OPERATIONS MANAGEMENT:
Creating Value Along the Supply Chain,
Canadian Edition
Robert S. Russell, Bernard W. Taylor III, Ignacio Castillo, Navneet Vidyarthi
§
CHAPTER 9
Project Management
1
§
Learning Objectives
Project Planning
Project Scheduling
Project Control
CPM/PERT
Probabilistic Activity Times
Microsoft Project
Project Crashing and Time-Cost Trade-off
9-2
§
Project Management Process
Project
• unique, one-time operational activity or effort
9-3
§
Project Management Process
9-4
§
Project Management Process
9-5
§
Project Elements
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
9-6
§
Project Team and Project Manager
Project team
made up of individuals from various areas and
departments within a company
Matrix organization
a team structure with members from functional areas,
depending on skills required
Project manager
most important member of project team
9-7
§
Scope Statement
Scope statement
a document that provides an understanding, justification,
and expected result of a project
Statement of work
written description of objectives of a project
9-8
§
Work Breakdown Structure
Work breakdown structure (WBS)
Breaks a project into components, subcomponents,
activities, and tasks
9-9
§
Work Breakdown Structure for Computer Order
Processing System Project
9-10
§
Responsibility Assignment Matrix
Organizational Breakdown Structure (OBS)
a chart that shows which organizational units are
responsible for work items
Responsibility Assignment Matrix (RAM)
shows who is responsible for work in a project
9-11
§
Responsibility Assignment Matrix
9-12
§
Project Scheduling
Steps
Define activities
Sequence activities
Estimate time
Develop schedule
Techniques
Gantt chart
CPM/PERT
Software
Microsoft Project
9-13
§
Gantt Chart
Graph or bar chart
Bars represent the time for each task
Bars also indicate status of tasks
Provides visual display of project schedule
Slack
amount of time an activity can be delayed without
delaying the project
9-14
§
Example of Gantt Chart
9-15
§
Project Control
Time management
Cost management
Performance management
Earned Value Analysis – standard procedure to
•
•
•
numerically measure a project’s progress
forecast its completion date and cost
measure schedule and budget variation
9-16
§
Project Control
Quality management
Communication
Enterprise project management
9-17
§
CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand
Deterministic task times
Activity-on-node network construction
Project Evaluation and Review Technique (PERT)
US Navy and Booz, Allen & Hamilton
Probabilistic task time estimates
Activity-on-arrow network construction
9-18
§
Project Network
Activity-on-node (AON)
nodes represent activities
arrows show precedence
relationships
Activity-on-arrow (AOA)
arrows represent activities
nodes are events for points in time
Event
completion or beginning of an activity
in a project
9-19
§
AOA Project Network for a House
9-20
§
Concurrent Activities
Dummy
two or more activities cannot share same start and end
nodes
9-21
§
AON Network for House Building Project
9-22
§
Critical Path
2
2
Start
1
3
7
1
3
1
A:
B:
C:
D:
4
3
1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
5
1
6
1
Critical path
Longest path through a
network
Minimum project
completion time
9-23
§
Activity Start Times
9-24
§
Node Configuration
9-25
§