METHOD STATEMENT FOR PAINTING WORK

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (18.62 MB, 152 trang )

Riviera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

Riviera Point Project

METHOD STATEMENT
FOR
PAINTING WORK

Relevant part reviewed by

Checked by

Prepared by
Dept.
JY Lee

QC/QA

Safety.

Construction.

Engineering.

H Thu

A Duc


OJ Cho

YC An

Approved (by)
Rev

Date

Description
Ssangyong

ICIC

KLV Safety

RPLLC

A

3-Jun-2013

Issue for Acceptance

SC Park

M.Tan

Bernarrd


CM Leong

B

11-Jul-2013

Issue for Acceptance

SC Park

M.Tan

Bernarrd

CM Leong

C

20-Aug-2013

Issue for Acceptance

SC Park

M.Tan

Bernarrd

CM Leong


Project : Riviera Point Condominium Development
Produced by : Ssangyong E&C
Assessment Duration : 7days
Document No. : Refer to the submital list.


Document Reference and Revision:

Comment of MOS for painting work_RevB

Submission Description:

Comment of MOS for painting work_RevC

Doc
Rev

Comment
No.

Reviewer’s Name
and Company

Comments

1

Duc, RPLLC

Based on pages 4/96 & 49/96, please clarify material use exterior

putty, it is Jotun or Seamaster?

2

Duc, RPLLC

Page 5/96, mixing and stirring process shall be ready inside floor area.

3

Duc, RPLLC

How to check and control the density for layers (skim coating, sealer &
coating). What is specify in our contract?

4

Duc, RPLLC

Page 12/96, item 30 “to ensure surface obtain good covering, uniform
color and smooth” please specify cover method?

5

Duc, RPLLC

Page 14/96 please separate method statement for gondola installation
work.

Duc, RPLLC


To provide:
-Protection method to material during rainy days not specify.
-Tool to check humidity.
-How large of area that will be applied for each inspection storey floor?
-Internal inspection form?
-Gondola installation work & equipment used, please to submit
separately?
-By gondola using: please to draw out what are work sequence :
transfer material, mixing proportion and application… where are access
for workers to external RC wall. How large for each applicable batch.
-How is groove line work to RC wall?

A

6

Project: Riviera Point Project
Document No: RP_MOS _P _SSY_ 02
Date: 31 Jul 2013
Produced by: Leong

Submission Date:

04 June 2013
12 July 2013
20 Aug 2013

Contractor’s Reply (and J.Y.Lee)
Jotun exterior Putty is right.

In case, side wall on gondola is impossible to be
supplied from each floor, that’s why the mixing
bucket should carry on gondola from ground.
By visual checking and controlling the dilution while
mixing to water & putty or paint.
In order to check for density, paint layers will be
checked by the tool of wet film thickness.
By visual checking and controlling the dilution while
mixing to water & putty or paint.
It will be submitted on September.
Now the painting Method is focused on Mock up
room.
- Protection for painted surface has no solution when
it rained, however, before applying paint, the rain
possibility will be presumed that checking humidity by
phychro-meter, also refer to the national weather
forecast, based on that we will get decision to
proceed.
- Checking tool of the surface humidity shall be used
by moisture-meter.
- Inspection is normally conducted 3-5 point per wall.
- Inspection form is inserted at the end of annex 2.
- Method statement of gondola installation work shall
be submitted on September.
- Gondola usage needs to show for the gable wall
painting situation that shall be proceeded from top to
bottom. And materials shall be loaded from bottom .
then also , mixing proportion shall be carried out on
gondola because it can be loaded till 700kg and has



7

Vuong, RPLLC

Page contents: what is meaning “please! Refer to the MS for tower
crane (General)”, please

electric outlet. The maximum size of gondola is
0.8mx7.5m. Those information can be referred to the
presentation data for working platform of architectural
works. Workers shall be taken on the ground floor.
Each painting session of area is normally 3-5 points
checking for a wall.
- Groove line’s substrate will be treated on
architectural cage after that putty and painting work
is on gondola.
-It is corrected.
-Please refer to presentation data for working
platform of architectural cage, there has description
of gondola usage.

8

Vuong, RPLLC

Page 6/96, please check external mock up painting have ceiling or not.

The external ceiling is the balcony ceiling.


9

Vuong, RPLLC

Page 17/96, where is method statement of Jotun Exterior Putty.

It has been described on annex 1.1 and 1.2.

10

Vuong, RPLLC

Please re-check item 5.2.3, Ssy will use external putty for internal wall
& ceiling, it is correct or not?

Paint for internal surface: Using Jotun Interior putty. It
is corrected.

11

Vuong, RPLLC

Please re-check item 5.2.3, Ssy will use Jotasealer Primer for internal
wall & ceiling, it is correct or not? Because the product is used for
external.

It is corrected by proper product name, both name
are slightly different between Jotasealer 03 for
external and Jotasealer primer for internal.


12

Vuong, RPLLC

Page 34/96, please revise 3 stage, it is 1 layer not 2
comment for page 39/96.

13

Bernarrd/ Minh,
RPLLC

Please provide the completed content as stipulated in MS guideline
page 2

It is corrected.

14

Bernarrd/ Minh,
RPLLC

Please provide RA, JSA to the relevant work scope accordingly.

It is inserted.

15

Bernarrd/ Minh,
RPLLC


Please provide the current organization chart.

It shall be submitted separately by official submission
because the subcontractor would be changed.

16

Bernarrd/ Minh,
RPLLC

Please provide the PPE listing as to the proposed work scope.

It is inserted.

rd

Project: Riviera Point Project
Document No: RP_MOS _P _SSY_ 02
Date: 31 Jul 2013
Produced by: Leong

st

nd

layer. Same

It is corrected.



17

Bernarrd/ Minh,
RPLLC

Please provide material safety data sheet (MSDS) in relationship to all
material to be used as proposed in this method.

It is inserted at annex.

18

Bernarrd/ Minh,
RPLLC

Do not allow to carry out mixing skim coat on scaffold (page 33/96).

It is corrected.

19

20

Tan, ICIC

Tan, ICIC

Jotasealer Primer is internal Primer, why did you apply it for exterior
painting work (item 21 – page 9/96)

Based on technical data of Jotun Exterior Putty mixing ratio of putty
and water is 3:1 by weight. It means that 1 bag/40kg of putty will be
mixed with 13 litres of water, why did your MOS indicate 16 litres of
water?

Based on technical data of Jotun Exterior Putty and Jotun Internal
Putty, the drying time of them is different one recoated after 8 hours
and another is 24 hours. So please separate.

21

Tan, ICIC

22

Tan, ICIC

Based on technical data of Jotasealer, mixing sealer with the thinner
maximum 5%, please comply.

23

Tan, ICIC

Item 27 - page 11/96: technical data did not indicate it, please explain
and get advice of manufacturer.

24

Tan, ICIC


Item 5,6 - page 23/96 Item 9 - page 24/96 Item 19 - page 27/96: Why
did you apply Jotun Exterior Putty for internal painting?

25

Tan, ICIC

26

Tan, ICIC

Project: Riviera Point Project
Document No: RP_MOS _P _SSY_ 02
Date: 31 Jul 2013
Produced by: Leong

This MOS only mentioned to Jotun Putty whether there is any
difference (ex: consumtion, application sequence, mixing…) if you use
Seamaster Putty?
This MOS did not indicate details of Gondola, so you are required to
submit separately for Gondola.

It is mis-naming for Jotasealer primer of external
wall, So, proper brand name is Jotashield primer
those are slightly different of spelling. And internal
primer’s name is Jotasealer 03, Those brand names
are also very similar but different from internal thing.
Confirmed dilution ratio: 40Kg Putty/ 13 litres of water
for normal case.

We need extra water, in case the plain surface is too
dry so that it can get adequate adhesion.
The standard drying duration is indicated on
technical data sheet. However, its time depends on
the condition on humidity & windy. The other words,
inside areas there are times to get higher humility
and less ventilation than outside one, in this case,
the drying time should be adjusted by crafts mas’
perception on each job’s detail.
It will be complied as technical data sheet.
Supplier confirmed that when the paint comes to dry
in the bucket over 2 hour, water should be added in it
in order to keep the proper viscosity.
It’s typo, it’s corrected.
It’s the only putty material in this work and
consumption, application, sequence, and mixing
information is indicated on the statement and
annexes, especially on technical data.
It will be submitted on September.


27

Tan, ICIC

There will be some location where you can not use Architecture
working cage and Gondola for painting work. So could you tell us you
intend to use Spider man for painting work if any you have to get
approval from RP client.


The remained external area can be accessed all
around because the gondola can adjust to approach
with extension by 1.7m.
It shall be able to controlled how finished topcoat is
by ;
o Apply fully paint system as proposed and got
approved.
o Carefully check the surfaces right after applying
the primer coat, polish or make even (if need)
o While applying each layer of top coats, It shall be
strictly exam the worker’s diluting the paint and
water (with ratio as proposed in Technical Data
sheet) to avoid the result of finished layer too thin.
It could incur some damage very soon. So we will
try to reduce it also.
o After completion of applying, check about colour
and aesthetic for the finalization.

28

Duc, RPLLC

Reply item 4: not cleared.

29

Vuong, RPLLC

No more comment.


30

Bernarrd, RPLLC

No more comment.

31

Tan, ICIC

Reply item 23: Please provide official confirmation of supplier.

It is attached on annex of certification.

32

Tan, ICIC

Reply item 25: what have difference between Jotun putty and
Seamaster putty? As this MOS did not mention to Seamaster putty?

Both are same performance to make proper
substrate. It isn’t indicated the name anymore as
reply no. 1.

B

Reviewer’s suggested status code for this revision only:
ICIC Consultant


TYLIN Structural
Review Consultant

JRP MEP Review
Consultant

KPK Cost
Consultant

Other (state)

Other (state)

Other (state)

RPLLC

This section is to record the reviewing party’s suggested status code only: the official status code for the submitted item is recorded on the first sheet of this document.
Project: Riviera Point Project
Document No: RP_MOS _P _SSY_ 02
Date: 31 Jul 2013
Produced by: Leong


Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

CONTENTS


* ANNEXS

1 ………………………………………………………. RA & JSA
2 ………………………………………………………. Organization Chart
3 ………………………………………………………. Drawings
4 ………………………………………………………. Specifications
5 ………………………………………………………. Certification
6 ………………………………………………………. MSDS
7 ………………………………………………………. Special Toolsl

Project:Rivera Point Condominium Development
Produced by:Ssangyong E&C
Preparing Duration :7days
Revision: A


Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

1. SCOPE
This method statement is for the Painting work.
The working Platform and Gondola will be installed step by step, safely fulfilling as
the installation plan by special team based on each method statement.

2. GENERAL PRECAUTIONS
To avoid dangerous and expensive consequences, the following points should be
observed :

 All operations should be carried out by special team, under the immediate
supervision of an SSang-yong safety dept.
 For the applying process, a roped -off area is required .The area should be
large enough to permit the components to be stacked and handled, and the
applying to be without Interfering site activities and risking the other site
personnel. Sufficient area must be set aside for the high position work.

3. EQUIPMENTS AND TOOLS / TACKLES
 Gondola & Scaffolding :
 For treatment of substrate at the external wall surface.
 For applying of paniting materials such as Skim coat, Putty, Primer, Paint at
the external wall.
 Hand tool :
 All tools and tackles supplied by special team under supervision of Ssangyong safety dept.

Project:Rivera Point Condominium Development
Produced by:Ssangyong E&C
Preparing Duration :7days
Revision:C

SsangYong E&C

7/152

19.08.2013


Rivera Point Condominium Development
DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,

HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

 List of equipment :
No.

Material Name

Type

Unit

Notes

1

Accessories (Brush,
roller, hammer,
chisel, wire brush)

many

EA

many

2

Floor grinder

portable


EA

1

3

Vacumn Cleaner

portable

EA

1

4

Air Hose

PVC

M

100

5

Harness

Full body type


Set

30

6

Glove

Anti Chemical rubber
coated glove

EA

30

7

Mask

Dust filteringTextile mask

EA

30

8

Shoes


Anti chemicalankle shoes

EA

30

9

Safety helmet

C, G, E

EA

30

4. RESOURCES (Materials, Equipments & Human Resources)
4.1. List of material
No.

Material Name

Type

Unit

Notes

1


Water

Clean

liter

plenty

2

Jotun Ext Putty

Pre coat

m2/kg

0.8

3

Jotashield Primer

1st coat

m2/kg

9.1

4


Jotashield

2nd coat

m2/kg

5.5

5

Jotun Int Putty

Pre coat

m2/kg

0.8

6

Jotasealer 03

1st coat

m2/kg

9.2

7


Jotaplast

2nd coat

m2/kg

5.0

Project:Rivera Point Condominium Development
Produced by:Ssangyong E&C
Preparing Duration :7days
Revision:C

SsangYong E&C

8/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5. Organization
 It is indicated at the annex 2.

5. APPLYING PROCEDURE
5.1. Flow Chart

 Procedure of Installing bracing.

Material Preparation
Inspection
by
Ssy QC mngr

YES
Working Platform
Installation
NO
YES
Surface preparation

Inspection
by
S.A.C

Fine Tune

1st Skim coat or Putty

2nd Skim coat or Putty
Surface sending

Inspection
by
SSY QC

YES

Repeating

Primer
Drying
1st finish coat

2nd finsh coat
NO
YES
NO
FINE-TUNE

Inspection
by
ICIC / KPL

YES
Final Touch up
NO
FINE-TUNE
YES
Painting complete

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C


9/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5.2. Description of working sequence.
5.2.1 External Mock up painting
1) Surface must be dried. To ensure moisture substance not exceeding
20%.
 Checking with Moisture Meter.
2) To remove foreign and unstable matters such as dirt powder, cement
splashes and other contaminants.
 Manual cleaning by chipping, scrapping or wire brushing.

3) Surface must be free from oil and grease.
 Wiping with cloth dampened solvent.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

10/152


19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4) Surface must be free from algae of fungus growth.
 Fungicidal washing.
5) Use Jotun Exterior Putty to apply as plastering.
 Jotun Exterior Putty.

6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water.
 By volume.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

11/152

19.08.2013


Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

7) Use a mixer if available or adequate mixing equipment to mix for 5
minutes until homogeneous.
 By drill mixer or pump mixer.

8) Allow the mixtures to stand for about 10 minutes then mix again until
homogenous. Ready plaster should be used within 2 hours after mixing.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

12/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st
coat.

 Patching by trowel only.

Scaffolding

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

13/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

10) Wait for 8-16 hours or until the surface is partially settled then apply a
2nd coat.
 Visual and manually checking
11) Sanding after surface dry (3h for minimum applying putty).

Scaffolding

12) Interval time for every coat is 8-16 hours at 30oC, minimum.
13) To ensure in order to obtain an even surfaces and reduce roughness.

14) To ensure surface is dry and stable.
 Visual and manually checking

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

14/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

15) Sanding the surface to give a smooth and even finish so as to give an
aesthetics appearance.
 Checking by visual and appropriate equipments

16) To ensure surface is smooth and even.
 Sanding with appropriate sand paper.
17) To ensure surface is dry, clean and stable.
 Checking by visual and appropriate equipment
18) Proceed coating system as from sealer coat to finishing coat.
 Refer to coating system data.

19) Please refer to Method Statement of Jotun Exterior Putty.
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

15/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

(Painting should start preferably within 24 hours after preparation. If
any delay, surface must be checked and re-preparation again if
contain other contaminants.)
20) Skimcoat surface must be dried, to ensure moisture content not
exceeding 16%.
21) Use Jotasealer Primer to apply as a sealer.
 Jotashield Primer

22) Mix the sealer with thinner approx. 5-10% before application if require.
 By volume

Project : Rivera Point Condominium Development

Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

16/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

23) Use adequate mixing equipment to mix for 3 minutes until
homogeneous.
 By electric mixer if available.
24) To apply 1 coat of diluted Jotashield Primer over the Skimcoat surfaces.
 Applying by medium hair roller.

25) Dry for minimum 2 hours at 300C before apply finishing coat.
 Manually checking

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S


SsangYong E&C

17/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

26) To apply 2nd coat of diluted Jotashield over the 1st finishing coat
surfaces.
 By appropriate checking method.

Scaffolding

27) Allow additional (1-3%) of water for dilution if the diluted paint pot life
time over 2 hours
 Manually checking
28) Dry for minimum 2 hours at 300C before apply 2nd coat.
 Manually checking
29) To ensure finishing surface is smooth. Color and appearance is
uniform.
 By visual assessing
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S


SsangYong E&C

18/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

30) To ensure surface obtain good covering, uniform color and smooth
finish.
 By appropriate checking method
31) To ensure surface is dry and stable.
 Manually checking
32) Ensure adequate curing period of paint film are secured (25 0C * 7 days)
if the paint film performance property test is required.
 By visual assessing.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

19/152


19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

5.2.2 External Wall Painting
1) Surface must be dried. To ensure moisture substance not exceeding
20%.
 Checking with Moisture Meter.
2) To remove foreign and unstable matters such as dirt powder, cement
splashes and other contaminants.
 Manual cleaning by chipping, scrapping or wire brushing.

3) Surface must be free from oil and grease.
 Wiping with cloth dampened solvent.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

20/152

19.08.2013



Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

4) Surface must be free from algae of fungus growth.
 Fungicidal washing.
5) Use Jotun Exterior Putty to apply as plastering.
 Jotun Exterior Putty.
6) Mix 1 bag of Jotun Exterior Putty with 16 litres of water.
 By volume.
7) Use a mixer if available or adequate mixing equipment to mix for 5
minutes until homogeneous.
 By drill mixer or pump mixer.

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

21/152

19.08.2013


Rivera Point Condominium Development

-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

8) Allow the mixtures to stand for about 10 minutes then mix again until
homogenous.
 Ready plaster should be used within 2 hours after mixing.
9) To apply Jotun Exterior Putty on the ceiling and walls surface for 1st
coat.
 Patching by trowel only.

`

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

22/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY


10) Wait for 8-16 hours or until the surface is partially settled then apply a
2nd coat.
 Visual and manually checking

11) Snding after surface dry (3h for minimum applying putty).
12) Interval time for every coat is 8-16 hours at 30oC, minimum.
13) To ensure in order to obtain an even surfaces and reduce roughness.
14) To ensure surface is dry and stable.
 Visual and manually checking

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

23/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

15) Sanding the surface to give a smooth and even finish so as to give an
aesthetics appearance.
 Checking by visual and appropriate equipments

16) To ensure surface is smooth and even.
 Sanding with appropriate sand paper.

17) To ensure surface is dry, clean and stable.
 Checking by visual and appropriate equipment
18) Proceed coating system as from sealer coat to finishing coat.
 Refer to coating system data.
19) Please refer to Method Statement of Jotun Exterior Putty.
(Painting should start preferably within 24 hours after preparation. If
Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

24/152

19.08.2013


Rivera Point Condominium Development
-DESIGN AND BUILD OF MAIN TENDER (PHASE 1A)
FOR PROPOSED CONDOMINIUM DEVELOPMENT AT DISTRICT 7,
HO CHI MINH, VIETNAM FOR M/S RIVIERA POINT LIMITED LIABILITY COMPANY

any delay, surface must be checked and re-preparation again if
contain other contaminants.)
20) Skimcoat surface must be dried, to ensure moisture content not
exceeding 16%.

21) Use Jotashield Primer to apply as a sealer.
 Jotashield Primer

22) Mix the sealer with thinner approx. 5-10% before application if require.
 By volume

Project : Rivera Point Condominium Development
Produced by : Ssangyong E&C
Preparing Duration : 7days
Revision : S

SsangYong E&C

25/152

19.08.2013


×