FUJITA CORPORATION
PROJECT: KYOCERA DOCUMENT TECHNOLOGY VIETNAM FACTORY FUTURE PLAN
FUJITA CORPORATION VSIP IZ - HAI PHONG - VIETNAM
FUJITA
WORKING METHOD
(MECHANICAL WORK)
1. INSERT & ANCHOR WORKING PLAN
2. SLEEVE WORKING PLAN
3. GI PIPE WORKING PLAN
4. PPR PIPE WORKING PLAN
5. HDPE PIPE WORKING PLAN
6. PVC PIPE WORKING PLAN
7. COPPER PIPE WORKING PLAN
8. PENETRATION WORKING PLAN
9. DUCTING WORKING PLAN
10. INSULATION WORKING PLAN
11. HANGING WORKING PLAN
12. EQUIPMENT WORKING PLAN
13. SUPPORT & SLEEVE ON PC SLAB WORKING PLAN
HAI PHONG, 2018
FUJITA CORPORATION
PROJECT: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY
VSIP IZ - HAI PHONG - VIETNAM
WORKING METHOD
(MECHANICAL WORK)
1. INSERT & ANCHOR WORKING PLAN
HAI PHONG, 2018
FUJITA CORPORATION
Form:
Project: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY
Valid date:
Location: LOT 56A, 56B, 56C - VSIP HAI PHONG
Page
of
CHECK SHEET FOR ANCHOR BOLT WORK
Description: ………………………………………………………………………..
Location/Area: ………………………………..
Grid line: ………………………………..
Date of inspection: ………………………………..
Time: ….:….
Ref.No: ………………………………..
Refrred drawing: ………………………………..
Attached to: ………………………………..
No
1
2
3
4
5
6
Inspection Items
Anchor bolt
Material
Size
Quantity
Length
Setting position
Fix method
Color
Damage
Protection
Result
Judgement standard
OK
NG
OK
NG
OK
NG
OK
N
NG
OK
NG
OK
NG
OK
NG
OK
NG
OK
NG
Correct material
± 0.5mm
Visual check
± 2mm
± 2mm
Correct method
Visual check
Visual check
Visual check
Specification
Follow approval catalog
Follow approval catalog
Follow drawing
Follow working method
Notes:
1 Method & setting location should be insue by Kinden engineer
Status
Approved
FUJITA's COMMENT
Approved with comment
Rejected
Comment:
KINDEN VIET NAM CO.,LTD.
Prepared by:
Confirmed by:
Signature:…………………
Name:……………..……..
Date:………………………
File:
Issue No:
Checked by:
Signature:……………..
Name:……………..…..
Date:…………………..
FUJITA
Approved by:
Signature:………………….. Signature:…………………..
Name:……………..……….. Name:……………..………..
Date:……………………….. Date:………………………..
Distribution:
Revision:
Date:
/
/
By worker
Nut & Washer
Marking red color
By engineer
Marking red color
1. Step-1
2.Step -2
Cleaning hole
3.Step -3
Insert Drop - in anchor
4.Step -4
Use hammer to expand
Anchor leg
Marking & drilling hole
5.Step -5
Install thread rod, bolt
Fix with nut & washer
Thread rod
By worker
6.Step -6
Marking by permanent
maker
Thread rod
DROP IN ANCHOR LIST
L
d
No.
d
D
L
Drill Bit
mm
Depth of
Drill
1
M10
12
40
12
40
2
M12
16
50
16
50
D
MECHANICAL WORK
KYOCERA DOCUMENT TECHNOLOGY VIETNAM CO., LTD.
TYPICAL DRAWING
KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2
FACTORY
LOT 56A, 56B, 56C - VSIP HAI PHONG
PROJ. MANAGER:
DETAIL INSTALL PIPING BY ANCHOR
APPROVAL BY:
CHECKED BY:
CONSTR.STAGE
DESIGNED BY:
SCALE:
DRAWING
NUMBER:
DATE:
FUJITA CORPORATION
PROJECT: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY
VSIP IZ - HAI PHONG - VIETNAM
WORKING METHOD
(MECHANICAL WORK)
2. SLEEVE WORKING PLAN
HAI PHONG, 2018
FUJITA CORPORATION
Project: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY
Location: LOT 56A, 56B, 56C - VSIP HAI PHONG
Form:
Valid date:
Page
of
CHECK SHEET FOR SLEEVE WORK
Description: ………………………………………………………………………..
Location/Area: ………………………………..
Grid line: ………………………………..
Date of inspection: ………………………………..
Time: ….:….
Ref.No: ………………………………..
Refrred drawing: ………………………………..
No
1
2
3
4
5
Attached to: ………………………………..
Inspection Items
Sleeve material
Material
Size
Quantity
Length
Setting position
Reinforcing work
Protection
Cleaning
Result
Judgement standard
OK
NG
OK
NG
NG
N
NG
OK
OK
OK
NG
NG
NG
OK
NG
OK
OK
Specification
Correct material
± 1mm
Visual check
± 10mm
± 5mm
Correct material, size, q'ty
Visual check
Visual check
Follow approval catalog
Follow approval catalog
Follow drawing
Follow civil standard
Notes:
1 Method & setting location should be insue by Kinden engineer
2 Reinforced steel material shuold be same with structure work
3 Marking location of sleeve on surface of formwork, careful check reinforced rebar with engineer
Status
Approved
Comment:
FUJITA's COMMENT
Approved with comment
KINDEN VIET NAM CO.,LTD.
Prepared by:
Confirmed by:
Rejected
FUJITA
Checked by:
Approved by:
Signature:…………………
Signature:……………..
Signature:…………………..
Signature:…………………..
Name:……………..……..
Name:……………..…..
Name:……………..………..
Name:……………..………..
Date:………………………
Date:…………………..
Date:………………………..
Date:………………………..
File:
Issue No:
Distribution:
Revision:
Date:
/
/
Application category of sleeves and boxes
Sleeve and Box
Execution area
Paper
Vinyl tube
Steel sheet Flanged
Actual tube Wooden
Sleeve
Sleeve
Sleeve
Sleeve
Underground beam
and underground
outer wall
If waterproof is required
〃
If both sides are pits
〃
Other than above
○
○
If no fear of submergence
○
○
Other than above
○
○
Outer wall on the
ground
〃
RC beam
〃
RC wall
○
○
○
Exposed area
〃
RC floor
○
If the underpart is exposed
〃
Other than above
○
○
○
○
○
○
○
○
○
○
Other than above
Box
○
Exposed area
Other than above
Sleeve
○
○
○
○
○
○
○
An actual tube sleeve represents a tube and a duct.
Sleeve and insert work
Application category of sleeves and boxes
SI
0010
SLEEVE TYPES
Paper sleeve
(Unit: mm)
Dia.
50
75
100
125
150
175
200
250
300
350
400
500
600
Outside Dia.
55
81
107
132
158
183
210
260
312
364
416
520
620
Wall Thickness
2.5
3.0
3.5
3.5
400
Max length
4.0
4.0
5.0
5.0
500
6.0
600
7.0
8.0
10.0
10.0
700
800
1,000
1,200
If a paper sleeve which is longer than the maximum length is used, it should be reinforced.
Vinyl tube sleeve
(Unit: mm)
Dia.
50
65
75
100
125
150
200
250
300
Outside Dia.
60
76
89
114
140
165
216
267
318
Wall Thickness
51
67
77
100
125
146
194
240
286
Steel iron sleeve
Bore Dia.
Min thickness
Max length
(Unit: mm)
~150
151~300
301~500
501~700
701~
0.5
0.6
1.0
1.2
1.6
400
500
600
1,000
1,200
If a sheet iron sleeve which is longer than the maximum length is used, it should be reinforced.
Actual tube sleeve
(Unit: mm)
50
Bore Dia.
65
80
100
125
150
200
250
300
350
Outside Dia.
60.5
76.3
89.1
114.3
139.8
165.2
216.3
267.4
318.5
355.6
Inside Dia.
52.9
67.9
80.7
105.3
130.8
155.2
204.7
254.2
304.7
339.8
Bore Dia.
400
450
500
Outside Dia.
406.4
457.2
508.0
Inside Dia.
390.6
441.4
492.2
JIS G3452 carbon steel pipe for piping (black pipe) should be used.
Sleeve and insert work
Types of sleeve
SI
0020
Preparing flanged sleeves
All the one side welding
T
Dφ
t
Brim for nailing
1/2L
L
(Wall beam thickness-5)
Brim for nailing 3pcs
For Wall & Beam
All the one side welding
Brim for nailing
T
Dφ
Brim for nailing
t
1/2L
1/2L
50
L
(Floor thickness)
For floor
(Unit: mm)
Dφ
~100
125~
Brim width
T
50
65
Brim thickness
t
2.3
2.3
Sleeve with brim
The waterproof side is all one side welding.
Steel pipe is black pipe JIS G 3452.
Sleeve and insert work
Preparing flanged sleeves
SI
0050
Preparing actual tube ducts
W2
W1
H2
H1
L
W1
=
Duct size
W2
=
W1
H1
=
Duct size
H2
=
H1
L
=
(Wall thickness)
(Long side)
+ (The joining
flange size)
×
2
×
2
(Short side)
+ (The joining
flange size)
- 5
or (floor thickness)
+
50
(Unit: mm)
Duct'
side
long
General sleeve size
The fireproofing block sleeve size
W2
H2
H1+53.2
Sheet
thickness
1.6
W1+51.6
H1+51.6
Sheet
thickness
0.8
W1+56.2
H1+63.2
1.6
W1+62.0
H1+62.0
1.0
W1+83.2
H1+83.2
1.6
W1+82.4
H1+82.4
1.2
W1
W2
H2
~750
W1+53.2
760~1,500
1,510~
Provide air vent at bottom and top with size 9φ@300 if W1≽1,600.
Sleeve and insert work
Preparing actual tube ducts
SI
0060
Attaching actual tube ducts
Floor
Itself duct
50
釘
Reinforcement wood. It put in center
if duct' long side more than 1000.
But in case steel plate thickness is 1.6 it is unnecesary
Wall
Nail
5
Reinforcement wood. It put in center if duct' long
side more than 1000. But in case steel plate thickness
is 1.6 it is unnecesary
≒30
In case duct' long side more than
1000 make hole pit 9F300
Sleeve and insert work
Itself duct
Thickness =wall thickness -5mm
Attaching actual tube ducts
SI
0070
Preparing boxes
For walls
Air vent hole
If the width is 1,000mm or more, insert a
reinforcing wood in the center of the box.
L
L is wall thickness -5mm.
Air vents are holed in the pitch ofφ9 300
at the top and the bottom surface if the
width of the box is 1,000mm or more.
Reinforced wood
W
If the width is 1,500mm or more, the box should
be divided into two parts. The clearance A
should be 100mm. Polish it after casting
concrete (no reinforcing).
Others are the same as above.
W
A
L
W
For floor
If the width is 1,000mm or more, insert
reinforcing woods on all sides of the upper
and the lower surface.
H
The height is –10mm for a direct
retaining floor and +50mm for others.
The lid is a laminated board of 9mm
thick and the width is 600mm or more.
The longer side of the duct should be
1,510 or more +50mm.
Reinforced wood
Wooden frame is polywood 6mm.
Box size is necessary size + 100mm. But, if duct long ≽ 1,500 is + 50mm.
Sleeve and insert work
Preparing boxes
SI
0080
Attaching boxes
Direct retaining floor
Box
10
Nail
Frame
Box
General floor
50
Nail
Frame
Wall
Box
Frame
Nail
5
Sleeve and insert work
Attaching boxes
SI
0090
Protection after box pulling-out
Conner frame made by sun wood 25x30
30
30
W
t
(Openning size) W
600×600 or Less
1,500 x 1.500 or less
Thickness of
laminated wood t
12
24
Periphery should be enclosed round if the dimension is 1,500x1,500 or
more.
Protection of itself pipe duct
Reinforced angle
Cover
50
Sleeve
The lid is a laminated wood with thickness of 9mm or more.
A reinforcing angle is equipped at an opening with a longer side of 1,000mm or more.
The dimension of the steel material is the same as the dimension of the reinforcing
angle of the duct.
Sleeve and insert work
Care of opening
SI
0130
FUJITA CORPORATION
PROJECT: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY
VSIP IZ - HAI PHONG - VIETNAM
WORKING METHOD
(MECHANICAL WORK)
3. GI PIPE & BS PIPE WORKING PLAN
HAI PHONG, 2018
FUJITA CORPORATION
Form:
Project: KYOCERA DOCUMENT TECHNOLOGY VIETNAM PHASE 2 FACTORY Valid date:
Location: LOT 56A, 56B, 56C - VSIP HAI PHONG
Page
of
CHECK SHEET FOR GI & BS PIPING
Description: ………………………………………………………………………..
Location/Area: ………………………………..
Grid line: ………………………………..
Date of inspection: ………………………………..
Time: ….:….
Ref.No: ………………………………..
Refrred drawing: ………………………………..
Attached to: ………………………………..
Inspection Items
Result
Judgement standard
Specification
No
Material
1
NG
Kind of pipe, CO, CQ
Correct material
Follow approval catalog
OK
NG
Kind of support
Correct material
Follow approval catalog
OK
NG
OK
Kind of painting
Correct material
Follow approval catalog
OK
NG
Pipe size
± 0.5mm
Follow approval catalog
OK
Quantity
Visual check
NG
Length
± 5mm
NG
OK
N
Setting position piping
± 5mm
Follow drawing
2
OK
NG
Interval support
±
50mm
Follow drawing
3
OK
NG
Tighting bolt, nut
Visual check
2 times
4
OK
NG
Pipe level
± 5mm
Follow drawing
5
OK
OK
NG
Fix method
Correct method
Follow working method
6
OK
NG
Maintenance space
Visual check
Follow actual site
7
OK
NG
Piping alignment
± 5mm
8
OK
NG
Color of pipe
Visual check
9
OK
NG
Anti- rust painting
Visual check
10
OK
NG
Painting
Visual check
11
OK
NG
Damage
Visual check
12
OK
NG
Clean work
Visual check
13
Notes:
1 Method working & installation working should be insue by Kinden engineer
Status
Approved
Comment:
FUJITA's COMMENT
Approved with comment
KINDEN VIET NAM CO.,LTD.
Prepared by:
Confirmed by:
Signature:…………………
Name:……………..……..
Date:………………………
File:
Issue No:
Signature:……………..
Name:……………..…..
Date:…………………..
Rejected
FUJITA
Checked by:
Approved by:
Signature:…………………..
Name:……………..………..
Date:………………………..
Signature:…………………..
Name:……………..………..
Date:………………………..
Distribution:
Revision:
Date:
/
/
Thread junction of copper pipe
Cutting
An automatic sawing machine, a lathe or a pipe cutter should be used as a tool. Pipes
should be cut vertically to the axis of the pipe.
Pipe end surface processing:
Burs should be removed with a reamer, a filer, etc.
Screw-thread cutting:
Cut a taper thread (JIS B0203-82) for pipes with a screw-thread cuter.
Pre-treatment
Wipe out cutting oil, cutting powder, dust, etc.
Applying cementing materials Use liquid sealants shown in the table below or equivalents according to
the application of piping.
Application of piping
Product number
Oil・Air
Helmetic No.B-X
Drainage, extinction
Helmetic No.S-2
Cooling water, cold/hot water
Helmetic No.S-2
Junction
Steam
Helmetic No.H-2
Propane gas
Helmetic No.G-1
Use pipe wrenches and chain wrenches (Chenton) which are appropriate
to the pipe diameter.
Pipe applicable
15A~50A
65A~100A
Finishing
Piping work
Index of remaining number of
threads
3threads
3.5 threads
Apply anticorrosive paints to the remaining thread area and the cutting
traces due to pipe wrenches, etc
Thread junction of copper pipe
P
0080
Weld junction of steel pipe
Cutting
An automatic sawing machine, a lathe or a pipe cutter should be used as a tool.
Pipes should be cut vertically to the axis of the pipe.
Pipe end surface
processing
Burs should be removed with
a reamer, a filer, etc.
Groove preparation
A groove of a pipe with a thickness less than 6.0mm should be I-shape. A groove
of a pipe with a thickness of 6.0mm or more should be V-shape.
60~90°
60~90°
6.0mm>t
6.0mm< t
=
0~2mm
Pre-treatment
Weld rod
1mm
1~3mm
Wipe out water, oil and extraneous matters from the welded section.
It is specified in JIS Z3211-91 (Coated arc weld rod for soft steel). The
diameter of rods are shown below.
Pipe dia.
Diameter of weld rods mm
~ 25A
2.6
32A ~ 125A
3.6
150A~~ 300A
3.2(1layer) 4.0(2layer)
Store them in a dried area. Do not use rods which soaked up moisture or whose
covering material was removed, stained or deteriorated.
Junction
Join pipes by butt welding. Adjust pipes in such a way that pipe axes are
aligned straight as a line. Perform tack welding at first (at three or four points).
Then, perform final weld.
Standard welding current (welding rodφ3.2) is shown below.
Pipe dia.
40A~65A
80A~200A
250A~350A
~32A
Current(A)100~130150~180180~200200~250
Finishing
Piping work
After welding, remove slag with blush. Apply anticorrosion paint.
Weld junction of steel pipe
P
0090
Flange welding of steel pipes
Tack weding
Perform one point welding. Adjust the flange surface at right angles with the
pipe using a ruler. Then, perform three or four point tack welding.
weld 3~4 points.
Ruler
Pipe
Flange
One side welding
Working pressure should be 0.98Mpa (10kg/cm2).
2
1
Flange
Pipe
t
Flange and end of pipe
is the same surface
Both side welding
Beveling
Working pressure should not exceed 0.98Mpa (10kg/cm2).
Flange
2
1
t
Pipe
t
Finishing
Remove peeled films with a wire brush, etc if the inner surface is galvanized.
Perform Roval paint.
Apply anticorrosive coating on the welded area after removing slag, etc.
Flange gasket
Pipe type
For general water
supply and drainage
Specification
Rubber sheet for water
service
Compressed asbestos sheet
For general cold/hot
Compressed asbestos sheet
water
Compressed asbestos sheet
For Steam
(for high temperature)
Compressed asbestos sheet
For Oil
(for oil)
Piping work
Flange welding of steel pipes
Standard
JIS K 6353 (1class 1No.)
JIS R 3453 (2 class)
JIS R 3453 (1 class)
JIS R 3453 (1 class)
JIS R 3453 (3 class)
P
0100
SUPPORT INTERVAL
Dia.
15
Classification
20
25
Shape steel sway
bracing support
Rod hanger
Steel pipe and
stainless pipe
32
40
50
65
80
100
125
≼ 2.0m
150
200
300
≼ 3.0m
PVC pipe and PE
pipe
≼ 1.0m
≼ 2.0m
Copper pipe
≼ 1.0m
≼ 2.0m
Cast iron pipe
One per each straight pipe and variant pipe
Lead pipe
≼ 1.5m
Steel pipe,
cast iron pipe
and stainless
250
≼ 8.0m
≼ 12.0m
PVC pipe and PE
pipe
≼ 6.0m
≼ 8.0m
≼ 12.0m
Copper pipe
≼ 6.0m
≼ 8.0m
≼ 12.0m
Notice 1. When heavy loads such as electric operated valves or joints with flexibility are used, they
should be suspended at the nearest point from the load or joints in addition to the suspension
with interval shown in the table above. Support the curved area or the branch as required.
2. The piping with nominal diameter 100 or more connected with the housing type pipe joints, if
the length of the suspension material is 400mm or less, should be suspended with eyebolts,
chains, etc instead of steel bar suspension in order not to generate flexural stress in the
suspension material.
Use a roller fixture, etc when a horizontal pipe for steam is supported by a shape steel steady
3.
brace from below.
A shape steel steady brace to prevent buckling should be equipped between an expansion joint
4.
and a fixed point of a horizontal pipe for steam.
5. A horizontal section of a drainage lead pipe which is longer than 1.0m should be carried on a
semicircle trough (standard thickness of the thick plate is 1.0m or more) made of galvanized
steel plate and suspended or supported.
6. The shape steel steady brace is not required for steel pipes, cast iron pipes and stainless pipes
with nominal diameter 50 or less, and vinyl pipes, polyethylene pipes and copper pipes with
nominal diameter 20 or less. If required, the supporting intervals are stated elsewhere.
Suspension bolt diameter (mm)
Dia.
Pipe
15
20
25
32
40
50
65
80
100
125
9
All pipes
150
200
12
Notice If suspension loads are concentrated in an area, check it and select a suspension
diameter for areas.
Piping work
Support interval and suspension bolt diameter
P
0470
250
300
15