schedule Probability
Z = T(S) – T(E)
SD(T[E])2

Z = Probability of
Meeting Schedule
T(S) = Scheduled Duration
T(E) = Critical Path Duration

Z is derived from a table of predetermined probabilities

© 2006 John Wiley


PERT Activity Times & Variances
Activity

a

m

b

1-2

17

29


47

2-3

6

12

24

2-4

16

19

28

3-5

13

16

19

4-5

2


5

14

5-6

2

5

8

© 2006 John Wiley

t(e)


Variance of Activity Estimates
Activity

a

m

b

t(e)

1-2


17

29

47

30

2-3

6

12

24

13

2-4

16

19

28

20

3-5


13

16

19

16

4-5

2

5

14

6

5-6

2

5

8

6

© 2006 John Wiley


[(b-a)/6]2
Var


Possible Project Durations

TS=67
TE=64

© 2006 John Wiley


Z Table
Z Value

Probability

Z Value

Probability

-2.0

0.02

+2.0

0.98


-1.5

0.07

+1.5

0.93

-1.0

0.16

+1.0

0.84

-0.7

0.24

+0.7

0.76

-0.5

0.31

+0.5


0.69

-0.3

0.38

+0.3

0.62

-0.1

0.36

+0.1

0.54

© 2006 John Wiley


Gantt Charts
• The Gantt chart shows planned and actual progress
for a number of tasks displayed against a horizontal
time scale
• It is an effective and easy-to-read method of
indicating the actual current status for each set of
tasks compared to the planned progress for each item
of the set
• It can be helpful in expediting, sequencing, and

reallocating resources among tasks
• Gantt charts usually do not show technical
dependencies
© 2006 John Wiley

Chapter 8-14


Drawing Networks
• Activity-on-Arrow (AOA) networks use arrows to
represent activities while nodes stand for events
• Activity-on-Node (AON) networks use nodes to
represent activities with arrows to show
precedence relationships
• The choice between AOA and AON
representation is largely a matter of personal
preference

© 2006 John Wiley

Chapter 8-12


Hypothetical Network
3

1

2


5

4

© 2006 John Wiley

6


AOA Network Building Blocks
Activity

79

Install software

© 2006 John Wiley

Event

80


Partial Koll Business Center - AOA

1

A
Application
approval


2

B
Construction
plans

4

C
Traffic
study
D
Service
availability
check

3

© 2006 John Wiley

5


Partial AOA Network
3

X
1


A

C

2

1

3

2

1

2

4

(B)
4
C

X

E

X

C


B
A

4

(A)

B
A

B

3
(C)

© 2006 John Wiley

E

E


Partial AOA Network
4

B
A

1


X

C

2

E

3
D

(D)

B
1

A

2

C

4
X
3
D

(E)

© 2006 John Wiley


5

E
?

5

F


Full AOA Network
B
15 X
1

A
5
Legend
Activity
Duration

2

C
10

3

4

0

0

Y
5

E
15
F
10

D
5

© 2006 John Wiley

6

G
170

7

H
35

KOLL BUSINESS CENTER
County Engineers Design Department


8


Activity-on-Node Network Fundamentals
J, K, & L can all begin at
the same time, if you wish
(they need not occur
simultaneously)

J
A

B

C
K

A is preceded by nothing
B is preceded by A
C is preceded by B

L

(A)

M

(C)

but

All (J, K, L) must be
completed before M can
begin

Y

Y and Z are preceded by X

X

Z

Z is preceded by X and Y

Z

Y and Z can begin at the
same time, if you wish

Y

AA

AA is preceded by X and Y

X

(B)

(D)


© 2006 John Wiley


×