DAILY CONSTRUCTION REPORT
(BÁO CÁO THI CƠNG HẰNG NGÀY)
Project:
(Cơng trình :)
Date: Tuesday,
(Ngày)
Supervise consultant:
(Tư vấn giám sát;)
Weather:
(Thời tiết)
Contractor:
(Đơn vị thi công )
AM
PM
Rain
Fair/ Sunny
WORK FORCE (NGUỒN LỰC)
Description
(Mô tả công việc)
Skilled worker
(Công nhân lành nghề)
General worker
(Công nhân phụ)
Engineer / Project Manager/ GD/ SM
(Kỹ sư / Quản lý Dự Án)
Surveyor
Equipment Operator
EQUIPMENTS: (THIẾT BỊ )
Description
Quantity
(Mô tả)
(Sốlượng)
Excavator / Bulldozer
Dump truck
Concrete Mixer /
Concrete Pump
Roller Compactor /
Portable Compactor
Quantity
(Số lượng)
5
5
SAFETY (AN TOÀN)
Number of accidents :
(Số tai nạn )
Number of fatal accidents :
(Số tai nạn tử vong )
Remarks :
(Ghi chú )
0
0
6/0/0/0
3
3
2/1
8
Working/None
(Làm việc
/khơng)
2/1
0/0
8
0
0/0
0/0
0/0
0/0
0/0
0/0
CONSTRUCTION ACTIVITIES : (HOẠT ĐỘNG THI CƠNG)
FACTORY AREA
1. Setting out of benchmark & boundary – on going
2. Installation of temporary hoarding – on going
3. Land leveling/excavation of footing – on going
4. Rebar delivery/testing – on going
UTILITY AREA
1. Installation of temporary hoarding – on going
CONSTRUCTION PLANNING : (KẾ HOẠCH THI CÔNG)
FACTORY AREA
1. Setting out of benchmark & boundary
2. Installation of temporary hoarding
3. Land leveling/excavation of footing
4. Rebar delivery/testing
5. Trial mix testing (Le Phan supplier)
Description
(Mô tả)
Crane
Grader
Welding and Cutting
Set
Jack Hammer / Air
Compressor
Quantity
(Sốlượng)
Working/None
(Làm việc /không
0
0
0
0
0
0
1/1
1/1
0/0
1/0
0/0
1/0
UTILITY AREA
1. Installation of temporary hoarding
COMMENTS / REMARKS : (GHI CHÚ)
Reported by
(Báo cáo)
Atelier Management
Endorsed By
(Xác nhận)
Client
E-S side view
Terrace roof (Brick railing plastering)
Plastering of balcony ceiling at 1st floor
Installation M&E pipe (Condensate pipe)