Tải bản đầy đủ (.docx) (92 trang)

Methor statement for production of super - T Girder

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (1.87 MB, 92 trang )

Method Statement for Production of Super-T Girder

CONTENTS

1. .............................................................................................................................

General

............................................................................................................................................
2. ...........................................................................................................................

Materials

..........................................................................................................................................
3. ..............................................................................................

Main Equipment and Tools

..........................................................................................................................................
1)

Fabrication Yard No.1.1............................................................................................

2)

Fabrication Yard No.1.2............................................................................................

3)

Fabrication Yard No.2................................................................................................


4. ...................................................................................................

Site Organization Chart

..........................................................................................................................................
5. .................................................................................................

Construction Flow Chart

..........................................................................................................................................
6. .......................................................................................

Detail Construction Procedure

..........................................................................................................................................
1)

Detail Work Procedure................................................................................................ 11
a) Preparation work........................................................................................................ 11
b) Pre-assemble rebar cage....................................................................................

12

c) Installation rebar cage........................................................................................

12

d) Installation PC strands........................................................................................

13


e) Installation inner formwork.................................................................................... 18

Page 1


Method Statement for Production of Super-T Girder

f) Casting concrete.................................................................................................... 19

2)

g) Curing and removal of inner formwork.................................................................

20

h) Cutting tendons....................................................................................................

21

i) Lifting girder to stock yard....................................................................................

24

j) Filling the non - shrinkage mortar.........................................................................

25

Cycle Time of Super-T Girders Fabrication.........................................................


25

7. ...................................................................

Schedule for Production of Super T Girder

.......................................................................................................................................
8. .................................................................................................................

Quality Control

.......................................................................................................................................
9. ....................................................................................................

25

Environmental Control

.......................................................................................................................................
10. ..............................................................................................................

25

Safety Control

.......................................................................................................................................
11. ...................................................................................

25


26

Emergency Call out Procedure

.......................................................................................................................................

36

1)

Initiation................................................................................................................... 36

2)

Second Stage........................................................................................................

36

3)

Third Stage...........................................................................................................

36

4)

Emergency response chart........................................................................................ 37

12. ......................................................................................................................


Appendix

.......................................................................................................................................

Page 2

37


Method Statement for Production of Super-T Girder

1)

Appendix – 1: Plan of fabrication yard No.1.1; No.1.2 and No.2

2)

Appendix – 2: Working drawing for production of super T girder

3)

Appendix – 3: General drawing gantry crane 80 tons and 5 tons

4)

Appendix – 4: General drawing of formwork system

5)

Appendix – 5: Drawing of pre-installation of rebar cage frame for super T girder


6)

Appendix – 6: Drawing lifting crane of rebar cage for super T girder

7)

Appendix – 7: Drawing of frame system for hanging inner formwork

8)

Appendix – 8: Drawing of detail for lifting hook

9)

Appendix – 9: Drawing of protection frame during stressing

10)

Appendix – 10: Calculation of formwork system
11)

Appendix – 11: Calculation of camber of permanents
12)

Appendix –12: Lifting device calculation of Super T girder
13)

Appendix –13: Calculation for pre-stressing of Super T girder
14)


Appendix –14: Inspections and test plan
15)

Appendix –15: Inspection sheet form

Page 3


Method Statement for Production of Super-T Girder

1.

General:

Project information:



Project name:

North – South Expressway Construction

Project (Ben Luc - Long Thanh Section) – Contract
Package No.J2.



Page 4



Method Statement for Production of Super-T Girder
Location: Can Gio District, Ho Chi Minh city, Viet Nam.



This is a Method Statement for Production of Pre-cast Pre-stressed Concrete super
T girders for Superstructure of Approach Span Structures in accordance with
General Specifications and Approved drawings. Length of Super T girder shall be
fabricated to adapt with each span length in consideration with the effect of
horizontal curve and change in width of carriage-way.



This work item shall be done in accordance with the requirements of Clause S07450
concrete structures of the Technical Specifications.



Quantity of Super T girder shall be shown on below tables:

There are 3 types of Pre-cast super-T girders as below table:

Precast Girder

Classify

Unit

Total


Work

Comme

Numbe

nt

r

Precast Super T Girder

strand
1

Type IA

Interio

Pcs

672

L=

44

Type IB


Exteri

Pcs

192

L=

44

or
2

Type VA

Interio

38.3m
Pcs

21

r
Type

Exteri

VB

or


L=

35

34.3m
Pcs

6

L=
34.3m

Page 5

35


Method Statement for Production of Super-T Girder

3

Type

Interio

IVA

r


Type

Exteri

IVB

or

Pcs

98

L=

34

33.3m
Pcs

28

L=

34

33.3m

Because of site’s characteristic is distributed with two particular locations which are
spaced by Cha River so contractor arranges positions and quantities of fabrication
yard as below:


N

Name

o.
1

2

3

2.



Locatio

Type of Girder

Total Girder

n
Fabrication Yard

Fabrication Yard

Fabrication Yard

No 1.1


No 1.2

No.2

38.3

180

m

pcs

33.3

45

m

pcs

38.3

135

m

pcs

33.3


81

m

pcs

34.3

27

m

pcs

38.3

549

m

pcs

180 pcs

180 pcs

657 pcs

Materials :


The list of main materials for production of pre-stressing super T girders which must
be approved by the engineer shall be shown as the below table:

Page 6


Method Statement for Production of Super-T Girder

Name of

Specification

material
Concrete C50
Reinforcement

Remarks

y
50MPa

Complied with design mix approved

S07500

PC strand

15.2mm


Mono anchor

S07500

Bonding mortar

Quantit

Sikadur 731

TCVN 1651:2008
ASTM A421-91/A416-99

Patch end side of girder at strand
areas

PVC pipes

D18/22 and D50/56

Anchor hook

D32

Form release

Sika separol

TCVN 1651:2008
Apply per manufacture


agent



Material stocked at side shall be kept off the ground by sleeper from rain and dirty by
roof or others measures.



Material quality control at site, especially rebar, stressed cable which are sensitive
against corrosion shall be carefully stocked and controlled in dry condition.



Detailed quantities shall be indicated and shown on the working drawing which is
approved by the engineer.

3.

Main Equipment and Tools:

The quantity of equipment’s below may be changed with required actual conditions.
Page 7


Method Statement for Production of Super-T Girder

1)


Fabrication Yard No.1.1:

N

Item

Capacity

Unit

Q’ty

Remark

1

Gantry crane

80 Ton

unit

01

Lifting and shifting

2

Gantry crane


5 Ton

set

02

Pouring concrete

3

Bar Cutter

As requirement

set

01

Rebar fabrication

4

Diesel Generator

As requirement

set

01


Electric supply

5

Welding Machine

As requirement

unit

02

6

Concrete Bucket

0.8~1.2m3

unit

02

Pouring concrete

7

Air Compressor

As requirement


unit

01

Cleaning work

8

Survey Instrument

As requirement

set

01

Surveying work

9

Concrete Rod Vibrator

φ30mm

unit

04

Pouring concrete


1

Concrete Rod Vibrator

φ50mm

unit

06

Pouring concrete

Plate vibrator

2.2Kw

unit

90

Mono Pre-stressing Jack

≥ 240kN

set

03

Pre-stressing


2HP

set

02

For curing concrete

set

03

Production SPT

Welding

0
1
1
1
2
1

Water pump

3
1

Casting bed type 38.3m


4

girder

1

Outer

5

38.3m

formwork

type

set

03

Production
girder

Page 8

SPT


Method Statement for Production of Super-T Girder


1

Inner

formwork

type

6

38.3m

2)

Fabrication Yard No.1.2:

N

Item

set

01

Production

SPT

girder


Capacity

Unit

Q’ty

Remark

1

Gantry crane

80 Ton

unit

01

Lifting and shifting

2

Gantry crane

5 Ton

set

02


Pouring concrete

3

Bar Cutter

As

set

01

Rebar fabrication

set

02

Electric supply

unit

03

requirement
4

Diesel Generator

As

requirement

5

Welding Machine

As

Welding

requirement
6

Concrete Bucket

0.8~1.2m3

unit

02

Pouring concrete

7

Air Compressor

As

unit


01

Cleaning work

set

01

Surveying work

requirement
8

Survey Instrument

As
requirement

9

Concrete Rod Vibrator

φ30mm

unit

04

Pouring concrete


1

Concrete Rod Vibrator

φ50mm

unit

06

Pouring concrete

Plate vibrator

2.2Kw

unit

90

Mono Pre-stressing Jack

≥ 240 kN

set

03

0

1
1
1

Page 9

Pre-stressing


Method Statement for Production of Super-T Girder

2
1

Water pump

2HP

set

02

For curing concrete

set

03

Production


3
1

Casting bed type 38.3m

4
1

girder
Outer formwork type 38.3m

set

03

5

Production

Inner

6

formwork

type

set

01


38.3m
set

01

33.3m

3)

Fabrication Yard No.2:

N

Item

Production

Production

Capacity

Unit

Q’t

Remark
Lifting and shifting

Gantry crane


80 Ton

unit

02

2

Gantry crane

5 Ton

set

06

Pouring concrete

3

Bar Cutter

As

set

03

Rebar fabrication


set

02

Electric supply

unit

05

requirement
As
requirement
Welding Machine

SPT

girder

1

Diesel Generator

SPT

girder

type


5

SPT

girder

1

4

SPT

As

Welding

requirement
6

Concrete Bucket

0.8~1.2m3

unit

04

Pouring concrete

7


Air Compressor

As

unit

02

Cleaning work

Page 10


Method Statement for Production of Super-T Girder

requirement
8

Survey Instrument

As

set

02

Surveying work

requirement

9

Concrete Rod Vibrator

φ30mm

unit

12

Pouring concrete

1

Concrete Rod Vibrator

φ50mm

unit

20

Pouring concrete

Plate vibrator

As

unit


270

≥ 240 kN

set

06

Pre-stressing

2HP

set

04

For curing concrete

set

07

Production

0
1
1
1

requirement

Mono Pre-stressing Jack

2
1

Water pump

3
1

Casting bed

4

type
38.3m
type

girder
set

01

34.3m
type

Outer

type


5

formwork

38.3m
type

set

01

set

07

Inner formwork

type

Production

SPT

Production

SPT

girder
set


01

Production

SPT

girder
set

01

33.3m
1

SPT

girder

34.3m
type

Production
girder

33.3m
1

SPT

Production


SPT

girder
set

Page 11

03

Production

SPT


Method Statement for Production of Super-T Girder

6

38.3m

girder

type

set

01

34.3m


SPT

girder

type

set

01

33.3m



Production

Production

SPT

girder

Hydraulic Jacking Machine (Hydraulic pump & Gauge) will be verified by
independent laboratory under supervision of Engineer.

4.

Site Organization Chart:


Project Manager
Mr. Tahara

Deputy Project Manager
Mr. Shimoyama

Planning Manager
Mr. Nguyen Song Toan
MOB: 0939495061

QC Manager
Mr. Nguyen Hoa

Planning Engineer

QC Engineer

Construction Manager
Mr. Higashi

Site Engineer

Page 12

Safety Manager
Mr. Le Ngoc Xuan

Safety Engineer



Method Statement for Production of Super-T Girder

Production of Super T
Girder Team

5.

Yard no.1.1

Yard no.1.2

Yard no.2

Yard no.2

Team Leader
Doan Van Hoai
(0904.268.262)

Team Leader
Vo Thanh Hien
(0912.122.737)

Team Leader
Pham Van Hiep
(0976.445.449)

Team Leader
Nguyen Thanh Son
(0989.650.907)


Technical
Surveyor
Worker (25)

Technical
Surveyor
Worker (30)

Technical
Surveyor
Worker (45)

Technical
Surveyor
Worker (30)

Construction Flow Chart:

1

Preparation work

• Mobilization for material and equipment
• Mobilization labor
• Approved for material, method statement and working drawing

2

Pre-assemble

rebar cage

• Inspection of shape and dimension of fabricated rebar
• Inspection of rebar after pre-assembles (position, spacing,
concrete cover…)

3

Installation rebar
cage
cage

• Using trussing beams for lifting the whole rebar cage
• Inspection of rebar after installation (stability, verticality, position,
concrete cover thickness…)

4

Installation PC
strands and
Curing and
tensioning
cage
Cutting
removalPC
inner
Installation
inner
strands
formwork

form
work
Casting
concrete
cage
cage






7
8
5

Checking strands testing result, certification of anchorage
Checking the calibration of jack and gauge
Checkingand
andinspection
recording the elongation
curing duration,
temperature
Measure
of strands
Confirmation of concrete
strength
(85%
design
concrete

elapsed
Page time
13 for removal of inner form
strength)
• Measure and record the pre-camber


Method Statement for Production of Super-T Girder

• Carefully install inner form after tensioning
• Checking the stability of inner form after fixing into bed
• Inspection of position and shapes of inner form





6

Checking resource of concrete supply
Checking slump and temperature of concrete.
Checking stability and deflection of form during casting process
Checking displacement of PC strand and rebar during casting
process

9

Lifting girder to
stock yard
cage


• Shifting girder to storage by gantry crane and lifting
• Finishing and repairing (if any) shall be carried out

10

Filling the non shrinkage mortar

• Mixing non-shrinkage mortar and filling

6.

1)

Detail Construction Procedure:

Detail Work Procedures:

a) Preparation Works:



Material and equipment for the work shall be set up and required approval

Page 14


Method Statement for Production of Super-T Girder
such as for material testing and calibration of stressing jack and pump shall be
confirmed.




Prior to commencement of work, all equipment and workers shall be inspected
with attendance of the Engineer.



Approval working drawing for super T girder shall be confirmed prior to
commence production of super-T girder.



Casting bed and outer formwork must be inspected assembly by engineer
according to allowable error in specification and working drawing of fabrication
yard.

b) Pre-assemble Rebar Cage:


Reinforcing steel bar shall conform to the requirements of the following
specifications: TCVN 1651:2008



The every delivery of reinforcement bars with respect of all diameters shall be
certified by the manufacturer’s mill certificates which are submitted and
approved by the engineer




Reinforcing rebar shall be kept off the ground and stored within a building or
provided with suitable cover



Reinforcing bars shall be accurately formed to the shapes and dimension
indicated in the approved working drawing, and shall be fabricated in a manner
that will not injure the material



All reinforcing bars requiring bending shall be bent cold. When reinforcing bars
are bent by heating, the entire operation shall be approved by the engineer.
Reinforcing bars that cannot be straightened by means of fabrication shall not
be used.

Rebar arrangement of girder

Page 15


Method Statement for Production of Super-T Girder

Anchor hook D32

Steel pipe making hole for
anchor bolt of upper plate
Rebar cage




Reinforcing bars before be positioned shall be cleaned and free form rust, dirt,
mud and loose scale and from paint, oil, or any other foreign substance
destroys or reduces the bond.



Fabricating reinforcement assembly frame which is used to install
reinforcement for super T girder.



Reinforcement frame is fabricated with conforming dimensions to easily install
reinforcement for super T girder.



On reinforcement assembly frame, we mark positions to install reinforcement.



Fabricated reinforcing bars shall be installed on the frame before setting into
casting bed.

Pre-installation frame
Rebar cage




Reinforcing bars shall be accurately placed in proper position so that they will
be firmly held during placing concrete.

Page 16


Method Statement for Production of Super-T Girder



Reinforcing bars shall be tied at intersections by using annealed iron wire
0.9mm or lager diameter or suitable clips.



Concrete covers shall be set to maintain the distance from the formworks to
reinforcing bars



When necessary to splice reinforcing bars, lengths of laps shall be 40d; with d
is nominal diameter of bars. In lapped splices the bars shall be lapped the
required length and wired together at several points by using annealed iron
wire larger than 0.9 mm. Location of splice shall not be staggered so that no
more 50% of bars are lapped in any one cross section.



The coupler bar at ends of girder and hook are located following right distance
in working draw




Method for locating the coupler bar at ends of girder are carry out following
steps:
-

Installation rebar No. 09-D22-100

-

Installation 2 bar No. A*-D16, as described in figure below.

- Mash the position of coupler on rebar No. A*-D16
-

Fix the coupler bar on the rebar No. A*-D16 as approved working drawing.

Page 17


Method Statement for Production of Super-T Girder

50 140

50

1140
90


90

90

84

75150 150110 190

610

50

1040

75150 150110 190

50

750

1360

1360

1750

1750

1140


760
50
300

660

300

300

50

75150 150110 190

75150 150110 190

75150 150110 190
75150 150110 190 75

75 190 110150 15075

D20 Bar
Threaded couplers

bé nèi lo¹i 1

bé nèi lo¹i 2

coupler type 1


coupler type 2

1220

380

1220

240

75150 150110 190

1950

c) Installation Rebar Cage:

Before installing the rebar cage, carry out assembling end form by gantry
crane 5 tons. End form is hold by 4 support jack as below drawing :
80

720

300

975
END FORM

550

END FORM


3850
1900

975

TENSIONING
BEAM B2

SUPPORT JACK

750

840

550

SUPPORT JACK
TENSIONING
BEAM B2

150

30

1300

SUPER T GIRDER

750




500
END FORM

Page 18

900

500


Method Statement for Production of Super-T Girder



Rebar including embedded rebar for diaphragm shall be installed in
accordance with approved working drawing.



Concrete blocks with steel wire or plastic spacer shall be installed at bottom
and side of rebar in order to keep the appropriate concrete covering.




Splicing length and location shall be in accordance with working drawing.
Rebar shall be tied at intersections of rebar to prevent dislocation during

casting.



Installed rebar shall be free from rust, dirt, oil or other material that might
reduce the bond.



Temporary embedded material such as thread bar for support of decks slabs
form work shall be installed at proper location.



Rebar cage after installed on the frame shall be set into casting bed by gantry
crane 80 tons.

Gantry crane
80 Tons

Rebar
Cage

Page 19


Method Statement for Production of Super-T Girder

Lifting frame
Rebar cage

Outer form

Plat form
Casting bed



A truss beam shall be used for hanging and lifting rebar cage. Truss beam
shall be dismantled and removed to out of rebar cage by gantry crane for
installation remaining bar.



After setting, reinforcement bars, concrete cover shall be adjusted to ensure
correctly position, spacing, and shall be inspected ,approved by the Engineer



The reinforcement bars during the pre-assembly period and waiting time after
setting into the casting bed shall be controlled in dry condition by cover vinyl
sheet to prevent rust and corrosion.



Inspection and approval of rebar cage by the Engineer shall be carried out
prior to setting of inner forms.



With exterior girders, after installing steel cage into casting bed, we carry out to

locate PVC holes by ruler, installing PCV D170 pipes in the positions which
had been located by the steel wires to create waiting holes for PVC tubes.

d) Installation PC strand:


High tension steel strand shall be low relaxation after stranding and shall
conform to requirements of ASTM 416 Grade 1860.



All the strands shall be cut with enough length. PVC pipes with outer diameter
22mm and inner diameter 18mm and adhesive tapes shall be installed at end
of strands for de-bonding.

Page 20


Method Statement for Production of Super-T Girder



Each tendon shall be passed through by handwork when processing it we
must notice position of each tendon at ends girder must be same.



The strands are inserted through holes of end forms and tensioning beam,
make sure the strands are straight set form this end to the other, the strands
shall not be twisted or stuck.




When tensioning the strands shall be lengthened, therefore to make sure debonding length of the strands complied with design, ends of PVC pipes shall
be lengthened to inner face of tensioning beams so that PVC pipes shall not
be moved when the strands are being tension.



Preparation of tensioning:
- Before carry out the tensioning work, having to check whether the forms and

casting bed have the defects or not, in case of defects have no repair.
-

Checking the test result of the strands and the certificate of anchor wedge.

-

The combination of jack and gauge shall be calibrated once every six
months or otherwise instructed by the Engineer.

- Stressing on all strands shall be maintained between anchorages until the

concrete has reached the compressive strength required at time transfer of
stress to concrete, it is the minimum 85% of design concrete strength.

Page 21



Method Statement for Production of Super-T Girder

- In any case the jacking stress shall not exceed 75% of specified minimum

ultimate tensile strength of the pre-stressing steel.
-

Determine coefficient of friction of jack and anchor wedge (separate
determination should be done for every jack).

-

Strands shall be stressed uniformly and be kept in the dry condition, free
form rust, dirt, oil, mud…

-

The anchor wedge shall be free dirty, sand and oil period to installation into
the strands.



Order of tensioning of strands
-

Stressing shall be accomplished by single strand stressing. The amount of
stress to be given each strand shall be as shown in the calculation which the
contractor proposed and the Engineer approved.

- Tensioning of strands from centre to outside and symmetrically about centre


of girder with the following sequence
Order of pre- stressing of Super T girder type 38.3m (44 strands):

6
15

18
21

5
28
26

7
33
35

17
2
38

19
10
41
43

30
14
12


31
22
24

4
27
25

8
34
36

16
39
37

20
40
42

44

37 38 39
40 41 42
25 26 27 28 29 30
31 32 33 34 35 36
12 13 14 15 16 17 18 19 20 21 22 23 24
1 2 3 4 5 6 7 8 9 10 11


Page 22

29
1
43

32
11
44

3
13

9
23


Method Statement for Production of Super-T Girder

Order of pre- stressing of Super T girder type 34.3m (35 strand):
6
15

5
20

7
27
22


17
30
25

18
2
32
34

4
10
12

8
14
23

16
21
24

19
26
33

28
31
34

29

1
35

3
11

9
13

35

24 25 26 27 28
29 30 31 32 33
12 13 14 15 16 17 18 19 20 21 22 23
1 2 3 4 5 6 7 8 9 10 11

Order of pre- stressing of Super T girder type 33.3m (34 strands):

Page 23


Method Statement for Production of Super-T Girder

6
28

18
29

5

2

7
10

17
14
12
33

19
22
24

4
27
25

8
30
32

16
1
33

20
11
34


3
13

9
23

15
26

21
31

34

25 26 27 28
29 30 31 32
12 13 14 15 16 17 18 19 20 21 22 23 24
1 2 3 4 5 6 7 8 9 10 11




Tension force of one strand without friction of jack and working anchor slipping.
Tensioning the tendons to check straightness between the tendons with force is
0.1 Pk, marking on ends of strands to measure elongation.



Tensioning with each force level 0.2; 0.4; 0.6; 0.8; 1 Pk.




Calculating elongation through interpolate method taking into wedges slipping at
both of ends



Comparing actual elongation and design elongation.

e) Installing Inner Formwork:


Only installing inner formwork after finishing pre-stressing all strands.



Before installing, inner form shall be treated by form – release – oil. Form
release oil which the contractor uses is Sika Separol and It was approved by
consultant

Page 24


Method Statement for Production of Super-T Girder



Inner form shall be set up with support frame besides casting bed, then shall
be lifted by gantry crane and shall be installed inside casting bed.




Checking the position and shape of inner forms.



In process installing inner form by gantry crane, we combine installing PVC
tube in girder web, using tie steel to hold PCV tube on positions which are
marked.

Gantry crane
80 Tons

Lifting
Support frame

Fix inner form system
by PC bar

Inner form

Casting bed

f) Casting Concrete:

Page 25


×