Tải bản đầy đủ (.pdf) (75 trang)

VIE: Second Northern Greater Mekong Subregion Transport Network Improvement Project - Additional Financing

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (1.97 MB, 75 trang )

Social Monitoring Report (Jan-Jun 2018)
Semestral Report
May 2019

VIE: Second Northern Greater Mekong Subregion
Transport Network Improvement Project - Additional
Financing

This document is prepared by Thang Long Project Management Unit (TL-PMU) under the
Ministry of Transport (MOT) for the Asian Development Bank (ADB). The views expressed
herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff,
and may be preliminary in nature.
Social Monitoring Report

Pages | 1


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

ABBREVIATIONS
ADB

=

Asian Development Bank

AH(s)

=


Affected Households

AP(s)

=

Affected persons

COI

=

Minimum corridor-of-impact

CPC

=

Commune Peoples' Committee

DCARB

=

District Compensation, Assistant Resettlement Board

DMS

=


Detailed Measurement Survey

DNA

=

Detailed Need Assessment

DOC

=

Department of Construction

DOF

=

Department of Finance

DPC

=

District People’s Committee

EA

=


Executing Agency

EM

=

Ethnic Minority

EMO

=

External Monitoring Organization

GOV

=

Government of Viet Nam

GMS

=

Greater Mekong Sub-Region

GRM

=


Grievance Redress Mechanism

HH(s)

=

Household

IMR

=

Internal Monitoring Report

IOL

=

Inventory of Losses

IRP

=

Income Restoration Program

LURC

=


Land Use Rights Certificate

MOLISA

=

Ministry of Labour - Invalids and Social Affairs

MOT

=

Ministry of Transport

NH1A

=

National Highway No. 1A

NH217

=

National Highway No. 217

PIB

=


Public Information Booklet

PPC

=

Provincial Peoples' Committee

RCS

=

Replacement Cost Study

ROW

=

Right of Way

REMDP

=

Resettlement and Ethnic Minorities Development Plan

SES

=


Socio-Economic Survey

Social Monitoring Report

Page | 2


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

SPS

=

Safeguard Policy Statement

TA

=

Technical Assistance

TL-PMU

=

Thang Long Project Management Unit

UREMDP =


Updated Resettlement and Ethnic Minorities Development Plan

VND

=

Viet Nam Dong

VWU

=

Viet Nam Women’s Union

Social Monitoring Report

Page | 3


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

CURRENCY EQUIVALENTS
(As of 2nd, March 2018)
Currency unit: Vietnam Dong (VND) and US dollar ($)
US$1 = VND 22,790

WEIGHTS AND MEASURES
km


-

kilometer

kg

-

kilogram

ha

-

hectare

m

-

meter

This Social Monitoring Report is a document of the borrower. The views expressed herein do
not necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
status of any territory or area.
Social Monitoring Report


Page | 4


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................... 5
Executive Summary ........................................................................................................ 6
I.

II.

BACKGROUND OF THE REPORT AND PROJECT DESCRIPTION ........................... 9
1.1.

Background of Report ............................................................................................. 9

1.2.

Project Description.................................................................................................. 9

Scope of Impacts ................................................................................................... 11

III. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS .............................. 14
IV. RELOCATION/RESETTLEMENT ............................................................................. 18
V.

INCOME RESTORATION PROGRAM (IRP) ............................................................. 20

5.1.

Status of Income/livelihood Restoration Program ................................................. 20

5.2.

Income Restoration Activities ................................................................................ 20

5.3.

Implementation arrangement and monitoring ........................................................ 22

5.4.

Estimate for IRP ................................................................................................... 23

5.5.

Consultation with Eligible APs .............................................................................. 24

5.6.

Other Remarks on Livelihood Restoration ............................................................ 25

VI. DISCLOSURE, CONSULTATION AND PARTICIPATION ......................................... 25
6.1.

Objectives of Consultation and Participation ......................................................... 25

6.2.


Consultation and Disclosure ................................................................................. 26

VII. OPERATION OF GRIEVANCE REDRESS MECHANISM (GRM) .............................. 28
VIII. OTHER ISSUES ...................................................................................................... 28
8.1.

Resolution of Issues ............................................................................................. 28

8.2.

New Issues ........................................................................................................... 28

8.3.

Institutional Matters and Capacity Training ........................................................... 28

8.4.

Temporary Impacts during Civil Works ................................................................. 28

IX. APPENDIX .............................................................................................................. 28

Social Monitoring Report

Page | 5


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2


Executive Summary
1.

The Updated Resettlement and Ethnic Minorities Development Plans (UREMDPs)

of three districts: Ha Trung (19/1/2018,), Cam Thuy (14/3/2018), and Ba Thuoc (9/2/2018)
were approved by the Asian Development Bank (ADB).
According to the approved URMEDPs:
2.

Total number of affected households (AHs): there are 2,792 project affected

households (11,945 people) in 03 districts, 10 communes, and 02 towns. The largest number
of AHs appears in Ba Thuoc district with 1,418 AHs (50.8%), followed by Cam Thuy district
with 1,123 AHs (40.2%), and Ha Trung district with 251 households (9%).
3.

The total number of vulnerable AHs in 03 districts includes 1,304/2,792 households

(46.7%), of which 1,069 (38.3%) are ethnic minority households (in Cam Thuy District1 and
Ba Thuoc District2), 44 households (3.4%) are poor households, 83 households (6.4%) are
female-headed households with dependents, 107 households (8.2%) belong to policy
households (war invalids, martyrs), and 32 (2.5%) belong to households to disabled people.
Cam Thuy
Out of 1,123 affected households, 492 (2,267 persons) households are identified as
vulnerable households of which 8 households (30 persons) are poor households, 25
households (124 persons) of war invalids and martyrs and social policy beneficiaries
households, 11 households (43 persons) with disabled people, 25 households (80 persons)
are female headed households, and 423 households (1,990 persons) belong to Ethnic

Minority group3.
Ba Thuoc
753/1418 AHs (3,195 persons) households are identified as vulnerable households of which
74 households (201 persons) are poor households, 85 households (402 persons) of war
invalids and martyrs and social policy beneficiaries households, 45 households (191
persons) with disabled people, 113 households (382 persons) are female headed
households, and 436 households (2,019 persons) belong to Ethnic Minority group4.

1

Actual number of Ethnic Minority affected by project is 447 however 24 EM households also belong
to other vulnerable groups.
2 Actually number of Ethnic Minority affected by project is 622 however 186 EM households also
belong to other vulnerable groups.
3 Actual number of Ethnic Minority affected by project is 447 however 24 EM households also belong
to other vulnerable groups therefore the number of EM households mentioned here is only 423.
4 Actually number of Ethnic Minority affected by project is 622 however 186 EM households also
belong to other vulnerable groups therefore the number of EM households mentioned here is only
436.
Social Monitoring Report

Page | 6


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

4.

The number of relocated households: there are 45 households, accounting for 1.6%


of the total AHs, of which 28 households are in Cam Thuy district, 16 households are in Ha
Trung district, and 01 household is in Ba Thuoc district.
5.

The EMDP Implementation, in practice, can be applied differently in each district.

There are 1069 vulnerable and affected ethnic minority households by this project. There are
no ethnic minorities in Ha Trung district; however, Cam Thuy district has 447 households and
Ba Thuoc district has 622 ethnic minority households (mainly Muong, Thai, Tay, H'Mong’
etc.).
As of June 2018:
6.

Received compensation: As of June 2018 the total households who received

compensation money are 1914/2792 households (or 68.6%). The others have not been
paid because the Compensation Committee has not completed the compensation/support
plans for them.
7.

Disbursement and Use of Funds: According to UREMDP reports of 03 districts, the

total compensation and support cost in 03 districts is VND 278,394,285,147, of which the
total direct cost for compensation and support is estimated VND 157,158,212,537. As of
June, 2018, the total payment is VND 76,335,916,643 (1914 AHs) accounting for 48.6% of
total cost on compensation and resettlement. The compensation and support cost will be
updated in the next monitoring report.
8.


Income Restoration Program (IRP): As of June 2018 the IRP program has not yet

been deployed in the three districts. The implementation process of the IRP will be updated
in the final second half IMR report of 2018. The IRP budget for the three districts is estimated
at 14,150,000,000 VND.
9.

The consultation meetings have been carried out in 03 districts since the

resettlement project has been implemented up to date. The number of consultative meetings
for information dissemination is remarkably. There were 1,952 participants to the
consultations, of which 1,494 are men (76.5%), and 458 are women (23.5%).
10.

Grievance redress mechanism: The Grievance redress mechanism was developed

in accordance with the ADB’s requirements. The ADB approved the mechanism in the
URPs/UREMDPs. The mechanism makes details the steps of resolving complaints relating
to land acquisition. However, as of June 2018, at the Compensation Committees of 03
districts, there are not any complaints received from the affected households.
Recommendation and Disclosure

Social Monitoring Report

Page | 7


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2


11.

The site clearance and resettlement will continue to be updated by PMU-TL until the

completion. In beginning stage, there was an independent monitoring of land acquisition and
resettlement of affected households to implement the monitoring. The monitoring results are
objective and timely to meet the compensation requirements of households. However, the
relocation is a process that depends on the implementation steps and can not be acquired at
once with the following details:
-

Inventory of property damage of households within the scope of land acquisition

-

Make compensation plans for resident compensation payment and publicize these plans.

-

After obtaining the consent of the people; at that time, make a compensation decision.

-

Resolve arising complaints to speed up the payment process for households.

-

Site handover for the project.

-


To relocate the affected people by the project for removal resident resettlement.

-

Organize the forms of income restoration etc.

12.

In addition to these solutions, income recovery assistance for affected people has to

be relocated to new places, including those who are disadvantaged in the affected
communities through the social organizations such as Veterans Association, Farmers'
Association, Women's Union, etc.
13.

Currently, all three districts of Ha Trung, Cam Thuy and Ba Thuoc are developing

programs in line with the actual schedule, informal courses (to be shown in details in the next
report IMR).

Social Monitoring Report

Page | 8


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

I.


BACKGROUND OF THE REPORT AND PROJECT DESCRIPTION
1.1.

Background of Report

14. The IMR reports are submitted every 6 months in the period of 2018-2019. The
process of internal monitoring is implemented for the following objectives: (i)
Compliance with the agreed updated RP/updated REMDP; (ii) The availability of
resources and the efficient, effective use of these resources to implement land
acquisition and resettlement activities; (iii) That resettlement institutions are wellfunctioning during the course of project implementation; (iv) Resettlement activities are
undertaken in accordance with the implementation schedule described in the updatedRP/updated REMDP; (v)To identify problems, if any, and remedial actions.
15. The structure of the IMR reports includes the following main contents: (i) scope of
impacts, (ii) detailed resettlement implementation progress, (iii) relocation/resettlement,
(iv) IRP (v) disclosure, consultation and participation, (vi) GRM, (vii) other issues, and
(viii) appendix.
1.2.

Project Description

16. GMS Second Transport Network Improvement Project. The original scope of the
Second GMS Transport Network Improvement Project (referred to as “ongoing project”)
included: (a) provision of works for about 200 km on Route 217 including (i) improving
road alignment and widening the road formation from Km 107.2 to Km 195.4 (about 88
km), (ii) construction of new bypasses in Cam Thuy (east and west) (about 3 km), (iii)
pavement repair and resurfacing from Km 0 to Km 104.9, (iv) stabilizing slopes and
erosion protection, (v) repairing and building new road structures including bridges and
culverts, and (vi) improving traffic safety measures; and (b) provision of consulting
services in pre-construction activities in the preparation of detailed design, tender
document preparation, bid evaluation, project implementation, project management and

construction supervision, and for HIV/AIDS and human trafficking awareness and
prevention program.
17. On 24 September, 2014, a minor change was approved by the Ministry of Transport
(MOT) to (i) scale up the project scope by adding road improvements for section Km
104.9 to Km 107.2 (additional 2.3 km); (ii) replace the pavement repair and resurfacing
from section Km 0 to Km 104.9 with full replacement of unsuitable bridges; and (iii)
increase the scope of consulting services to (a) prepare detailed design, bid documents;
and resettlement plans for the proposed change in scope; and (b) update the feasibility
study for full scale improvement of section Km 59+800 to Km 104+900 for the proposed

Social Monitoring Report

Page | 9


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

additional financing which traverses through Ha Trung, Vinh Loc, Cam Thuy, Ba Thuoc
and Quan Son districts in Thanh Hoa province.
18. The Second Northern Greater Mekong Sub-region Transport Network Improvement
Project - Improvement of National Highway 217 - Phase 2, Thanh Hoa province
includes the upgrading of the section from Km 59 + 800 to Km 104 + 475 and the
Flyover Bridge passing the North-South railway and the NH-1A at Km 301 + 400,
passing through the districts of Ha Trung, Cam Thuy and Ba Thuoc, Thanh Hoa
province.
19. The Project’s total investment is US$ 94.7 million (equivalent to VND 1,899.3 billion), of
which ADB lends US$ 75 million and the counterpart fund of the Vietnamese
government is US$ 22.4 million.
20. Section from Km 59+900 ÷ Km 76+800 in Cam Thuy District: it is mainly widened

two sides of route. Due to technical requirement, two bypasses are proposed in which
(i) section at Km 59+800 – Km 60+300 has total length of 400m. The bypass creates a
crossroad at the beginning of route and improves two reverse curves with small radius
(R=30-40M) which is the black spot of traffic accident on the route, (ii) section at Km
70+100 – Km 72+500 has total length of bypass of 2.25 km. The bypass is on the right
of old route, crosses old road at Km 71, runs to the left of old road to avoid residential
area, crosses Chieng Cham stream, and then combines with old road at…
21. Section from Km 76+800 ÷ Km 104+475 in Ba Thuoc District: it is mainly widened
two sides of route. Due to technical requirement, one left bypasses from Km 79+900 is
separated from old road and runs to field area to avoid residential area of Dien Trung
commune (the farthest residential area is about 120m from bypass) and then combines
with old road at position which is in front of Thanh Tung fuel station at Km 80+800. Total
length of bypass is L=900m.
22. The Flyover Bridge passing the North-South railway and the NH-1A at Km 301 +
400, in Ha Trung district, will be expanded and upgraded up to Grade-III rural road
standard. The designed speech is 80 Km/h. The road width is 12m wide. The road
surface is 7m wide. The minimum curve is R250. The culvert design load is H30-XB80.
The bridge design load is HL93. Speed at intersection at the right direction reaches 40
km/h and at the left direction to NH 1A reaches 15 km/h. The Flyover Bridge at central
line passing railway and NH 1A has the length of 372.0 m which ensures clearance
height of railway of 6.55 m. The intersection is arranged by shape of T-junction is land
and middle separator of NH 1A at Km 300 + 570 is widened to turn left; Pedestrian
Flyover bridge is supplemented to pass NH 1A and railway which is 150m far from the
current intersection to the South direction.
Social Monitoring Report

Page | 10


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING

Improvement Highway No.217, Thanh Hoa Province - Phase 2

23. The project feasibility studies prepared by the project preparatory technical assistance
(PPTA) team together with government agencies indicate a category A for involuntary
resettlement and Category B for indigenous peoples, according to ADB’s Safeguard
Policy Statement 2009.
II.

Scope of Impacts

24.

According to the uREMDPs approved by the ADB in 2018, there are 2,792 project

affected households with 11,945 people living in 03 districts (Ha Trung, Ba Thuoc and Cam
Thuy), 10 communes, and 02 towns. The largest number of AHs are in Ba Thuoc district with
1,418 households (50.8%), followed by Cam Thuy district with 1,123 households (40.2%),
and Ha Trung district with 251 households (9%).
Table 1: Summary of affected households in 3 districts
District

Affected

Affected

Affected > 10%

s

Resettled AHs


Vulnerable AHs

total agricultural
land
agencies
No. of

No. of

AHs

APs

251

1097

No.

Organiza

/commu

No.

tions

nity


AHs

of

No. of

No. of

No.

APs

AHs

Aps

of

No.

of

AHs

of
APs

Ha
Trung


2

2

95

397

16

63

Cam
Thuy

1123

4919

3

3

44

209

28

492


226
7

753
1418

5929

4

24

63

259

1

2

1194
Total

153

124

Ba
Thuoc


59

2792

5

5
1304

9

29

202

865

45

189

319

561
5

(Source: URMDEP – Ha Trung - Cam Thuy and Ba Thuoc district – January and March
/2018)
Ha Trung District ( Source: UREMDP – Ha Trung district – 1/2018)

25.

Construction of the Flyover Bridge passing the North-South railway and the NH-1A at

Km 301+400 road section will affect 251 households (1,097 persons), two state agencies (Ha
Ninh Commune and Ha Trung Town People's Committees) and two state organizations
(Water Company and Power Company). There are 95 households (397 persons) who have
10% and more of total production landholding affected and 16 relocation households (69
Social Monitoring Report

Page | 11


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

persons) due to land acquisition - these are considered as severely affected households; and
59 vulnerable affected households (153 persons) among the total affected households by
construction of the bridge and the road section in Ha Trung District.
26.

The total land area to be permanently acquired for construction of the bridge and the

road section is 61,525.80 m2, consisting of 44,996.70 m2 of agricultural land of 202
households (891 persons), 9,185.19 m2 of residential land owned by 65 households (265
persons), In addition, the subproject will acquire a total of 816.31 m2 of land which is the
existing ROW of the existing road, and 6,527.60 m2 of unused land managed by People's
Committee of Ha Trung town.
27.


Construction of the bridge and the road section will affect 68 houses (4,699.2 m2)

which are owned by 30 house-owners. There are 52 houses (owned by 16 house-owners)
that will be fully affected; and the remaining 16 houses (that owned by 14 house-owners) will
only be partially affected and will require only minor repairs.
28.

There are 04 houses-cum-shops that will be affected. The households will relocate

their houses and shops to new residential areas. In addition, construction of the bridge and
the road section will affect 17 electricity poles, 5,375 m length of wire and one 10kV station
managed by the Power Company; 1,180 m length of three water pipelines managed by the
Water Company; 733.2 m of concreted village road and 12 m of a culvert which are the
community's assets. The bridge and road section construction will also affect 2,338 fruit-trees
of 47 households and 1,001 timber trees of 37 households and 2,253 m2 of crops of 215
households in the area.
Ba Thuoc District ( Source: UREMDP – Ba Thuoc district – 1/2018)
29.

Construction of the Road section from Km 76+800 ÷ Km 104+475 in Ba Thuoc District

will affect 1,418 households (5,929 persons), 04 enterprises, 22 public facilities in the
following communes Thiet Ong, Lam Xa, Ai Thuong, Dien Quang, Dien Lu and Dien Trung
and 02 state organizations (Ba Thuoc DPC and Power Company). There are sixty-three (63)
households (259 persons) who have 10% and more of total production land holding affected,
01 relocation household (02 persons) - these are considered as severely affected
households and 03 households (11 persons) will shift back in their remaining land due to
land acquisition; 753 vulnerable households (3,195 persons) are identified among the total
households affected by construction of the road section in Ba Thuoc District.
30.


The total land area to be permanently acquired for the Project is 144,862.86 m2,

consisting of 86,490.76 m2 of agricultural land of 355 households (1,583 persons), 1,990.1
m2 of residential land owned by 41 households (167 persons) and 56,382.00m2 of public
land in ROW of 06 communes.
Social Monitoring Report

Page | 12


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

31.

Among total affected households, 1,036 households will be affected on houses and

structures due to the construction of the road section in Ba Thuoc district. 34 houses (1,411.1
m2) owned by 32 house-owners will be affected. Among houses affected, 04 houses (owned
by 04 house-owners) will be fully affected and the remaining 30 houses (owned by 28 houseowners) will only be partially affected and require minor repairs. In addition, 3,559 structures
of 1,004 households will be affected by project. Out of 04 houses totally affected, there is 01
house-cum-shop. The household will relocate their house and shop to new residential area.
32.

In addition, construction of the road section will affect 204 electricity poles, 13,159.7 m

length of wire managed by the Power Company; 1,670m length of Irrigation ditches managed
by the Ba Thuoc DPC; 197.23 m2 of concreted village road, 34.7 m sewage drainage along
the road, 10.3m built fence and 39.86 m3 foundations of stone which are the assets of 22

communities and non-land assets of 04 enterprises.
33.

Out of 1,418 AHs, the road section construction will affect 29,282 fruit-trees of 1,175

households, 51,615 timber trees of 788 households and 64,073 m2 of crops of 557
households.
Cam Thuy – District (Source: URMDEP – Cam Thuy district – 3/2018)
34.

Construction of the Road section from Km 59+900 ÷ Km 76+800 in Cam Thuy District

will affect 1,123 households (4,919 persons), 06 public facilities in the following communes
Cam Thanh, Cam Thach, and Cam Binh, and 03 state offices (Cam Thuy DPC, Water supply
company and Power Company). There are forty four (44) households (209 persons) who
have 10% and more of total production land holding affected, 28 relocation households (124
persons)5 - these are considered as severely affected households and 39 households (190
persons) will shift back in their remaining land due to land acquisition; 492 vulnerable
households (2,267 persons) are identified among the total households affected by
construction of the road section in Cam Thuy District.
35.

The total land area to be permanently acquired for the for construction of the road

section is 140,161.9 m2, consisting of 98,466.5 m2 of agricultural land of 425 households
(1,934 persons), 25,061.4 m2 of residential land (including 4,948.68 m2 of garden land in
same land plot of residential land) owned by 417 households (1,818 persons), and 31,224.7
m2 of agricultural land is used for paddy and forest, managed by 3 People's Committee of
Cam Binh, Cam Thach, Cam Thanh communes (Cam Thuy District), and 16,634.0m2 public
land in ROW of 03 communes and 01 town. 40 out of 417 households with residential land

affected will also be affected to garden land in same land plot of residential land. Beside the
5

Among severely affected households, one household is both losing 10% and more productive land
holding and relocated household.
Social Monitoring Report

Page | 13


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

compensation for garden land at replacement cost for agricultural land, they will be entitled to
receive cash assistance equivalent to 50% of the current market value of residential land for
the affected garden land area.
36.

Among total affected households, 902 households will be affected on houses and

structures. 297 houses (9,734 m2) owned by 235 house-owners will be affected. Among
houses affected, 86 houses (owned by 67 house-owners) will be fully affected and the
remaining 211 houses (that owned by 168 house-owners) will only be partially affected and
will require only minor repairs. In addition, 3,368 auxiliary structures of 667 households will
be affected by project. Out of 67 houses totally affected, there are 12 houses-cum-shops
(owned by 12 households). The households will relocate their houses and shops to new
residential areas.
37.

In addition, construction of the road section will affect 189 electricity poles, 8,340 m


length of wire managed by the Power Company; 1,219.49 m length of water pipelines
managed by the Water Supply Company and 5,788 m length of Irrigation ditches managed
by the Cam Thuy DPC; 242.3 m2 of concrete village road/yard, 23,5 m2 of wooden house,
30m built fence and 01 village Gate which are the assets of 6 communities.
38.

Out of 1,123 AHs, the road section construction will affect 17,678 fruit-trees of 787

households, 20,837 timber trees of 699 households and 33,728 m2 of crops of 457
households.
III. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS
General progress in Resettlement implementation
39.

The Asian Development Bank (ADB) approved the Resettlement Plans and the Ethnic

Minority Development Plans (UREMDPs) on 19/1/2018, 9/2/2018, and 14/3/2018,
respectively for the three districts of Ha Trung, Ba Thuoc and Cam Thuy.
40.

The DMS was conducted in

-

Ha Trung District: August 2016 and completed in October 2017

-

Cam Thuy District: August 2017 and completed in September 2017


-

Ba Thuoc District: August 2017 and completed in October 2017
by the Working Group established by the People's Committee of Ha Trung, Cam Thuy
and Ba Thuoc district.

41.

In general, the handover and site clearance for construction works in the subproject

area has been started in in February 2018 and has been almost completed. The percentage

Social Monitoring Report

Page | 14


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

of land which has been taken over from AHs accounts for about 85.5%. The specific
progress of the land acquisition and handover of land by the subproject is as follows:
Table 2. General Progress in Land Clearance and Handing Over of Land for Civil Works
Land handed Over (m2)
Total
Affected
Land Area
(m2)


Districts

Cumulative amount of
land handed over

Land that still has to
be acquired/handed
over (m2)

Land
Handed
over this
reporting
period

Amount in
m2

% of total
affected
land

Amount
in m2

% of total
affected
land

Remaining

encumbrances
[yes/no]

Ha Trung

61,525.80

60,135.72

60,135.72

97.7%

1,390.08

2.3%

Yes

Cam Thuy

140,161.90

98,567.35

98,567.35

70,32

41,594.55


29.7%

Yes

Ba Thuoc

144,862.86

137,549.96

137,549.96

94.95

7,312.90

5.0%

Yes

TOTAL

346,550.56

296,253.03

85.49%

50,297.53


14.51%

Remarks

(Source: DCARBs June/2018)
42.

The compensation payment for the AHs has been conducted in February 2018. As of

June 2018, the total households who received compensation are 1,914/2,792 households (or
68.6%). The others have not been paid because the Compensation Committee has not
completed the compensation/support plan which is expected to be completed in quarter
2/2019.
Table 3. General of Compensation Progress

AHs (APs) eligible for compensationa and/or

Districts

assistance/allowances
Total Number of

Number of AHs

% Progress

AHs (AHs)

(AHs) fully paid


Ha Trung

251

224

89.2%

Cam Thuy

1123

665

59.2%

Ba Thuoc

1418

1025

72.3%

TOTAL

2792

1914


68.6%

(Source: DCARBs June/2018)
43.

The total number of vulnerable households in the three districts includes 1,304

households (46.7%), of which 1,069 (38.3%) are ethnic minority households, 44 are poor
households (1.6%), and 83 are (3%) female-headed households with dependents as in the
table below. In which, the number of vulnerable households who have received full
compensation is 994 AHs.

Social Monitoring Report

Page | 15


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2
Table 4. Progress in Compensation of Vulnerable AHs
Total Number of Vulnerable AHs (APs)
Districts

EM

FHH with
dependen
ts


Others

14

0

7

492

6

447

753

18

1,304

44

Total

Poo
r

Ha Trung

71


Cam Thuy
Ba Thuoc
TOTAL

Number of Vulnerable AHs (APs) fully paid

Total

Poor

57

55

10

0

5

40

77.5%

17

14

244


3

225

9

7

49.6%

622

59

28

695

16

601

53

25

92.3%

1,069


83

80

994

29

826

67

72

76.2%

(*)

FHH with
dependen
ts

Others

%
Progress

Ethnic
Minorit

y

(*)

(Source: DCARBs June/2018)
44.

The number of relocated households includes 45 households, accounting for 1.6% of

the total AHs, of which there are 28 households in Cam Thuy district, 16 households in Ha
Trung district, and 01 household in Ba Thuoc district.
At present (June 2018) the compensation plans of the resettled households have not been
approved and they have not received compensation money. It is expected that the
compensation payment progress and relocation households will be in two quarter of 2019.
Table 5: Selection of resettlement by households

Commune/town

Number of
households

Number of
people

Total 1

16

63


Number of
households
to
resettlement
site
0

Ha Trung town

11

43

0

11

Ha Ninh commune

5

20

0

5

124

0


28

76

0

18
2

Total 2
Cam Thuy town

28
18

Number of
households
self-relocating

16

Cam Binh commune

2

10

0


Cam Thach commune

2

8

0

2

Cam Thanh commune

6

30

0

6

Total 3

1

2

0

1


Thiet Ong commune

1

2

0

1

Lam Xa commune

0

0

0

0

0

0

0

0

0


0
0

Ai Thuong commune
Dien Quang commune

0
0

Dien Lu commune

0

0

0

Dien Trung commune

0

0

0

0

Total (1+2+3)

45


189

0

45

(Source: DCARBs June/2018)
45.

All of 45 relocated households submitted claims to the DCARB asking for

compensation money to relocate by themselves. The households to be resettled are eligible
for the compensation for their affected land and affected assets on land at the replacement
Social Monitoring Report

Page | 16


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

costs. In addition, they will receive cash allowance, including: (i) a life stabilization allowance
is equivalent to 30 kg of rice per person per month in 03 months for all household members
(12,000 - 13,000 VND/kg/ person) (ii) an allowance of 5,000,000 VND/AH equals the
transportation cost (trucks and labor) to the new residential places, and (iii) house renting
(1,000,000 VND/month) in 6 months. In addition, each affected household will receive from
VND 52,000,000 to VND 60,000,000 for self-relocation allowance.
46.


Disbursement and Use of Funds: According to UREMDP reports of 03 districts, the

total compensation and support cost in 03 districts is VND 278,394,285,147, of which the
total direct cost for compensation and support is estimated VND 157,158,212,537. As of
June, 2018, the total payment is VND 76,335,916,643 (1914 AHs) accounting for 48.6% of
total cost on compensation and resettlement. The compensation and support cost will be
updated in the next monitoring report. The details are as follows.
Table 6. Disbursement and Use of Funds
Location

LAR Budget
Requirement

Ha
Trung
37,988,682,868

Cam
Thuy

ADB
Loan
Fund

Funds Disbursed
this Reporting
Period

10,747,207,913


ADB
Loan
Fund

50,839,684,873

59.379.985.139

ADB
Loan
Fund

14,769,023,688

157,158,212,537

Specific
Resettlement
activities
funded this
Reporting
Period

224 ( 55 hhs

93,754,741,473

Ba
Thuoc


TOTAL

Source
of
Funding

76,355,916,643

vulnerable and
169 hhs others
received
provision of
compensation
and supports)
665( 244 hhs
vulnerable and
421 hhs
others
receiced
provision of
compensation
and supports)
1025 ( 695
hhs vulnerable
and 330 hhs
others
received
provision of
compensation
and supports)


Timeliness of
Fund
Disbursement

Delay in
targets for
fund
disbursement?
(Y/N)

Reasons for delay

Y

The Compensation
Committee has not
completed the
compensation/support
plan

Y

Y

1914

(Source: DCARBs June/2018)
47.


Of the total 2792 AHs, 1914 households have been paid, accounting for 68.6%. The

remaining of 878 households have not been paid because their compensation plans have not
been completed.

Social Monitoring Report

Page | 17


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

Table 7: The compensation progress of payment to affected households
Unpaid amount

Unpai

(VND)
Locations

Total

Uncomp

Total cost

d
amou


AHs in

Compens

ensated

estimate

DMS

ated AHS

AHS

(VND)

Paid amount
(VND)

nt (%)

(hhs)

(hhs)

(hhs)

Ha Trung

251


224

27

37,988,682,868

10,747,207,913

27,241,474,955

71.6%

Cam Thuy

1123

665

458

93,754,741,473

50,839,684,873

42,915,056,600

45.8%

Ba Thuoc


1418

1025

393

25,414,788,196

14,769,023,688

10,645,764,508

47.8%

Total

2792

1914

878

157,158,212,537

76,355,916,643

80,802,295,894

52.4%


(Source: DCARBs June/2018)
IV. RELOCATION/RESETTLEMENT
48.

All of 45 relocated households submitted claims to the DCARB asking for

compensation money to relocate by themselves. The households to be resettled are eligible
for the compensation for their affected land and affected assets on land at the replacement
costs.
49.

At present (June 2018), the compensation plans of the resettled households have not

been approved and they have not received compensation money.
Table 8: Confirmed Resettlement Preferences for Households with Fully Affected Houses
# of AHs with
Location

# of AHs

Fully Affected Required to
Houses

# of AHs Opting
for Replacement

Relocate

Ha Trung


16

16

Cam Thuy

28

Ba Thuoc
TOTAL

# of AHs Opting # of AHs that Can # of AHs that opt for

Land

0

for Self

Rebuild on

relocation apartment

Relocation (HHs) Remaining Land in relocation building

16

0


0

28

28

39

0

4

1

1

3

0

48

45

45

42

0


0

(Source: UREMDPs January and March 2018)
Table 9: Resettlement Solutions Implemented for Vulnerable Households
Indigenous
No

People
(HHs)

Landless

Poor

(HHs)

(HHs)

Female

Other [add

Headed
Households

as needed]

Rebuilt on remaining land

10


0

0

0

0

Rebuilt on another plot of land already owned

0

0

0

0

0

0

0

0

0

0


Rebuilt on other person’s land (e.g. relative)

6

0

0

0

1

Purchased replacement land elsewhere

0

0

0

0

0

Rebuilt (e.g. moved back) out of COI but on
public land

Social Monitoring Report


Page | 18


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2
themselves

Solution pending

0

0

0

0

0

(Source: DCARBs June/2018)
50.

Implementation of the EMDP in practice can be applied differently in each district.

There are 1069 vulnerable and affected ethnic minority households by this project. There are
no ethnic minorities in Ha Trung district; however, Cam Thuy district has 447 households and
Ba Thuoc district has 622 ethnic minority households (mainly Muong, Thai, Tay, H'Mong’
etc.). The project has focused on weak, vulnerable groups in the ethnic minority community.
51.


EM households are entitled to the IRP. However ( June/2018), 3 districts are now

rebuilding the IRP. The IRP preparation progress will be updated in the next IMR.
Table 10: General Progress in Ethnic Minority Development Plan (EMDP)
Implementation
List of
District

EM Development Activities

Implementation

Remarks

EM living
in the
area

Ha Trung

0

Not applicable

Not applicable

Cam Thuy

447


Life support, job change and

IRP

restoration

implemented

Life support, job change and

IRP

restoration

implemented

Ba Thuoc

622

is

is

not

yet

Vulnerable
households will


not

yet

receive
additional cash
assistance

by

VND
1,000,000/HH.
assistance

for

stabilizing
households’ life
equivalent to 30
kg

of

rice/household’s
member/month
for

all


family

members,
minimum
three
and

in

months
maximum

in 36 months
TOTAL

1069

Social Monitoring Report

Life support, job change

IRP

is

not

yet

Page | 19



THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2
and restoration

implemented

(Source: DCARBs June/2018)
V.

INCOME RESTORATION PROGRAM (IRP)
5.1.

52.

Status of Income/livelihood Restoration Program

As of June 2018, the IRP has not yet started in all 03 districts. There are 1,415

households eligible to the IRP, of which 243 households are severely affected and 1,172
affected households belong to vulnerable group. The implementation process of the IRP will
be updated in the IMR report of the second half of 2018. However, during the SES, DMS, RP
and UREMDP implementation, the Consultant has conducted preliminary surveys relating to
the IRP. The IRP implementation will be updated in the next internal monitoring report.
5.2.
53.

Income Restoration Activities


According to the result of Detailed Need Assessment (DNA) the following activities will

be implemented:
(i)

Cash Assistance for Vulnerable Households: vulnerable households will
receive additional cash assistance by VND 1,000,000/HH.

(ii)

Assistance for Severely Affected Households: The household losing from
10% and more of their total production land holding (agricultural land) and or
relocation households will get additional assistances includes assistance for
stabilizing households’ life equivalent to 30 kg of rice/household’s member/month
for all family members, minimum in three months and maximum in 36 months (it
depends on the level of land acquisition impacts), and other assistance will be
also provided to severely affected households as follows:

(iii)

Agriculture extension with sustainable production technique to improve current
cultivation capacity will be provided to households through programs of the
Government and through guidance of agriculture extension staffs of commune
and district;

(iv)

Prioritized to access to agricultural credit;

(v)


Technical assistance and support in accessing to credit for starting business or
other economic activities through the National Fund for Employment Support of
MOLISA, Agriculture and Rural Development Bank, Policy Bank for the Poor.

(vi)
54.

Be prioritized in recruitment of labors for construction of Project.

In addition to the above, In-kind support will be specially paid attention to severely AHs

who lose their productive land, buy new land or look for non-farm jobs. However, each
Social Monitoring Report

Page | 20


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

severely affected household is entitled to receive only one economic recovery allowance
package at different assistance levels which depends on whether they lose their house or
lose more than 10% of their land holding.
55.

In-kind support will include supply of breeding/seedling, veterinary materials, and

fertilizers to households who want to receive in-kind support to develop their livestock and
cultivation activities. In-kind support can be either full scholarships or a certain percentage to

provide occupational training for severely affected AHs who want to change their jobs. In the
process of developing a detailed livelihood program by Livelihood Restoration Board of
District, severely AHs will be provided the guidance on how to use in-kind support to get the
most effectiveness that corresponds to the level they are entitled to receive.
56.

It is allowed if the household opts to receive assistance in cash, to restore livelihood by

themselves, however the guidance how to use money effectively shall be provided to
households, especially poor households before they receive money for livelihood restoration
on the base of approved budget of the project, the need and impact level of households as a
sustainable method to restore livelihood.
57.

Besides allowance in cash for job changing and creation as regulated in entitlement

matrix, the project will facilitate one member of severely affected household in registering to
participating in occupational training center of the province basing on the results of survey on
the need of livelihood restoration of households. Through consultation with Division of Labor,
Invalids and Social Affairs of District, fund for occupational training will be applied in
accordance with the Plan of Decision No.1956/2009/QD-TTg dated 17th November, 2009 by
Prime minister allocated to districts and provinces.
58.

Support in accessing to loans: Policy on fund assistance for affected households will be

implemented in accordance with regulations in Decision No.52/2012/QD-TTg of Prime
Minister dated 16th November, 2012 regarding the policy for supporting employment and
training for employees who lose their agricultural land.
59.


Introduction of job and labour export opportunities: Policy on introducing labour export

opportunity for affected person will be implemented in accordance with regulations in
Decision No.52/2012/QD-TTg of Prime Minister dated 16th November, 2012 regarding the
policy for supporting employment and training for employees who lose their agricultural land.
60.

Prioritize to employ members of severely affected households when Contractor needs

to recruit local labours for site clearance, excavation and other construction activities for the
works of constructing road section in 3 Districts. Bidding document and conditions in the
contract for civil works regulate that when recruiting local labours, construction contractors
and labour contractors will:
Social Monitoring Report

Page | 21


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

-

Prioritize in recruiting qualified labors and especially severely affected persons;

-

Pay salary for labors in compliance with regulation of law; and


-

Do not use children labor.

61.

Livelihood Restoration Board of District will contact with contractors to organize

recruitment in locality in accordance with regulation in bidding document. Schedule and
requirement on minimum skill will be planned. Information on job opportunities will be
disseminated to villages in order for people to easily access. Severely affected women need
to be specially paid attention in consultation meetings and assistance programs as
mentioned above. In addition, severely affected women should be also specially paid
attention in priority of recruitment equality in the construction process.
5.3.
62.

Implementation arrangement and monitoring

Detailed livelihood restoration program will be managed and implemented by the

stakeholders with the roles as follows:
(i)

Thang Long PMU will be responsible for: (i) cooperating with Thanh Hoa PPC
and related departments to manage implementation progress of livelihood
restoration program of the project and preparing reports to ADB; (ii) DCARBs and
implementation board of livelihood restoration program of district carry out
livelihood restoration program; (iii) ensure that fund is available in bank account
to implement livelihood restoration program.


(ii)

Board in charge of implementing livelihood restoration program at district level:
which is established by DPCs, will be responsible for: (i) developing livelihood
restoration program in details and then submitting the program to PMU-TL for
reviewing before submitting to DPC for approval; (ii) following up the detailed
implementation plan of approved livelihood restoration program; (iii) providing
necessary documents to PMU-TL to timely allocate fund for livelihood restoration
activities; (iv) closely working with local authority at levels (DPC, CPC),
organizations/unions (Women union, farmer association) to find out resolutions
for arising issues during the process of implementing livelihood restoration
program; (v) preparing reports on implementation progress of livelihood
restoration program to submit to PMU-TL, Ha Trung, Ba Thuoc and Cam Thuy,
DPC.

(iii)

Members of Board in charge of implementing livelihood restoration program at
district level include deputy chairman of DPC being in charge of development of
agriculture, representative of PMU-TL (one person), Division of Labor, Invalids

Social Monitoring Report

Page | 22


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2


and Social Affairs (one person), head and cadastral officers of District Agriculture
Extension Station, representative of farmer association (one person) and Women
Union at district level (one person) Deputy chairman of DPC will be the head of
Board in charge of implementing livelihood restoration program.
(iv)

External monitoring consultant: will externally monitor and assess the
implementation of livelihood restoration program, reflect arising issues in
restoring livelihood of severely affected households in periodical monitoring
reports and give recommendations or adjustment for livelihood restoration
program if necessary. The effectiveness of resolutions in livelihood restoration
program will be assessed in independent monitoring program and will be
implemented during the process of implementing the project.

5.4.
63.

Estimate for IRP

The cost estimate for income restoration implementation is presented in Table below

Table 11:

Cost estimate for income restoration programe
Districts

Occupation
Ba Thuoc

Cam


Ha

Thuy

Trung

Unit cost

Amount

Total

Cultivation

0

0

11

11

10,000,000

110,000,000

Livestock

40


51

11

102

10,000,000

1,020,000,000

Cultivation and livestock

88

71

14

173

10,000,000

1,730,000,000

130

148

13


291

10,000,000

2,910,000,000

110

78

17

205

10,000,000

2,050,000,000

142

83

18

243

10,000,000

2,430,000,000


269

97

24

390

10,000,000

3,900,000,000

779

528

108

1,415

Development

of

small

business
Occupational training
Introduction


of

job

opportunities
Access

to

preferential

loan
Total

14,150,000,000

(Source: URMDEP – Ha Trung - Cam Thuy and Ba Thuoc district – January and March
/2018)
Social Monitoring Report

Page | 23


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

5.5.
64.


Consultation with Eligible APs

A Detailed Need Assessment (DNA) was conducted in August and October 2017 by

the Social Safeguard Consultant together with representatives of affected households, local
authorities and the DCARB. Twelve (12) Focus Group Discussion (FGD) with severely
affected households, and vulnerable affected households (with 408 people: 178 women
(43.6%) and 230 men (56.4%), and nine (09) key informant interviews with income
restoration program (IRP) eligible households and local authorities were carried-out. In
addition, survey on livelihood preferences of all AHs by questionnaire was also conducted.
65.

Result of DNA also shows that out of the total 1,415 affected households. In the 1,415

AHs, include: 291 households wish to development of their small business and 286
households opted to develop livestock or combination of livestock and cultivation and receive
technical supports as well as loan support to raise cattle and chicken. Together with the need
of livestock development, severely affected households also proposed to be trained and
guided on technique of growing rice, especially severely affected households with remaining
land is enough for cultivation. There are 205 households who have the need of occupational
training for their children and 243 households that expect that their children who have
graduated from university will be introduced on job opportunities. The remaining 390
households want to access to preferential loan to develop economy of their family. IRP
preferences of the IRP participating households are summarized in the Table below:
Table 12: IRP preferences of IRP eligible households

Occupation

Ha Ninh
Ha


Trung

town
Total - Ha
Trung
Cam

Thuy

Town
Cam

Binh

Commune
Cam Thach
Commune
Cam Thanh
Commune
Total - Cam
Thuy

Cultivation

Livestock

Cultivation

Development


and

of small

livestock

business

Occupational
training

Introduction

Access to

of job

preferential

opportunities

loan

Total

9

8


12

9

13

13

18

82

2

3

2

4

4

5

6

26

11


11

14

13

17

18

24

108

0

2

3

20

6

4

13

48


0

11

36

62

34

38

47

228

0

24

14

21

12

18

13


102

0

14

18

45

26

23

24

150

0

51

71

148

78

83


97

528

Social Monitoring Report

Page | 24


THE SECOND NORTHERN GMS TRANSPORT NETWORK IMPROVEMENT PROJECT – ADDITIONAL FINANCING
Improvement Highway No.217, Thanh Hoa Province - Phase 2

Occupation

Cultivation

Livestock

Cultivation

Development

and

of small

livestock

business


Occupational
training

Introduction

Access to

of job

preferential

opportunities

loan

Total

Thiet Ong

11

22

29

43

37

97


239

Lam Xa

11

31

31

18

25

34

150

Ai Thuong

12

12

15

20

27


38

124

Dien Quang

0

4

7

2

1

6

20

Dien Lu

0

8

17

6


9

18

58

Dien Trung

6

11

31

21

43

76

188

40

88

130

110


142

269

779

102

173

291

205

243

390

1415

Total - Ba
Thuoc
Total

11

(Source: URMDEP – Ha Trung - Cam Thuy and Ba Thuoc district – January and
March/2018)
5.6.

66.

Other Remarks on Livelihood Restoration

General difficulties: For DCARBs, the IRP implementation is currently new as the

DCARBs staff have not considerably experienced in the ADB projects. Therefore, during the
IRP implementation, there should be supports from the other stakeholders for the
implementation. In March 2018, DCARB of Ba Thuoc, Cam Thuy and Ha Trung made written
to ADB and TL-PMU for requests Consultant to support in preparation and implementation of
the detailed IRP, but TL-PMU not yet approved.
67.

Households' livelihood needs may change by the time because this will inevitably face

difficulties for the stakeholders when implementing activities.
VI. DISCLOSURE, CONSULTATION AND PARTICIPATION
6.1.
68.

Objectives of Consultation and Participation

Implementation of consultation with the affected HHs, affected organizations and

community will reduce the conflicts and minimize delay of the project. Based on this, it
enables the project to update the resettlement plan which is compliance with the needs,
benefit of the affected HHs and organizations.
69.

The objectives of the public consultation and participation of local people include: (i)


ensuring the participation of the affected HHs, affected organizations and local community
into the progress of design, preparation and making decision of project; (ii) disseminating all
the information, activities related to the project to APs; (iii) collecting the idea, concern, need
or priority of affected people; (iv) ensuring that all the APs notified all the decision which is
related directly to their income and living standard; and (v) ensuring the transparency in
implementation of land acquisition, compensation and assistance payment, and relocation.
Social Monitoring Report

Page | 25


×