FOR COMMENT
A
Rev
Owner
16-Jan-13
Date
S.J Cho
Prepared
C.K Kim
Checked
Y.M Cho
Approved
For Comment
Details of Revision
AES-VCM MONG DUONG
POWER COMPANY LIMITED
Consultant
POWER ENGINEERING CONSULTING
JOINT STOCK COMPANY 2
Contractor
Doosan Heavy Industries & Construction Co., Ltd
PC
Project :
T10206
MONG DUONG II 2 x 560MW(NET)
THERMAL POWER PLANT
UAS
DN02
UNIT
P0
KKS
Title
COMMISSIONING PROCEDURE
FOR
11KV MV SWITCHGEAR OF SITE TEST
Document No.
BBG
Reg. No.
840001
Rev.
A
Pages –No.
T10206-DN02-P0BBG-840001
1 of 27
Rev. A
Table of Contents
1.0 GENERAL PURPOSE.............................................................................................. 4
2.0 INSPECTION AND TEST ITEM...............................................................................7
2.1 Scope 7
2.2 Code and Standard...................................................................................................................7
2.3 General test...............................................................................................................................7
2.4 Circuit Breaker test...................................................................................................................7
2.5 Current Transformer test...........................................................................................................7
2.6 Potential Transformer test.........................................................................................................7
2.7 Protection Relay test.................................................................................................................7
2.8 Meter & TD test.........................................................................................................................7
2.9 Di-electric Strength & Insulation Resistance test.....................................................................7
2.10 Check for Phase Sequence(After energizing)........................................................................7
2.11 NSPB(Non-Segregated Phase Bus duct)...............................................................................7
3.0 INSPECTION AND TEST METHODS......................................................................8
3.4 Potential Transformer test ; Confirm the following items........................................................11
3.5 Protective Relay test ; Confirm the following items................................................................12
3.10 Contact Resistance test for Breaker and Bus bar spouts.;..................................................13
3.11 NSPB(Non-Segregated Phase Bus duct).............................................................................14
3.12 NSPB – Insulation Resistance Test ; Confirm The Following Items....................................14
3.13 NSPB – Di-Electric Strength Test.........................................................................................15
4.0 RESULT OF CHECK SHEETS...............................................................................16
4.1 General test record.................................................................................................................17
4.2 Circuit Breaker Test Record....................................................................................................18
4.10 NSPB - Bus Duct Test Record..............................................................................................27
5.0 ATTACHMENTS..................................................................................................... 28
Attachment 5.1 SLD FOR #1 11KV SWGR A(P1BBA01)
Attachment 5.2 SLD FOR #1 11KV SWGR B(P1BBA02)
Attachment 5.3 SLD FOR #2 11KV SWGR A(P2BBA01)
Attachment 5.4 SLD FOR #2 11KV SWGR B(P2BBA02)
Attachment 5.5 SLD FOR INTAKE SWGR A(P0BBG03)
Page 2 of 27
Rev. A
Attachment 5.6 SLD FOR FGD 11KV MV SWGR(P0BBJ01, P0BBJ02)
Attachment 5.7 SLD FOR CHS, ASH, NSPB
(P0BBE01, P0BDD01, P1BDD01, P2BDD01, 11KV NSPB 3200A)
Page 3 of 27
Rev. A
1.0
1.1
GENERAL PURPOSE
Introduction and commissioning boundary
This procedure covers the activities required for testing and commissioning of the following
Overall 11kV MV SWGR system for Unit 1, 2, consist of the below table
1.2
KKS Number
Description
P1BBA01
11kV SWGR for UNIT 1 (BOP, BLR, TBN)
P1BBA02
11kV SWGR for UNIT 1 (BOP, BLR, TBN)
P2BBA01
11kV SWGR for UNIT 2 (BOP, BLR, TBN)
P2BBA02
11kV SWGR for UNIT 2 (BOP, BLR, TBN)
P0BBG03
11kV SWGR for Intake
P0BBJ01
11kV SWGR for FGD 1
P1BBJ01
11kV SWGR for FGD 1A
P1BBJ02
11kV SWGR for FGD 1B
P0BBJ02
11kV SWGR for FGD 2
P2BBJ01
11kV SWGR for FGD 2A
P2BBJ02
11kV SWGR for FGD 2B
P0BBE01
11kV SWGR for CHS
P0BDD01
11kV SWGR for ASH (Common)
P1BDD01
11kV SWGR for ASH UNIT 1
P2BDD01
11kV SWGR for ASH UNIT 2
-
11kV NSPB, 3200 A
Scope of Commissioning Package
The commissioning package for Overall 11kV MV SWGR system, consist of the following
packages :
KKS Number
Description
Page 4 of 28
Rev. A
1.3
1.3.1
P1BBA01
11kV SWGR for UNIT 1 (BOP, BLR, TBN)
P1BBA02
11kV SWGR for UNIT 1 (BOP, BLR, TBN)
P2BBA01
11kV SWGR for UNIT 2 (BOP, BLR, TBN)
P2BBA02
11kV SWGR for UNIT 2 (BOP, BLR, TBN)
P0BBG03
11kV SWGR for Intake
P0BBJ01
11kV SWGR for FGD 1
P1BBJ01
11kV SWGR for FGD 1A
P1BBJ02
11kV SWGR for FGD 1B
P0BBJ02
11kV SWGR for FGD 2
P2BBJ01
11kV SWGR for FGD 2A
P2BBJ02
11kV SWGR for FGD 2B
P0BBE01
11kV SWGR for CHS
P0BDD01
11kV SWGR for ASH (Common)
P1BDD01
11kV SWGR for ASH UNIT 1
P2BDD01
11kV SWGR for ASH UNIT 2
-
11kV NSPB, 3200 A
The Safety Knowledge in operation
Before the start of any testing it should be confirmed that all power supplies to the system have
been isolated or that they are in a known condition. The Commissioning engineer is
responsible for the safety of those personnel working of the system Check for the presence of
harmful electrical or mechanical potential energy before starting work.
1.3.2
Project lockout / Tagout(LOTO) procedures must be adhere to all test area.
1.3.3
Fire is strictly prohibited on site, no smoking there must be a warning mark in hazardous area.
1.3.4
Strictly comply with the safety and environmental protection regulations of local government.
1.3.5
In order to ensure the reliable operation of every part of the system, strictly obey the
corresponding procedures.
1.3.6
Have a regular maintenance for the long-time standby equipment
1.3.7
Obey the relevant safety regulations of the power plant during commissioning all along. Ensure
the successful commissioning work.
1.3.8
All personnel directly involved with the commissioning that will attend a kickoff safety meeting to
review for the dangers. Ensure that all personnel understand the process and the operation.
Page 5 of 28
Rev. A
Any personnel involved in the commissioning have the authority to terminate the operation at
any time, if a serious problem or safety issue develops.
Page 6 of 28
Rev. A
2.0
INSPECTION AND TEST ITEM
2.1
Scope
This procedure is applied for the site inspection and test of the overall 11kV MV SWGR
on site.
2.2
Code and Standard
- IEC 62271-2
- IEC 62271-1
- Specification & Drawing
2.3
General test
2.4
Circuit Breaker test
2.5
Current Transformer test
2.6
Potential Transformer test
2.7
Protection Relay test
2.8
Meter & TD test
2.9
Di-electric Strength & Insulation Resistance test
2.10
Check for Phase Sequence(After energizing)
2.11
NSPB(Non-Segregated Phase Bus duct)
Page 7 of 28
Rev. A
3.0
INSPECTION AND TEST METHODS
3.1
General test
- Visual inspection ; Confirm the following items
No
Procedure
Criteria
1
Check the arranged condition of all panels
2
Check the mounted conditions of each component
& device
3
Check the tightened condition of bolts & the
marking of bolts for tightening
4
Check the wire conditions
5
Check the color of panels, painting condition
6
Check the Labeling of Power, Control wiring and
panels.
Method
Approval Spec & Drawing
- Dimension inspection ; Confirm the following items
No
Procedure
Visual
Torque
wrench
Criteria
Method
1
Check the dimension of panel enclosure
Approval Spec & Drawing
- Wiring check for CT,PT ; Confirm the following items
No
Procedure
1
Check the wire spec, color and size
Criteria
Method
Visual
Approval Spec
& Drawing
2
Check the continuity of wiring for CT & PT circuit
- Wiring check for CT,PT ; Confirm the following items
- Check of the operational sequence ;
All control circuits shall be
checked in accordance with the
schematic drawing by simulation
at the rated voltage
No
Procedure
Criteria
1
Input control power(AC/DC)
AC 230V, DC220V
2
Check the Annunciation & lamp
3
Check the Circuit breaker operation
(Local & Remote Mode)
Approval Spec
Check the electrical interlock(2 Out of 3 interlock & Drawing
4
checks)
5
Visual
Buzzer Tester
Method
Visual & Operation
Check the external contacts
Page 8 of 28
Rev. A
3.2
Circuit Breaker test
No
Procedure
1
Check the structure, nameplate data
2
Check the manual charging operation
3
Check the manual close operation
(In the test position)
4
Check the manual trip operation
(In the test position)
5
Nameplate
& Shop Test Report
Visual
Approval Spec & Drawing
Visual
Test Instrument
Approval Spec & Drawing
Visual
Test Instrument
check (In the Test position)
Check the automatic charging operation
7
Check the manual close
(In the connection position) and automatic
charging
8
Check the manual trip operation
(In the connection position)
9
Check the insulator
10
Check the circuit and contact
3.3
Method
Repeat 3 times close/open operation
6
11
Criteria
Operation characteristic Test
open : less than 40ms
close : less than 60ms
Time difference between
phase and phase :
less than 4ms
Current Transformer test ; Confirm the following items
No
Procedure
1
Verification with manufacturer's test certificates,
nameplates details etc
2
Ratio check
3
Polarity check
Subtractive
Check the continuity of wiring for CT
secondary circuit and ground connection
CT Excitation Test(To be performed with
CT which is used for protection relay)
Approval Spec
& Drawing
4
5
6
CB analyzer
(Refer to Note 5)
Insulation test on secondary winding
(Using DC 500V Megger)
Criteria
Approval
Drawing
Spec
Approval Spec
Above 5
Method
&
Visual
CT Tester
(Refer to Note 1)
CT Tester or
Polarity checker
(Refer to Note 1, 2)
Visual
Buzzer tester
CT Tester
(Refer to Note 1)
Megger or CT Tester
(Refer to Note 1)
Page 9 of 28
Rev. A
▣ Note 1 : Test method for CT
- Safety Precaution
1. Wear the insulation glove, shoes and helmet.
2. Install the safety tape around test site.
- Test method
1. Make connections per diagram.
2. Select run test
3. Select resistance, excitation & ratio test
4. Select voltage and current range
5. Set Name Plate Ratio
6. Select default Test Note
7. Start test
8. Print test results
▣ Note 2 : Polarity check method for PT
1. Verify that the current transformer is being isolated from power source.
2. Make test setup as shown above.
A 6 10 V lantern-type battery can be used as DC voltage source.
3. Watching the analog-type meter, apply DC voltage momentarily by using the switch.( An analog-type
milli-ammeter or milli-voltmeter can be used on this test)
4. Record the polarity of current transformer.
Page 10 of 28
Rev. A
3.4
Potential Transformer test ; Confirm the following items
No
Procedure
1
Verification with manufacturer's test
certificates, nameplates details etc
2
Ratio check
- PT Primary voltage input and measuring of
secondary output
3
Insulation test(Using DC 500V Megger)
- Secondary- Ground, Primary-Ground
Criteria
Method
Visual
Approval Spec
& Drawing
2nd ; above 5 MΩ
1st ; above 50MΩ
Primary voltage
injection
(Refer to Note 3)
Megger
▣ Note 3 : Ratio check method for PT
After connecting the power supply to primary winding, read the primary voltage V1
and induced secondary voltage V2, Calculate the ratio with readings and record it
on attachment 1.
▣ Note 4 : Polarity check method for PT
Connect the circuit as follows(see Fig.2).
Close the switch(SW1) momentarily and observe the deflection of voltmeter(V). If
polarity is in accordance with terminal marking, voltmeter will deflect momentarily
to upscale when switch is closed.
Page 11 of 28
Rev. A
3.5
Protective Relay test ; Confirm the following items
No
Procedure
Criteria
1
Verification with manufacturer's test
certificates, nameplates details etc
2
Check the continuity of wiring
3
Check the set value of each output
contact and indications
4
Check the measuring values of display
5
Operation test
- According to the commission method
3.6
Buzzer tester
Approval Spec
& Drawing
Visual
Secondary injection
Relay tester
Meter test ; Confirm the following items
Procedure
Criteria
Method
1
Verification with manufacturer's test
certificates, nameplates details etc
2
Check the bolts, fittings, mountings
3
Check the enclosure for crack & integrity
Operation test
- Apply voltage or current to Test Termianl Block
- Check the measuring values
Approval
Visual
Spec
Relay tester
& Drawing
Secondary
injection
TD test ; Confirm the following items
No
1
Visual
recommended by Relay manufacturer
No
3.7
Method
Procedure
Criteria
Method
Verification with manufacturer's test
certificates, nameplates details etc
2
Check the bolts, fittings, mountings
3
Check the enclosure for crack & integrity
Operation test
- Apply voltage or current to CTT,PTT
- Check the measuring values
Visual
Approval Spec
Relay tester
& Drawing
Secondary injection
Page 12 of 28
Rev. A
3.8
No
1
2
3
3.9
No
Di-electric Strength & Insulation Resistance test ; Confirm the following items
Procedure
Insulation Resistance test
- This test conduct brefore and after
dielectric test using DC1000V Megger
※ Test Condition
- All electronic devices are disconnected
and C.T secondary circuits shorted.
- All CB is connected position and Close
- The fuse of PT is removed.
Di-electric Strength test
Main busbar parts and earthing bus bars
will be tested with the following voltage
for 1 minute
- Earth to phase : 30kV DC
- Phase to phase : 30kV DC
※ Test Condition(Common)
- All electronic devices are disconnected
and C.T secondary circuits shorted.
- All CB is connected position and Close
- The fuse of PT is removed.
2
Check the Phasing out between sources
1
2
Megger Tester
Criteria
Clock-wise
Reference only
Method
Phase Detector
Power Analyzer
Contact Resistance test for Breaker and Bus bar spouts.;
Confirm the following items
Procedure
Criteria
Method
Verification with manufacturer's test
certificates, nameplates details etc
Check the 1st and 2th part's connection
condition between breaker to bus bar
3
Connect the contact resistor.
contact resistance of Breaker
will tested with the following ampare
- phase to ground
; Above 50
- Phase to phase
; Above 50
Disruptive discharge
should not be
occurred
Procedure
Check the Phase sequence
No
Method
Check for Power Quality(After energizing)
1
3.10
Criteria
- input ampare : DC 100A
- Standard value
Contact resistance
: 100uΩ
tester
Page 13 of 28
Rev. A
▣ Note 5 : check method for Operation Characteristic Test
1. Check operating rightly by close, open CB in local /remote condition.
2. Earth by connecting earth wire to earth terminal of test equipment.
3. Connect main contact connection jack to main contact connection terminal and
then connect main contact wire to both ends of ES or bushing.
4. One end of close, open source connection jack connect to test equipment and
the other end connect to close, open terminal of VCB terminal
5. Figure out property data by operating circuit breaker(Operate over 3 times manually)
5.1 open : less than 40ms
5.2 close : less than 60ms
5.3 Time difference between phase and phase : less than 4ms
3.11
NSPB(Non-Segregated Phase Bus duct)
- Visual inspection ; Confirm the following items
No
Procedure
1
Arranged condition of Transformer
2
Mounted conditions of fix bolt
Criteria
Method
Approval Spec & Dwg
Visual
3
Tightened condition of bolts connections
4
Check the cleanliness of Transformer
3.12
No
1
NSPB – Insulation Resistance Test ; Confirm The Following Items
Procedure
Insulation Resistance test
- Measure of insulation resistance
- Using DC1000V Megger
※ Measured points
- Line to Line
- Phase to earth
Criteria
Method
; Above 50
Megger Tester
Page 14 of 28
Rev. A
3.13
NSPB – Di-Electric Strength Test
No
Procedure
Criteria
Method
Di-electric Strength test
Apply the test voltage between each
1
electrically isolated
Disruptive discharge
should not be
- Earth to phase
occurred
DC dielectric tester
- Apply to table #1
- Phase to phase
#Table 1
Rated Voltage
Specified Value
600V or below
2500V
11kV
28000V
Auxiliary circuit
1500V
Apply Time
Remarks
1 Minute
Page 15 of 28
Rev. A
4.0
RESULT OF CHECK SHEETS
4.1
General Test Record
4.2
Circuit Breaker Test Record
4.3
Current Transformer Test Record
4.4
Potential Transformer Test Record
4.5
Protection Relay Test Record
4.6
Indicating Meter With Transducer Test Record
4.7
Transducer Test Record
4.8
Di-electric Strength & Insulation Resistance Test Record
4.9
Di-electric Strength & Insulation Resistance Test Record
4.10
NSPB – Bus Duct Test Record
Page 16 of 28
Rev. A
4.1
General test record
GENERAL TEST RECORD
(ECTR-E-COM-010A)
Sub
contractor
LS Industrial Systems Co., Ltd.
Equipment Description
Locatio
n
DWG
NO.
Contractor
Doosan Heavy Industries & Construction
Co., Ltd.
KKS NO.
Sheet NO.
TEST DATA
NO.
ITEMS
1
Visual Inspection
RESULT
REMARK
Check the arranged condition of all panels
Check the mounted conditions of each component & device
Check the tightened condition of bolts & the marking of bolts for
tightening
Check the wire conditions
Check the color of panels, painting condition
Check the Labeling of Power, Control wiring and panels.
2
Check the dimension, wire spec, color and size of panel enclosure
3
Check the continuity of wiring for CT & PT circuit
4
Operational sequence test
Check for control power line to supply power by multi-meter
Clsoe & open test for circuit breaker in test positon according to
sequence
Clsoe & open test for circuit breaker in run positon according to
sequence
Indicating lamp check according to operation condition of ciruit
breaker and fault
Electrical interlock check between upstream and downstream/each
other
Binary input & output check for protection relay
Trip test of MCCB by test button
Trip test of protection relay by relay tester
External contacts check(open & close condition)
NO.
TEST EQUIPMENT
CONTROL NO.
DUE DATE
1
Prepared by LSIS
DATE
NAME
SIGN.
Page 17 of 28
Rev. A
4.2
Circuit Breaker Test Record
CIRCUIT BREAKER TEST RECORD
(ECTR-E-COM-010B)
Sub contractor: LS Industrial Systems Co., Ltd.
Equipment Description : MV SWGR(SWGR No)
Contractor: Doosan Heavy Industries & Construction Co.,
Ltd
Document No.
Q-SITP-010
Location
DWG No.
Single Line DWG
KKS NO.
BREAKER NAME PLATE DATA
Manufacture
Type
Rating(Amps)
Serial Number
Operating
Voltage(V)
TEST DATA
1. Check The Breaker Rating and Identification Number is corrected
2. Insulation Resistance( )/Using by 500V Megger
Performed by(LSIS)
Date
Ambient
Breaker Closed
Breaker Opened
L1
L2
L3
Temperature
L1
L2
L3
L1-L2
L2-L3
L3-L1
℃
Pri - Sec
Pri - Sec Pri - Sec
Test Value
3. Operation Mechanism Check
Performed by(LSIS)
Date
3.1 Manual Charging Operation
3.2 Manual Close Operation (In the Test position)
3.3 Manual Trip Operation (In the Test position)
3.4 Repeat 3 times Close/Open operation check (In the Test position)
3.5 Automatic Charging
3.6 Manual Close (In the Connection position) and Automatic Charging
3.7 Manual Trip Operation (In the Connection position)
3.8 Insulator Inspection
3.9 Circuit and contact Inspection
3.10 Breaker Mechanism is correct and No Wear and Damage
3.11 Lubrication is Correct in Accordance with Manual
Performed by(LSIS)
Date
4. Operation Characteristic Test
order
1
2
3
4
work
Mesure CB trip time
Mesure CB close time
Mesure CB time difference
between phase and phase
cretia
less than 40ms
less than 60ms
Open
less than
4ms
Close
Attatch Time (open) record
Measure
Judgement
Attatch Time (Close) record
Performed by(LSIS)
4. Restoration
(CB and its circuit are restored to original configuration.)
Test Equipment
Control No.
Cal. Due Date
Performed by(LSIS)
Verified by(
)
Name/Signature
Date
Name/Signature
Date
Approved by
Date
Date
Page 18 of 28
Rev. A
4.3
Current Transformer Test Record
CURRENT TRANSFORMER TEST RECORD
(ECTR-E-COM-010C)
Sub contractor: LS Industrial Systems Co., Ltd.
Contractor: Doosan Heavy Industries & Construction Co., Ltd
Document
No.
DWG No.
KKS NO.
Equipment Description : MV SWGR(SWGR No)
Location
Single Line DWG No.
Nameplate Ratio :
Serial No.
Q-SITP-010
Used For(Meter or Relay No.):
Rφ:
Yφ:
Bφ:
TEST DATA
1.
Visual
Inspection
Current transformer is installed
satisfactory.
2. Ratio Tests
Accuracy Class :
Calculated Ratio :
Accept Error ≤ ±
3. Polarity Tests
Performed by(LSIS):
□Volt
Rφ
Date
:
%er
r
rati
o
%err
Date
:
Date :
Performed by(LSIS):
Date :
5. Insulation test on secondary winding(Using DC 5000V Megger)
%er
r
□ Additive
□ Subtractive
Performed by(LSIS):
rati
o
□Not Required
Bφ
Yφ
rati
o
Polarity Test Result
Measured Ratio
Single Tap
Multi
Tap
[%]
Check Applied Method
Check Applied Method :
Performed
by(LSIS):
4. Secondary Circuit and ground connection Check
All secondary winding - Ground : Accept : Above 5
Performed by(LSIS):
6. Restoration :
Date :
CT and its circuit are restored to original configuration.
Test Equipment
Performed by(LSIS):
Control No.
Due Date
Verified by(
Date:
)
Name/Signature
Date
Approved by
Name/Signature
Date
Page 19 of 28
Rev. A
4.4
Potential Transformer Test Record
POTENTIAL TRANSFORMER TEST RECORD
(ECTR-E-COM-010D)
Sub contractor: LS Industrial Systems Co., Ltd.
Contractor: Doosan Heavy Industries & Construction Co., Ltd
Equipment Description : MV SWGR(SWGR No)
Location
Single Line DWG No.
Document No.
DWG No.
KKS NO.
Q-SITP-010
Used For(Meter or Relay No.):
NAMEPLATE DATA
MFGR.:
Insu.Rating[BIL]:
Nominal Ratio :
Accuracy Class :
Serial No.
Rφ :
1. Visual Inspection
[kV]
Yφ :
TEST DATA
Rated Pri .Volt:
[V]
Thermal Rating :
at
[℃]
Bφ :
[VA],
Potential transformer is installed satisfactory.
2. Ratio and Polarity
Performed by(LSIS) :
Date :
Performed by(LSIS) :
Date :
Ratio
Rφ
Yφ
Bφ
3. Insulation test on Primary & Secondary winding with ground.
Readings
All secondary winding – Ground : Accept: above 5 MΩ(Using DC 5000V Megger)
All primary winding – Ground : Accept: above 5 MΩ(Using DC 5000V Megger)
Performed by(LSIS) :
4. Restoration Completed
Performed by(LSIS) :
Date :
Date :
Remark :
Test Equipment
Control
No.
Due Date
Date
Approved by(
Verified by(
)
Name/Signature
)
Name/Signature
Date
Page 20 of 28
Rev. A
4.5
Protection Relay Test Record
Protection Relay Test Record
(ECTR-E-COM-010E)
Sub contractor: LS Industrial Systems Co., Ltd.
Equipment Description : MV SWGR(SWGR No)
Location
Single Line DWG No.
Manufacturer
Relay Description :
C.T Ratio
Type or Model
P.T Ratio
Contractor: Doosan Heavy Industries & Construction Co., Ltd
Document No.
Q-SITP-010
DWG No.
KKS NO.
NAMEPLATE DATA
Serial No.
TEST DATA
Rated current
1. Visual Inspection
2. Mashalling-Trip Relay
3. Mashalling-LED Indications
4. Measuring Values
Injection
[Current/Voltage]
50% [0.5A/31.8V]
R:
75% [0.75A/47.6V]
R:
100% [1A/63.5V]
R:
5. Secondary injection test
Setting
Test Item
tap/time
50
Test
Value(%)
100
110
110
I2 *3
I2 *3
Standard
time(Sec)
R/Y/B
I Motor
Start
* 0.9
Actual
time(Sec)
R/Y/B
200
300
I Motor
Norminal
*5
G
G
G
R/Y/B
R/Y/B
46
49
51LR
Test
Phase
R/Y/B
R/Y/B
R/Y/B
R/G
Test
Value(%)
200
200
300
500
200
200
200
100
100
/
/
/
Actual
time(Sec)
50G(N)-2
50G(N)-1
50G(N)
27
59
81
87M
87L
Y:
Y:
Y:
Tolerances
Standard
time(Sec)
R/Y/B
Setting
tap/time
Test
Phase
R/Y/B
51
Test Item
/
/
/
Measuring Values
Current[A] / Voltage[kV]
/
B:
/
B:
/
B:
N:
N:
N:
/
/
/
1% of measured
value or 0.5% of
I / VNom
Pick-up
(A or V)
Drop-out
(A or V)
Pick-up
(A or V)
Drop-out
(A or V)
□ Check the
66 Trip &
Restart Inhibit
R/Y/B
66
6. Results
:
Remarks :
Test Equipment
Tested by(LSIS) :
Control No.
Due Date
Date :
Verified by(
)
Name/Signature
Date
Page 21 of 28
Rev. A
Approved by
Name/Signature
Date
Page 22 of 28
Rev. A
4.6
Indicating Meter with Transducer Test Record
Indicating Meter with Transducer Test
Record(ECTR-E-COM-010F)
Sub contractor: LS Industrial Systems Co., Ltd.
Contractor: Doosan Heavy Industries & Construction Co., Ltd
Equipment Description : MV SWGR(SWGR No)
Document No.
Q-SITP-010
Location
DWG No.
Single Line DWG No.
KKS NO.
1.
NAMEPLATE DATA
Type or Model
P.T Ratio
Manufacturer
C.T Ratio
TEST DATA
Visual Inspection
1.1 Instrument is de-energized/Check the nameplate data
1.2 Bolts, Fittings, Mountings are tightened
Serial No.
Accuracy
1.3 Check the enclosure for crack & integrity
2.
Description
Rating
Current
transformer
for metering
Voltage
transformer
for metering
Performed by(LSIS):
Date :
Expected
Value
Actual
value
Phase
Injected
Value
R
0.25A
Y
0.25A
B
0.25A
R
0.5A
Y
0.5A
B
0.5A
R
1A
13200/
110
Error(%)
Remarks
1A
Y
B
R-Y
1A
1A
110V
110V
110V
P(MW)
Y-B
B-R
--
Q(MVAR)
--
S(MVA)
--
Performed by(LSIS):
F(HZ)
--
--
PF(%)
--
KWH
KVARH
--R
R
R
Current
transducer
3.
Calibration by secondary injection
--
1A/110V
36.9Deg(5
Min)
0A
0.5A
1A
Date :
Restoration is completed
Performed by(LSIS):
Remarks :
Test Equipment
Control No.
Due Date
Date :
Verified by(
)
Name/Signature
Date
Approved by
Name/Signature
Date
Page 23 of 28
Rev. A
4.7
Transducer Test Record
Transducer Test Record
(ECTR-E-COM-010G)
Contractor: Doosan Heavy Industries & Construction Co.,
Ltd
Sub contractor: LS Industrial Systems Co., Ltd.
Equipment Description : MV SWGR(SWGR No)
Location
Single Line DWG No.
Manufacturer
C.T Ratio
Document No.
Q-SITP-010
DWG No.
KKS NO.
NAMEPLATE DATA
Type or Model
Serial No.
Accuracy
P.T Ratio
TEST DATA
1.
1.2 Bolts, Fittings, Mountings are tightened
1.3 Check the enclosure for crack & integrity
2.
Performed by(LSIS):
Calibration by secondary injection
Description
Rating
3.
1.1 Instrument is de-energized/Check the nameplate data
Visual Inspection
Phase
Injected
Value
Expected
Value
Actual
value
Error(%)
Remarks
Performed by(LSIS):
Restoration is completed
Date :
Date :
Performed by(LSIS):
Date :
Remarks :
Test Equipment
Control No.
Due Date
Verified by(
Name/Signature
Date
Name/Signature
Date
)
Approved by :
Page 24 of 28
Rev. A
4.8
Di-Electric Strength & Insulation resistance Test Record
DI-ELECTRIC STRENGTH &
INSULATION RESISTANCE TEST RECORD
(ECTR-E-COM-010H)
Sub contractor: LS Industrial Systems Co., Ltd.
Contractor: Doosan Heavy Industries & Construction Co., Ltd
Equipment Description : MV SWGR(SWGR No)
Location
Amb. Temp.
Document No.
Q-SITP-010
Single Line DWG
Humidity(%)
DI-ELECTRIC STRENGTH TEST DATA
Circuit
Test condition
Duration
(Min)
Test
Volt
Judgement
(Disruptive discharge
should not be occurred)
Remarks
1 Min.
30kV
1 Min.
30kV
1 Min.
30kV
CB is closed.
R-Y+B+E
PT is opened.
CT is shorted.
CB is closed.
Y-B+R+E
PT is opened.
CT is shorted.
CB is closed.
B-R+Y+E
PT is opened.
CT is shorted.
Performed by(LSIS):
Date :
INSULATION RESISTANCE TEST DATA
Circuit
Test condition
Test
Acceptance Criteria
Test Results(GΩ)
R-Y+B+E
Before
Di-electric
DC 1000V
Y-B+R+E
Before
Di-electric
DC 1000V
B-R+Y+E
Before
Di-electric
DC 1000V
R-Y+B+E
After
Di-electric
DC 1000V
Y-B+R+E
After
Di-electric
DC 1000V
B-R+Y+E
After
Di-electric
DC 1000V
50MΩ Above
Performed by(LSIS):
Date :
Remarks
Test Equipment
Control No.
Due Date
Verified by(
)
Name/Signature
Date
Approved by
Name/Signature
Date
Page 25 of 28