TIGER DRYLAC
Quality Control
Test instruction
Resistance against mortar
PA 14
Approved by:
Ing. Holzberger
Issue date
January 93
Update status
00
Folder - Nr
HQ 03 - 18
page
1/3
1. Outline:
1.1 Test standard
•
ASTM C 207
•
ASTM D 3260
1.2 Explanation
This test should guarantee the resistance against mortar.
2. Work instruction
2.1 Brief description of the procedure
Mortar mixed accordingly to ASTM C 207 is put on the coated test sheet metal. The test has
to take place accordingly to ASTM D 3260.
2.2 Requirements
After 24 hours the mortar should be removed easily and without arrears. Mechanical
violations of the coating are not to be considered by grains of sand.
3. Test intervals
3.1 Original inspection
At the time of the termination of a development a check is to be executed before the mass
production.
3.1 Repeat inspection
The check is to be executed in an interval of one year. Those products, which pass through
annual system inspections of the GSB or Qualicoat, are excluded.
4. Analysis
The analysis has to take place without consideration from possibly occurring scratches. The
removal of the mortar must be easily possible, there mustn’t be any color modification in the
powder coating.
If the requirements are not fulfilled all loads are to be locked and the customer about the lack
to be informed.
TIGER DRYLAC
Quality Control
Test instruction
Resistance against mortar
PA 14
Approved by:
Ing. Holzberger
Issue date
January 93
Update status
00
Folder - Nr
HQ 03 - 18
page
2/3
5. Responsibility
5.1 Original inspections
•
The internal checks are passed on by the laboratory conductor or in its absence by its
deputy to the laborants trusted with the check.
•
The results are in that above mentioned sequence to transmit.
•
With negative results the product may not become certified for the sales. The
prescription should accordingly be improved.
5.2 Repeat inspections
•
The inspection results are to be transmitted to the responsible laboratory conductor or in
its absence to its deputy, in order to initiate, if necessary, following steps.
•
With a negative result the barrier of the product is to be arranged by the QA and a
recheck from the above mentioned initiated.
This product is locked out from the GSB till repeat inspections.
The sales conductor and its deputies are informed about the product barrier.
5.3 Customer information
•
The sales department has to inform the customers about the loss of the GSB -
permission.
•
All customers which purchased this product are to be informed about the result.