Graduation Project
PROJECT PLAN DOCUMENT

KIDSLAND

Mentor: MSc Huy Nguyen Dang Quang
Team Members: Duong Nguyen Thi Thuy
Tai Nguyen Van
Thao Mai Thi Thu
Hao Nguyen Chiem

Da Nang, 2020

PROJECT INFORMATION

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Project Acronym PMS
Project Title
Start Date KidsLand
Lead Institution
Feb 17, 2020 End Date Apr 29, 2020

The Faculty of Information Technology, Duy Tan University


Project Mentor MSc Huy Nguyen Dang Quang

MSc Huy Nguyen Dang Quang

Project Manager Email:
& Contact Details
Phone: 0935525354
Members
Duong Nguyen Thi nguyenthuyduong72018 0389121969

Thuy @gmail.com

Tai Nguyen Van nguyenvantai22298@gm 0764466624
ail.com

Hao Nguyen Chiem nguyenchiemhao2205@ 0365225603
Thao Mai Thi Thu gmail.com 0343431856


m

Page 2 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

PROJECT PLAN DOCUMENT


Document Title Project Plan Document

Reporting Period Feb 2020

Author(s) Tai Nguyen Van

Date Feb 19, 2020 Filename KidsLand_Project_Plan_Vers
ion-1.5.docx

Access Project and FIT program

DOCUMENT HISTORY

Version Person Date Description
1.0 Tai Nguyen Van Feb 19, 2020
1.1 Tai Nguyen Van Feb 22, 2020 Create Document
1.2 Feb 24, 2020 Update Name and
1.3 Team Mar 09, 2020
1.4 Team Mar 23, 2020 Date Time
1.5 Team Apr 06, 2020 Update Detail
Team Schedule for sprint 1
Update Detail
Schedule for sprint 2
Update Detail
Schedule for sprint 3
Update Detail
Schedule for sprint 4

Page 3 of 75


Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

SIGNATURE
Document Approvals: The following signatures are required for approval of this
document.

MSc Huy Nguyen Dang Quang Date

Mentor

Duong Nguyen Thi Thuy Date

Scrum Master

Tai Nguyen Van Date

Member

Hao Nguyen Chiem Date

Member

Thao Mai Thi Thu Date

Member


Page 4 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Table of Contents
I. Introduction.................................................................................................................6

1. Purpose..................................................................................................................... 7
2. Scope........................................................................................................................ 7
3. References................................................................................................................ 7
4. Definitions, Acronyms and Abbreviations...............................................................7
II. Team organization.......................................................................................................7
1. Scrum Team Information.........................................................................................7
2. Role and responsibility.............................................................................................8
3. Communication Methodology..................................................................................9
4. Communication and Report.....................................................................................9
III. Project Overview....................................................................................................10
1. Project Name..........................................................................................................10
2. Project Duration.....................................................................................................10
3. Project Goal...........................................................................................................11
4. Project vision.........................................................................................................11
5. Project Scope.........................................................................................................11
IV. Schedule and Cost..................................................................................................12
1. Work Breakdown Structure....................................................................................12
2. Detailed Schedule..................................................................................................12

3. Cost........................................................................................................................59
V. Development Process................................................................................................60
1. Reason for selecting process..................................................................................60
2. Description Scrum..................................................................................................60
VI. Project’s Risk.........................................................................................................64
VII. Deliverable.............................................................................................................66
VIII. Configuration Management....................................................................................67

Page 5 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Table
Table 1: References............................................................................................................7
Table 2: Definitions, Acronyms and Abbreviations...........................................................7
Table 3: Scrum Team Information.....................................................................................8
Table 4: Role and responsibility.........................................................................................8
Table 5: Communication Methodology..............................................................................9
Table 6: Communication and Report...............................................................................10
Table 7: Detailed Schedule..............................................................................................59
Table 8: Detailed Cost......................................................................................................60
Table 9: Project’s Risk.....................................................................................................64
Table 10: Detailed Risk....................................................................................................66
Table 11: Detailed Deliverable.........................................................................................67
Figure
Figure 1: Work Breakdown Structure..............................................................................12

Figure 2: Stages in Scrum................................................................................................61
Figure 3: Scrum team members........................................................................................62

Page 6 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

I. Introduction
1. Purpose
This document provides a summary of the project's objectives, division of work, the
major milestones, required resources, time and overall schedule and budget allocation
used and based on the document proposal to build an expense management application on
time, at the request and plan.

2. Scope

 This document provides an overview about product, process, and team in project.
 This is just a general plan then details plan will be updated throughout the life

cycle of the project.

3. References References
Project Plan Template
No. Proposal Document
1
2


Table 1: References

4. Definitions, Acronyms and Abbreviations

No. Term Definition or Description

1 API Application Programming Interface

2 UI User Interface

3 AWS Amazon Web Service

4 S3 Simple Storage Service (Cloud Storage)

Table 2: Definitions, Acronyms and Abbreviations

II. Team organization
1. Scrum Team Information

Full Name Position Phone Email
Duong Nguyen Scrum 038912196
Thi Thuy Master 9

Page 7 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106


Project Plan Version 1.5 | PMS

Tai Nguyen Van Team 076446662
member 4
Hao Nguyen Team 036522560
Chiem member 3
Thao Mai Thi Team 034343185
Thu member 6

Table 3: Scrum Team Information

2. Role and Responsibility Responsibility Participant(s)
Role

● Guide on the process.

Mentor ● Monitoring all activities of Team. MSc Nguyen Dang
Quang Huy
● Supporting team management skills,
writing, technical, business operation and
some things else's.

● Responsible for increasing productivity.

Scrum master ● Using the Scrum framework. Duong Nguyen Thi
● Facilitates and Coaches the team. Thuy

● Owns the impediment Backlog.
● Responsible for the ROI.


Product Owner ● Responsible for the product. MSc Nguyen Dang
Quang Huy
Team members ● Owns the Product backlog.
● Responsible for quality. Tai Nguyen Van
Hao Nguyen Chiem

Page 8 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

● Responsible for delivering the potentially Thao Mai Thi Thu
shippable product of the Application each
sprint.

● Report progress based on remaining time.

● Self-organized.

● Owns the Sprint backlog.

Table 4: Role and responsibility

3. Communication Methodology

Audience/ Topic/ Deliverable Frequency Method
Attendees Weekly

Manager, Mentor Project Progress Meeting, Email,
and Team member Review Phone, Skype

Customer, Manager Project Progress Weekly Meeting,
and Scrum master Review Conference
Meeting, Skype
Customer, Manager Explicit When needed Meeting, Email,
and Scrum master Requirement Daily
Project Progress Skype
Scrum master and Review and Daily
Team Member Meeting, Email,
Meeting Facebook, Skype

Table 5: Communication Methodology
4. Communication and Report

Type of Methods, Frequenc Information People

Page 9 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

communication tools y

Communication among in group


Daily Meetings Face to Face Daily Informed about what was Project
or Skype or done in the last 24 hours, team
Facebook working on plans for
today, the difficulties Project
encountered and the team,
solutions required, just Product
meeting 10-15 minutes. Owner

Task Planning Meet face to Weekly All members in team Project
Meeting face, Skype, together to analyze the team,
requirements, functions, Product
Email working on the sprint Owner
going to do, planning and
design for the sprint.

Task Review Meet face to 15-20 days Complete documentation.
Meeting face, Skype, For each stage, sharing
materials, given the
Email strengths and weaknesses
for each. Period for each
member and the solution
calculated measurement
project.

External communication and reporting

Page 10 of 75

Downloaded by LIEU TAI ()


lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Task Google Every day A web based on task Project
Management Drive, tracking system. To team
Trello manage or divide task,
report bugs/issues.

Table 6: Communication and Report
III. Project Overview
1. Project Name
The project name is: KidsLand

2. Project Duration
 Project will be started on Feb 03, 2020
 Project will be finished on Apr 22, 2020

3. Project Goal
Building Mobile applications can perform child management functions at preschools.
This includes manipulating attendance and identifying children through the camera when
entering the classroom and notifying Parents what time the child is at school, and notify
the child's activities to parents and parents. Parents update the child's situation for
teachers through the application. In addition, creating a contact book helps schools and
parents to keep an overall track on the learning situation of children.
4. Project Vision

 Create a preschool management system with full feature focus on the instant,
quickly and useful for parent and management.


 Create trust and become long-term partners with recent user and others.

5. Project Scope
 Application running on native platform.
 Admin dashboard running on web platform.

Page 11 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106 Project Plan Version 1.5 | PMS

IV. Schedule and Cost
1. Work Breakdown Structure

F
i
g
u
r
e
1
:

Work Breakdown Structure

2. Detailed Schedule

No. Task Duration Starting Ending Person Total Hour
Day Day


Page 12 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

1 Start Up 15 days Feb 03, Feb 21, Team

2020 2020

1.1 Gathering 10 days Feb 03, Feb 14, Team 320

Requirement 2020 2020

1.2 Create Proposal 1 day Feb 17, Feb 17, Team 32

Document 2020 2020

1.3 Project Kick-off 2 days Feb 18, Feb 29, Team 64

Meeting 2020 2020

1.4 Make Project 1 day Feb 20, Feb 20, Tai 8

Plan Document 2020 2020

1.5 Make User Story 1 day Feb 20, Feb 22, Hao, 8


Document 2020 2020 Thao

Make Product Feb 20, Feb 20,

1.6 Backlog 1 day 2020 2020 Duong 8

Document

1.7 Review 1 day Feb 21, Feb 21, Team 32

Document 2020 2020

2 Development 49 days Feb 24, Apr 22, Team

2020 2020

2.1 Sprint 1 10 days Feb 24, Mar 06, Team 300

Page 13 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

2020 2020

Sprint plan 1 day Feb 24, Feb 24, Team 16

2.1.1
2020 2020
meeting

Create Sprint Feb 25, Feb 25,

2.1.2 Backlog 1 day 2020 2020 Tai 4

Document

2.1.3 Create Test Plan 1 day Feb 25, Feb 25, Hao 8

Document 2020 2020

2.1.4 Design Database 1 day Feb 25, Feb 25, Tai 4

2020 2020

2.1.5 Design UI 2 days Feb 24, Feb 25, Hao,

2020 2020 Thao

Design UI of 1 day Feb 25, Feb 25, Hao 4

“Login” 2020 2020

Design UI of 1 day Feb 25, Feb 25, Hao 4

“Previous Login” 2020 2020


Design UI of 1 day Feb 25, Feb 25, Hao 4

“App loading” 2020 2020

Design UI of 1 day Feb 24, Feb 24, Thao 4

“Forgot

Page 14 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

password” 2020 2020

Design UI of 1 day Feb 24, Feb 24, Thao 4

“Verification” 2020 2020

Design UI of 1 day Feb 25, Feb 25, Thao 4

“Reset password” 2020 2020

Design UI of 1 day Feb 25, Feb 25, Thao 4

“Authorization” 2020 2020


2.1.6 Design API 3 days Feb 24, Feb 26, Tai,

2020 2020 Duong

Design API of 1 day Feb 25, Feb 25, Duong 4

“Login” 2020 2020

Design API of Feb 26, Feb 26,

“Forgot 1 day 2020 2020 Duong 4

Password”

Design API of 1 day Feb 25, Feb 25, Tai 2

“Verification” 2020 2020

Design API of 1 day Feb 25, Feb 25, Tai 2

“Reset Password” 2020 2020

Page 15 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS


2.1.7 Design Test case 2 days Feb 25, Feb 26, Tai,
2020 2020 Duong

Design Test case 1 day Feb 26, Feb 26, Tai 2

of “Login” 2020 2020

Design Test case Feb 26, Feb 26,

of “Forgot 1 day 2020 2020 Tai 2

Password”

Design Test case 1 day Feb 25, Feb 25, Duong 6

of “Verification” 2020 2020

Design Test case Feb 25, Feb 25,

of “Reset 1 day 2020 2020 Duong 6

Password”

2.1.8 Coding Feb 25,
2020

Set up front-end Feb 25, Feb 26,

develop 2 days 2020 2020 Hao 16


environment

Set up back-end Feb 26, Feb 28,

develop 3 days 2020 2002 Tai 16

environment

Page 16 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Code UI and Feb 26, Feb 27,

Consume API of 2 days 2002 2020 Hao 8

“Login”

Code API 1 day Mar 02, Mar 02, Duong 10
“Login”
2002 2002

Code UI and Feb 28, Feb 28,

Consume API of 1 day 2020 2020 Hao 4


“Previous Login”

Code UI and Feb 28, Feb 28,

Consume API of 1 day 2020 2020 Hao 4

“App loading”

Code API of Feb 28, Feb 28,

“Forgot 1 day 2020 2020 Tai 4

password”

Code UI and

Consume API of 2 days Feb 25, Feb 26, Thao 8

“Forgot 2020 2020

password”

Code UI and Feb 27, Feb 27,

Consume API of 1 day 2020 2020 Thao 8

“Verification”

Page 17 of 75


Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

Code API 1 day Mar 02, Mar 02, Tai 4

“Verification” 2002 2020

Code UI and Feb 28, Feb 28,

Consume API 1 day 2020 2020 Thao 8

“Reset password”

Code API of 1 day Mar 02, Mar 02, Tai 4

“Reset password” 2020 2020

Code UI and Mar 02, Mar 02,

Consume API 1 day 2020 2020 Hao 8

“Authorization”

Code API 1 day Mar 02, Mar 02, Duong 10

“Authorization” 2020 2020


2.1.9 Testing 1 day Mar 03, Mar 03, Team
2020 2020

Test feature 1 day Mar 02, Mar 03, Thao, 4

“Login” 2020 2020 Tai

Test feature Mar 02, Mar 03, Thao,

“Forgot 1 day 2020 2020 Tai 4

password”

Test feature 1 day Mar 02, Mar 03, Hao, 4

Page 18 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

“Verification” 2020 2020 Duong

Test feature 1 day Mar 02, Mar 03, Hao, 4

“Reset password” 2020 2020 Duong

Test feature 1 day Mar 03, Mar 03, Hao, 4


“Authorization” 2020 2020 Duong

2.1.10 Fix Bugs

Fix bug feature 1 day Mar 04, Mar 04, Hao, 4

“Login” 2020 2020 Duong

Fix bug feature Mar 04, Mar 04, Thao,

“Forgot 1 day 2020 2020 Tai 8

password”

Fix bug feature 1 day Mar 04, Mar 04, Thao, 8

“Verification” 2020 2020 Tai

Fix bug feature 1 day Mar 04, Mar 04, Thao, 8

“Reset password” 2020 2020 Tai

Fix bug feature 2 days Mar 04, Mar 05, Hao, 4

“Authorization” 2020 2020 Duong

2.1.11 Re-Testing

Re-test feature 1 day Mar 05, Mar 05, Thao, 4


Page 19 of 75

Downloaded by LIEU TAI ()

lOMoARcPSD|38557106

Project Plan Version 1.5 | PMS

“Login” 2020 2020 Tai

Re-test feature Mar 05, Mar 05, Thao,

“Forgot 1 day 2020 2020 Tai 4

password”

Re-test feature 1 day Mar 04, Mar 04, Hao, 4

“Verification” 2020 2020 Duong

Re-test feature 1 day Mar 05, Mar 05, Hao, 4

“Reset password” 2020 2020 Duong

Re-test feature 1 day Mar 05, Mar 05, Thao, 4

“Authorization” 2020 2020 Tai

2.1.12 Release Sprint 1 1 day Mar 06, Mar 06, Team 32


2020 2020

2.2 Sprint 2 Mar 09, Mar 20,
2020 2020

Sprint plan 1 day Mar 09, Mar 09, Team 16
2.2.1
2020 2020
meeting

Create Sprint 2 Mar 09, Mar 09,

2.2.2 Backlog 1 day 2020 2020 Tai 4

Document

2.2.3 Create Test Plan 1 day Mar 10, Mar 10, Thao 4

Page 20 of 75

Downloaded by LIEU TAI ()


×