Introduction
This document defines the procedures
for installing products contained in the
KRONE Certified Cabling System. The
Installation Procedures are part of a series
of documents supporting the design, instal-
lation, and use of the KRONE Certified
Cabling System.
KRONE reserves the right, without
notice, to change its products as progress
in engineering or manufacturing methods
or other circumstances may warrant.
If you have questions on the content or
intent of this document, please call the
Tech Support Line at 800-775-5766.
IP-1
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-2
Installation Procedures
8-Pair HighBand
TM
and Series 2 Frame Mount
(Wall or EIA Rack)
STEP 1:
Secure Type 105 mounting
bracket to mounting frame
using rivets provided. Install


rubber grommets.
STEP 2:
Route cables through grommet
holes and secure as required.
STEP 3:
Beginning at bottom of mount-
ing bracket, cut cables 18" from
front edge of mounting bracket,
strip back 6" of sheath, and split
pairs back 4½".
Incoming Cables
Mounting Frame
Type 105
Mounting Bracket
IP-3
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
8-Pair HighBand and 10-Pair Series 2 Rod Mount
Using Universal Mounting System (UMS) (Using EIA
Rack or Wall)
STEP 1:
Assemble the UMS brackets by
sliding the two halves all the way
together. Repeat for all brackets.
STEP 2:
Secure UMS Backboard to rack.
Install two top screws first, then
hang the backboard and install
remaining screws.

STEP 3:
Secure UMS Brackets to
backboard per diagrams for the
desired layout printed on the
backboard. Use provided rivets
to attach.
STEP 4:
Secure included jumper rings
using rivets provided or install
separate large jumper ring as-
sembly using screws provided.
STEP 5:
Pull Cables through center hole
of bracket and strip back sheath
as indicated.
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-4
Installation Procedures
8-Pair HighBand and 10 Pair Series 2 Rod Mount
Using UMS (Wall Mount)
STEP 1:
Assemble the UMS brackets by
sliding the two halves all the way
together. Repeat for all brackets.
STEP 2:
Attach first (top left) UMS to ply-
wood backboard with top left screw.
Do no tighten screw down all the
way. Using a level, adjust bracket

and secure top left screw all the
way. Repeat for the top right screw.
Secure remaining two screws at
bottom.
STEP 3:
Using interlocking tabs, secure next
bracket or wire manager, and se-
cure with four screws. Continue
until all brackets and wire manag-
ers are secured.
STEP 4:
Install wire management rings
using rivets provided.
STEP 5:
Route cables from top or bottom.
Dress and strip as shown. (Cables
can be routed through center
bracket hole if using a false wall.)
Secure slack loop bundles using tie
wraps to tabs on inside of UMS
bracket.
IP-5
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
Top Wall Mount Adapter
Type 105
Mounting Bracket
Installation Procedures
STEP 1:

Secure bottom mounting
adapter (without jumper
rings) level to backboard.
STEP 2:
Snap the Type 105 mounting
bracket into the bottom
mounting adapter (rubber
grommets optional).
STEP 3:
Snap top mounting adapter
(includes jumper rings) onto
mounting Bracket and se-
cure to backboard.
STEP 4:
Route cables from above or
below mounting bracket and
secure as required.
STEP 5:
Beginning at edge of mount-
ing bracket, cut cables 18"
from front edge of mounting
bracket, strip back 6" of
sheath, and split pairs back
4½".
8-Pair HighBand
TM
and Series 2 Termination Block Direct Wall Mount
Bottom Wall Mount
Adapter
Incoming Cables

KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-6
Installation Procedures
HighBand
Termination Block
STEP 1:
Holding block in hand. Dress
pairs through wire guides
and across contact slots
(maintain twist up to point of
connection). Maintain
sheath up to back of block.
Repeat for second cable.
8-Pair HighBand
TM
Block Termination Procedures
(Wall or EIA Rack)
STEP 2:
Snap block onto mounting
bracket and terminate conduc-
tors with KRONE tool.
STEP 3:
Flare wires with thumb from the
center of both cables to the
outside of the block. This will
flatten the arc in the cables so
there is no chance of skinning
the pairs while installing block
on the bracket.

Type 105
Mounting Bracket
KRONE Tool
UMS
IP-7
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
Individual Label Holder
STEP 4:
Repeat steps 1 through 3 work-
ing from bottom to top of mount-
ing bracket for remaining mod-
ules.
STEP 5:
Install block label holder at top
of mounting bracket and label
individual blocks as required.
8-Pair HighBand
TM
Block Termination Procedures
(Wall or EIA Rack) (Cont.)
Type 105
Mounting Bracket
Block Label Holder
UMS
Block Label Holder
Individual Label Holder
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98

IP-8
Installation Procedures
STEP 1:
Slide halves of bracket to-
gether to its 1st position.
UMS Backboard
STEP 2:
Secure UMS Mounting Bracket
to backboard using rivets pro-
vided.
STEP 3:
Route cables through opening in
back of UMS (bracket) and
secure to tabs on inside of
bracket using tie wraps.
STEP 4:
Snap FT Block base onto the top
of the mounting bracket.
STEP 5:
Bundle six (6) 4-pair cables
together for each 25-Pair FT
block and route through wire
management ring on back of the
25-Pair FT base.
STEP 6:
For each cable in its relative
position, cut cable 18" from front
of the base, strip back 6" of
sheath, and split pairs back 4.5"
to front of base.

25-Pair FT Mount (EIA Rack)
25-Pair FT
Termination Block
Mounting Frame
Incoming Cable
Plastic Rivets
IP-9
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
25-Pair FT Mount (Wall)
STEP 1:
Assemble brackets to first
position and secure with
screws as shown.
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-10
Installation Procedures
25-Pair FT Mount (Wall) (Cont.)
STEP 3:
Using interlocking tabs, secure
next bracket or wire manager
and secure with four (4) screws.
Continue until all brackets and
or wire manages are secured.
STEP 4:
Install wire management rings
using the rivets provided.
STEP 5:

Snap FT base in position you
wish to terminate, route cables
from top or bottom and secure
with tie-wraps to tabs inside
mounting bracket.
STEP 6:
Bundle six (6) 4-pair cables or
one 25-Pair cable and route
through wire management ring
on back of 25-Pair FT base.
STEP 7:
For each cable in its relative
position, cut cable 18" from front
of base and remove the 6" of
sheath. Separate pairs and split
pairs approximately 4.5" back.
STEP 2:
Attach UMS to plywood
backboard with top left screw.
Do not tighten screw down all
the way. Using a level,
adjust the bracket and se-
cure top left screw all the way
down. Repeat for top right
screw.
IP-11
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
25 Pair FT

Termination Block
KRONE Tool
UMS
Mounting Bracket
STEP 1:
Install the 25-Pair FT connector
onto the base, making sure you
install with the comb facing
away and down.
STEP 2:
Dress pairs across contact slots
(maintain twist up to point of
connection). Sheath should be
maintained within 2" of the
connection point.
STEP 3:
Terminate conductors with
KRONE tool or Harris Dually
Blade for 814 or 914 tool handle.
Repeat steps 1 and 2 for remain-
ing cables.
25-Pair FT Block Termination Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-12
Installation Procedures
UMS
Mounting Bracket
Connector
Base

STEP 4:
Pull Connector from the center to
release connector from the base.
STEP 5:
Unsnap the base from the
mounting bracket. Replace base
on mounting bracket above the
terminated cables/connector.
STEP 6:
Flip the connector 180° and
insert connector into the base.
Slide block assembly down until
it stops.
Note: Check wire pairs for any
kinks, high bends or knuckle
kinks.
25-Pair FT Block Termination Procedures (Cont.)
IP-13
Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
UMS Mounting
Bracket
25-Pair FT
Termination Block
Label Strip
Hinged Label Holder
STEP 1:
Repeat steps 1 through 6 of
Termination Procedures,

working from bottom to top of
mounting bracket for re-
maining blocks.
STEP 2:
Label all FT blocks as shown.
25-Pair FT Block Labeling Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-14
Installation Procedures
Incoming Cables
24 Port
Plug & Play Patch Panel
Installation Procedures
STEP 1:
Secure the patch panel to the
rack.
Plug & Play Patch Panel EIA Rack Mount
STEP 2:
Route cables above or below
right side of the patch panel,
secure as required.
STEP 3:
For each cable in its relative
position cut cable 4" from be-
yond its jack location, strip back
4" of sheath, and split pairsback
3¼".
19” EIA Rack
IP-15

Installation Procedures
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
Installation Procedures
STEP 1:
Secure the wall mount
bracket to the backboard.
STEP 2:
Secure the patch panel to the
wall mount bracket.
STEP 3:
Route cables from above or
below the hinged side of the
patch panel.
STEP 4:
For each cable in its relative
position cut cable 4" from
beyond its jack location, strip
back 4" of sheath, and split
pairs back 3¼".
Plug & Play Patch Panel Wall Mount
Wall Mount Bracket
24 Port Plug & Play
Patch Panel
Incoming Cables
KRONE Installation & Testing Procedures MK023-01
Printed in USA 1/98
IP-16
Installation Procedures
KRONE Tool

24 Port
Plug & Play Patch Panel
STEP 1:
Route conductors through
center of jack and dress
conductors through contact
slots (maintain twist up to
point of connection). Sheath
should butt up against back
of jack.
STEP 2:
Terminate conductors with
KRONE tool.
Plug & Play Patch Panel Jack Termination

×