HANOI UNIVERSITY OF CIVIL ENGINEERING
FALCUTY OF ECONOMICS AND CONSTRUCTION MANAGEMENT
DEPARTMENT OF CONSTRUCTION ECONOMICS
PROJECT
DETERMINE THE BID PRICE OF THE BIDDING PACKAGE
‘‘CONSTRUCTION OF THE STRUCTURAL COMPONENTS’’
Category: Detached House, Duplex House, Shophouse, Townhouse
under Construction Investment Project V Residences
SUPERVISOR: Ph.D NGUYEN TUAN ANH
STUDENT:
STUDENT ID:
CLASS:
CODE:
DANG PHAM VIET ANH
1500665
65KTE
767411
Hanoi – 2023
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
INTRODUCTION
I. The role and purpose of construction bidding
1. Role of construction bidding
The bids for construction works could bring advantages from different points of view:
For the authority:
o Improve the capability of the officers from the state to local authorities.
o Increase the management role of the authority.
o Achieve high-quality construction works.
o Save the Budget State.
For the owner:
o Choose the most suitable contractor compared to the owner’s requirements.
o Prevent the monopoly of some contractors, increase the competitiveness and the role of
the owner to the contractor.
o The responsibility and obligations of the Owner which is authorized by the State for
implementation of an investment project will be clarified.
For the contractor:
o Ensure the equality to all the contractors. Due to competitiveness, each contractor needs to
develop, research, apply technology advances, suitable business models to win the bids, as
a contribution to the development of the construction industry in general.
2. Purposes of construction bidding
Construction bidding is to provide the owners with the optimum price for the project and provide
multiple entities the opportunity to compete for work.
II. The role of bid prices in construction bid
According to Government’s regulations: “The bid price is the price in bid document after
deducting the discount (if any), including all costs necessary to fulfill the requirements of the bid
document on schedule.
The bid price is based on the production norm of the enterprises corresponding to the scientific –
technological and the business strategy of contractor. From there, each contractor has a different
bid price. Contractors with reasonable technological measures and low prices will be selected.
The bid price is the contractor's ability, which is the basis for investors to rank the contractors,
thereby selecting the best contractor.
The bid price is an important indicator that plays a decisive role in the contractor’s ability to win
the bidding, directly affecting the production and business results of construction enterprises.
III. Project’s tasks
Determining the bidding package price: “Construction the structural components, exterior
finishes. Category: detached house, duplex house, shophouse, townhouse under construction
investment project “V Residences”.
Determining the bid price for the package: “Construction the structural components, exterior
finishes. Category: detached house, duplex house, shophouse, townhouse under construction
investment project “V Residences”.
Comparing the bid package price and the bid price to decide whether to participate in bidding or
not.
Present the bidding price in full unit price.
Topic data:
Number of houses
DL
SL
SH
TH
7
6
7
4
Type of contract
Project
component
Location
Lump Sum
Contract
Foundation
Bao Lam, Cao Bang
DANG PHAM VIET ANH – 1500665 – 65KTE
2
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
CHAPTER 1
THEORETICAL BASIS OF THE BID PRICES
I. Definition of construction bid price
The bid price means the price stated by a tenderer in application for bid participation, quotation,
including all costs for implementation of bidding package as required by dossier of bid invitation,
dossier of requirement.
The bid price is determined based on the selected technical-technological solutions, norms, unit
price, bidding strategies and management of contractors. In case the contractor has a discount
letter, the bid price is the bid package price after the discount.
II. Contents and structure of construction bid price
Contents and structure of construction bid price depends on the type of contract.
For Lump sum contract:
Construction cost
= T + GT + LN
G
+ GTGT
In which:
o Direct cost:
T = VL + NC + M
Material cost: VL
Labor cost: NC
Equipment cost: M
o Indirect cost:
GT = C + LT + TT
General cost: C
Cost for temporary housing and construction management: LT
Cost for some work cannot be determined form the design: TT
Profit before tax: LN
Value added tax: VAT
Other cost: G
III. Methods of determining the bid price.
1. Input resources demand analysis
Material demand analysis:
VL =
Q x ĐM
NC =
Q x ĐM
Labor demand analysis:
Construction machine demand analysis:
M =
Q x ĐM
2. Determine price of input resources
3. Determine the direct cost
Material cost:
VL =
VL x ĐG
NC =
NC x ĐG
Labor cost:
Construction machine cost:
DANG PHAM VIET ANH – 1500665 – 65KTE
3
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
M=
M x ĐG
4. Determine the indirect cost
General cost shall be determined in percentage estimated or detailed estimate of each item.
Cost for the construction of makeshift houses for accommodation and administration on site.
The cost of work can not determine the volume of the design.
The one-time cost of equipment.
Cost for makeshift works.
5. Estimate the expected profit
TL = i% x (T + GT)
6. Determine the value added tax and construction cost summary
TVAT = t% x (T + GT + TL)
G
= T + GT + TL + TVAT
7. Determine the contingency cost
IV. Construction bid price process.
V. Presentation the construction bid price in bids
CHAPTER 2
DETERMINING THE BID PRICE FOR THE PACKAGE
CONSTRUCTION OF THE STRUCTURAL COMPONENTS’’
Category: Detached House, Duplex House, Shophouse, Townhouse under
Construction Investment Project V Residences
I.
1.
Introduction of bid package and requirements of bids.
Bid package introduction.
Project’s name: Investment in construction of V Residences.
Owner: V Joint Stock Company (V.JSC)
Name of bid package: Construction the structural components. Category: detached house, duplex
house, shophouse, townhouse under construction investment project of V Residences.
Location: Bao Lam – Cao Bang
Characteristics of structural solutions: Based on the design drawings and the related
documentation.
Contractor selection form:
o Open bidding
o Bids evaluation method: method of combination of technical aspect and price
DANG PHAM VIET ANH – 1500665 – 65KTE
4
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
2. Summary of the requirements of the bids related to the determining bid price.
Table 2.1.1: Bill of quantities
QUANTITY PER HOUSE
No
NAME OF WORK
EARTHWORKS
Excavation and leveling by excavator
1
1,25m3, soil grade II
Soil excavation for strip footing
2
manually, width ≤ 3m, depth ≤ 1m, soil
grade II
Soil embankment by hand compactor
3
70kg, soil compaction factor K=0,90
Soil transportation by 5-ton dump
4
truck in radius <= 1000m, soil grade
II
Soil transportation by 5-ton dump
5
truck for the next 4km in radius ≤5km,
soil grade II
Soil transportation by 5-ton dump
6
truck outside the radius >5km, soil
grade II (next 10km)
FOUNDATION
Mixing concrete by mixers poured
7
manually, leveling concrete, width
≤250 cm, stone 4x6, grade 100
Wooden formwork. Strip footing
8
formwork
UNIT
QUANTITY OF THE PROJECT
DL
SL
SH
TH
7
6
7
4
TOTAL
DL
SL
SH
TH
100m3
1,022
1,123
0,962
0,548
7,154
6,738
6,734
2,192
22,818
100m3
11,352
11,887
10,692
6,085
79,464
71,322
74,844
24,34
249,97
100m3
0,843
1,075
0,892
0,317
5,901
6,45
6,244
1,268
19,863
100m3
0,292
0,167
0,177
0,292
2,044
1,002
1,239
1,168
5,453
100m3
0,292
0,167
0,177
0,292
2,044
1,002
1,239
1,168
5,453
100m3
0,292
0,167
0,177
0,292
2,044
1,002
1,239
1,168
5,453
m3
10,237
11,748
9,445
5,901
71,659
70,488
66,115
23,604
231,866
100m2
0,192
0,22
0,185
0,115
1,344
1,32
1,295
0,46
4,419
DANG PHAM VIET ANH – 1500665 – 65KTE
5
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
9
10
11
12
13
14
15
16
Ready-mixed concrete, poured by
concrete pump, concrete foundation,
foundation width ≤250 cm, stone
1x2, grade 250
Ready-mixed concrete, poured by
concrete pump, concrete foundation
wall, stone 1x2, grade 250
Wooden formwork. Strip footing
formwork
Wooden formwork. Wall bracing
formwork
Fabrication and installation of
reinforcing steel. Reinforced
foundation, diameter < 10mm (steel
grade CB240T)
Fabrication and installation of
reinforcing steel. Reinforced
foundation, diameter =10mm (steel
grade CB400V)
Fabrication and installation of
reinforcing steel. Reinforced
foundation, diameter ≤18mm (steel
grade CB400V)
Fabrication and installation of
reinforcing steel. Reinforced
foundation, diameter >18mm (steel
grade CB400V)
m3
41,313
39,181
32,946
19,21 289,191 235,086 230,622
76,84
831,739
m3
2,109
2,337
2,45
1,577
14,763
14,022
17,15
6,308
52,243
100m2
0,699
0,736
0,76
0,337
4,893
4,416
5,32
1,348
15,977
100m2
0,205
0,234
0,245
0,158
1,435
1,404
1,715
0,632
5,186
ton
0,39
0,491
0,479
0,259
2,73
2,946
3,353
1,036
10,065
ton
0,612
0,934
0,751
0,455
4,284
5,604
5,257
1,82
16,965
ton
0,271
0,273
0
0
1,897
1,638
0
0
3,535
ton
1,141
1,478
1,728
0,88
7,987
8,868
12,096
3,52
32,471
DANG PHAM VIET ANH – 1500665 – 65KTE
6
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Requirements for quality and specifications of materials
3.
Concrete mortar used in the construction structures shall be crushed stone commercial
concrete with 1x2cm aggregate, grade 250, with a slump of 14+/-2 cm.
Cement used in construction shall be produced according to the PC-30 rotary kiln
technology as per the current TCVN (Vietnamese standard).
Sand used in plastering and concrete shall be clean, with particle size and impurities
meeting the current TCVN standards.
Steel used in construction shall belong to the AI and AII groups as per the current
TCVN standards (AI for steel ≤ 8mm, AII for steel ≥ 10mm).
The bricks used for construction shall be solid bricks produced by manufacturing plants
with a brick grade of 75 (or as per the bid invitation).
Construction mortar: Cement and yellow sand mortar, grade 50 (or as per the bid invitation).
Plastering mortar: Cement and black sand mortar, grade 75 (or as per the bid invitation).
Wood used for doors and door frames shall belong to group 2 wood (or as per the bidinvitation).
Glass used for window and door assembly shall be 5mm thick colored glass (or as per the bid
invitation).
Floor tiles: Locally manufactured ceramic tiles (or as per the bid invitation).
Wall tiles: Locally manufactured ceramic tiles (or as per the bid invitation).
Requirements of technological solution for the bid package
Construction of soil excavation by backhoe excavator combined with manually repair. Using
dump truck to remove excess soils.
For main structures such as: foundation, column, slab, beam, using ready-mix concrete, poured by
concrete pump. Other structures: stairs, lintel, chajja, using concrete mixed by concrete mixer
poured manually.
For formwork of foundation, beam, column, slab, stairs using steel formwork. Other components
use timber formwork.
Reinforcement work: reinforcing steel will be cut, bent as the design on site, installed manually at
the positon which has been marked.
Finishing works: are technological solution which are being commonly used in civil buildings,
hotels, villas, guest houses with the height corresponding to the number of floors ≤ 5 floors (≤
16m)
Type of contract: Lump sum contract
Requirements for capital advance, advance capital recovery and payment
Pursuant to the Decree No. 37/2015/ND-CP “Detailed regulations on construction contract”
dated April 22, 2015 of Point b, Clause 5, Article 18, the contractor is received in advance for
15% of the contract value with the contract value from 10 – 50 billion.
The contractor will be received in advance for 95% of finished and inspected construction works
according to stages after completing 30% of the contract value.
The contractor will be received in advance for 95% of finished and inspected construction works
at the 2nd phase after completing up to 60% of the contract value. (30% of the contract value).
The contractor will be received in advance for 95% of finished and inspected construction works
at the 3rd phase after completing up to 90% of the contract value. (30% of the contract value) but
deduct 10% of the advance value contract from the commencement of construction work.
The contractor is received the rest at the end of the contract but 5% of the contract value will be
kept by owner during the maintenance phase or can apply the form of bank guarantee.
Introduction of contractor participating in bidding
Name of contractor: V.A Construction Group Joint Stock Company.
o Total employees: 28915 employees
DANG PHAM VIET ANH – 1500665 – 65KTE
7
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
o Direct employees: 21200 employees
o Total value of fixed assets: 1161 billion VND
No.
1
2
3
4
5
6
7
8
9
10
11
12
Table 2.1.2. List of construction equipment and equipment of the contractor
Equipment
Unit
Quantity
Original Cost
Wheel excavator 0,35m3
piece
4
420 million VND
Tower crane
piece
2
7,3 million VND
Hoist
piece
8
26 million VND
Dump truck 9 tons
piece
13
320 million VND
Dump truck 5 tons
piece
10
190 million VND
Truck 9 tons
piece
10
300 million VND
Welding machine 250-400
piece
8
3,2 million VND
Concrete mixer 250L
piece
6
17,5 million VND
Internal vibrator 3 phase electricity
piece
16
3,5 million VND
External vibrator
piece
12
1,6 million VND
Mortar mixer
piece
14
2,2 million VND
Steel scaffolding
set
10
100 million VND
Own working capital: 100% of total working capital demand
Organizational structure of enterprise for each bid package:
Construction manager: Chief engineer: 01 person
Deputy construction manager: Engineer with seniority of 10 years: 01 person
Technical staff: Civil engineer 02 persons
Economic staff : Engineer, bachelor 02 person
Other staffs: Vocational 01 person
Watchman: 03 persons
II. Determine the bid package price
1. Principles to determine the bid package price
Based on bid quantity and design from the owner.
Estimating norms and construction unit price of provinces or cities.
The State’s current regulations on determining the price of construction estimate
Notice price adjustment of provinces or cities.
Unit price index issued by Department Construction of Province or Ministry of
Construction.
Type of contract specified in bids
Legislations:
o Circular 11/2021/TT-BXD dated Ausgust 31, 2021 on Guiding a number of provisions on
determination and management of construction investment costs issued by The Ministry of
Construction.
o Circular 12/2021/TT-BXD dated Ausgust 31, 2021 on Construction norms issued by The
Ministry of Construction.
o Circular 13/2021/TT-BXD dated Ausgust 31, 2021 on Guiding methods of determination of
techno-economic norms and takeoff of quantities of works issued by The Ministry of
Construction.
o Decree 10/2021/ND-CP dated February 2, 2021 on The Management of construction
investment costs issued by The Gorvernment.
o Decision 1801/QĐ-UBND dated October 04, 2021 about the Announcement of construction
labor price in Cao Bang issued by UBND Cao Bang.
DANG PHAM VIET ANH – 1500665 – 65KTE
8
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
o Decision 1899/QĐ-UBND dated October 14, 2021 about the Announcement of the
construction machines and equipment price in Cao Bang issued by UBND Cao Bang.
o Decision 44/2021/QĐ-UBND dated December 8, 2021 about the Announcement of
construction materials price in Cao Bang issued by UBND Cao Bang.
2. Determine the bid package price
3. Determine the costs of materials, labors, construction equipments
DANG PHAM VIET ANH – 1500665 – 65KTE
9
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Table 2.2.1. Costs of materials, labors, construction equipments
No.
Work
code
HM
*
1
AB.21132
2
AB.11312
3
AB.65120
4
AB.41412
5
AB.42112
6
AB.42212
T*
*
7
AF.11111
8
AF.81111
Working list
FOUNDATION
EARTHWORKS
Excavation and leveling by excavator 1,25 m3,
soil grade II
22,818 = 22,818
Soil excavation for strip footing manually, width
≤ 3m, depth ≤ 1m, soil grade II
249,97 = 249,97
Soil embankment by hand compactor 70kg, soil
compaction factor K=0,90
19,863 = 19,863
Soil transportation by 5-ton dump truck in radius
<= 1000m, soil grade II
5,453 = 5,453
Soil transportation by 5-ton dump truck for the
next 4km in radius ≤5km, soil grade II
5,453
Soil transportation by 5-ton dump truck outside
the radius >5km, soil grade II (next 10km)
5,453
Total: EARTHWORKS
FOUNDATION
Mixing concrete by mixers poured manually,
leveling concrete, width ≤250 cm, stone 4x6,
grade 100
231,866 = 231,866
Wooden formwork. Strip footing formwork
4,419 = 4,419
Unit
Quantity
Unit price (đ)
Material
Labor
Total (đ)
Machine
Material
Labor
Machine
0
1.830.392
17.537.709
0
32.240.381
0
1.297.641
0
19.338.994
25.775.043
100m3
22,8180
80.217
768.591
m3
249,970
128.977
100m3
19,8630
973.619
100m3
5,4530
1.817.917
0
0
9.913.101
100m3
5,4530
3.282.920
0
0
17.901.763
100m3
5,4530
6.976.200
0
0
38.041.219
0
m3
100m2
231,8660
513.043
200.786
4,4190
3.650.140
2.792.772
DANG PHAM VIET ANH – 1500665 – 65KTE
47.998
10
53.409.766
109.168.835
118.957.228
46.555.447
11.129.104
16.129.969
12.341.259
0
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
9
AF.31114
10
AF.32314
11
AF.81111
12
AF.81141
13
AF.61110
14
AF.61110
15
AF.61120
16
AF.61130
Ready-mixed concrete, poured by concrete
pump, concrete foundation, foundation width
≤250 cm, stone 1x2, grade 250
831,739 = 831,739
Ready-mixed concrete, poured by concrete
pump, concrete foundation wall, stone 1x2,
grade 250
52,243 = 52,243
Wooden formwork. Strip footing formwork
15,977 = 15,977
Wooden formwork. Wall bracing formwork
5,186 = 5,186
Fabrication and installation of reinforcing steel.
Reinforced foundation, diameter < 10mm (steel
grade CB240T)
10,065 = 10,065
Fabrication and installation of reinforcing steel.
Reinforced foundation, diameter =10mm (steel
grade CB400V)
16,965 = 16,965
Fabrication and installation of reinforcing steel.
Reinforced foundation, diameter ≤18mm (steel
grade CB400V)
3,535 = 3,535
Fabrication and installation of reinforcing steel.
Reinforced foundation, diameter >18mm (steel
grade CB400V)
32,471 = 32,471
m3
831,7390
752.513
103.208
93.993
625.894.410
85.842.119
78.177.644
m3
52,2430
752.513
340.632
116.054
39.313.537
17.795.638
6.063.009
100m2
15,9770
3.650.140
2.792.772
58.318.287
44.620.118
0
100m2
5,1860
5.216.024
5.643.000
27.050.300
29.264.598
0
ton
10,0650
18.223.453
2.205.900
97.810
183.419.054
22.202.384
984.458
ton
16,9650
18.223.453
2.205.900
97.810
309.160.880
37.423.094
1.659.347
ton
3,5350
18.292.820
1.573.884
490.477
64.665.119
5.563.680
1.733.836
ton
32,4710
18.225.623
1.147.068
506.563
591.804.204
37.246.445
16.448.607
T*
Total: FOUNDATION
2.034.712.989
338.854.781
116.196.005
THM
TOTAL
2.034.712.989
392.264.547
225.364.840
DANG PHAM VIET ANH – 1500665 – 65KTE
11
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
4. Resources analysis and determine the differences of materials, labors, construction
equipment costs
a. Determine the requirement of materials, labors and construction equipment
According to the detailed of volume of construction works and Construction estimating norms
Circular 12/TT-BXD issued by Ministry of Construction, the volume of main materials and
reclaimed materials consumed, labor consumed and construction equipment demand are
determined following these formulas:
𝑉𝐿 =
𝑄
x Đ𝑀
𝑁𝐶 =
𝑄
x Đ𝑀
𝑀 =
𝑄
x Đ𝑀
In which:
o 𝑉𝐿 : number of main materials and reclaimed materials type j to complete the entire
volume of construction work of the bid package.
o 𝑁𝐶 : labor consuming of worker level j (man-day) to complete the entire volume of
construction works of the bid package.
o 𝑀 : Equipment consuming of construction consuming type j to complete the entire volume
of construction works of the bid package.
o 𝑄 : The volume of construction work i.
o Đ𝑀 : Estimating norms for main materials and reclaimed materials, labor and
construction equipment type j to complete one unit of construction work i.
o 𝑛: Quantity of type of construction works of the bid package, according to the bidding
documents.
Table 2.2.2: Summary of materials, labor and machine consumption in direct cost.
No.
Name Supplies
I
MATERIALS
Unit
Quantity
1
Golden sand
m3
132,853
2
Steel wire
kg
722,074
3
4x6 stone
m3
215,322
4
Nail
kg
318,86
5
Stand plywood
m3
14,325
6
Plywood
m3
2,755
7
Wooden planks
m3
20,312
8
Water
liter
38.501,35
9
Welding rod
kg
188,499
10
CB240T Steel D<10mm
kg
10.115,325
11
CB400V Steel D<=18mm
kg
3.605,70
12
CB400V Steel D=10mm
kg
17.049,83
DANG PHAM VIET ANH – 1500665 – 65KTE
12
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
13
CB400V Steel D>18mm
kg
33.120,42
14
PC30 cement mortar, coarse sand, 1x2
M250 stone - Slump 14 - 17cm
m3
897,242
15
PCB30 cement
kg
45.868,89
16
Other materials
%
II
LABORS
1
Level 3,0/7 employees – Group 1
Workday
339,5646
2
Level 3,0/7 employees – Group 2
Workday
705,5531
3
Level 3,5/7 employees – Group 2
Workday
1.006,1268
III
7
MACHINE
Concrete pump – Capacity: 40 - 60
m3/h
Bending machine for rebar – Capacity:
5,0 kW
Single bucket, crawler excavator –
Bucket capacity: 1,25 m3
Needle vibrator for concrete - Capacity:
1,5 kW
Vibratory plate compactor for concrete Capacity: 1,0 kW
Handheld soil compactor – Weight:
70kg
AC welding machine – Capacity: 23kW
8
1
Shift
29,1714
Shift
17,1386
Shift
4,9743
Shift
83,4285
Shift
20,6361
Shift
76,3732
Shift
45,1974
Concrete mixer – Capacity: 250,0 liters
Shift
22,0273
9
Bulldozer – Capacity: 110 CV
Shift
0,6617
10
Dump truck – Capacity: 5,0 T
Shift
48,1445
11
Other machines
2
3
4
5
6
%
b. Determine the difference of main materials and reclaimed materials
CL =
VL x (ĐG
− ĐG )
In which:
o CL: total difference of material
o VL : quantity of material
o ĐG : cost of materials at the time of construction
o ĐG : cost of material in circular
DANG PHAM VIET ANH – 1500665 – 65KTE
13
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Table 2.2.3: Differences in total amount of materials
1
Coarse sand
m3
132,8534
270.000
Current price
(đ)
300.000
30.000
Total
difference (đ)
3.985.603
2
Steel wire
kg
722,0743
21.250
21.250
0
0
3
4x6 stone
m3
215,3224
140.000
190000
50.000
10.766.118
4
Nail
kg
318,8599
22.000
22000
0
0
5
Stand plywood
m3
14,3248
2.500.000
2.500.000
0
0
6
Plywood
m3
2,7546
2.500.000
2.500.000
0
0
7
Wooden planks
m3
20,3121
2.500.000
2.500.000
0
0
8
Water
liter
38.501,3493
5
5
0
0
9
Welding rod
kg
188,4987
21.500
21.500
0
0
10
CB240T Steel D<10mm
kg
10.115,3250
17.793
16.500
-1.293
-13.079.115
11
12
13
CB400V Steel D<=18mm
CB400V Steel D=10mm
CB400V Steel D>18mm
PC30 cement mortar, coarse sand, 1x2
M250 stone - Slump 14 - 17cm
kg
kg
kg
3.605,70
17.049,8250
33.120,420
17.643
17.793
17.593
16.500
16.500
16.500
-1.143
-1.293
-1.093
-4.121.315
-22.045.424
-36.200.619
m3
897,2417
734.052
734.052
0
0
45.868,8915
1.150
1.500
350
16.054.112
No.
14
Material
Unit
15
PCB30 cement
kg
16
Other materials
%
Quantity
Norm price (đ)
Difference (đ)
-182.318
TOTAL
-44.822.958
Total material cost: A = VL + CLVL = 2.034.712.989 – 44.822.958 = 1.989.890.030 (dong)
DANG PHAM VIET ANH – 1500665 – 65KTE
14
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
c. Determine the difference of labor consuming.
Using the direct compensation method
CLNC =
𝑆𝐿𝑁𝐶 𝑥 (Đ𝐺
− Đ𝐺 )
In which:
o CLNC: total difference of labor
o SLNC
: Number of working days of worker level j according to each sector.
o j: Average level of worker of a sector.
o ĐG : cost of labor in circular
o ĐG : cost of labor in reality
Table 2.2.4: Summary of employees and price difference of labor
No.
Level of work
II
LABOR
Unit
Quantity
Norm
price (đ)
Current
price (đ)
Difference
Total
difference
1
Level 3,0/7 – Group 1
man-day
339,5646
157.289
157.289
0
0
2
Level 3,0/7 – Group 2
man-day
705,5531
187.650
187.696
46
32.455
3
Level 3,5/7 – Group 2
man-day
1.006,1268
205.200
205.250
50
50.306
TOTAL
82.762
Total labor cost: NC = B + CLNC = 392.264.547 + 82.762 = 392.347.309 (dong)
d. Determine the difference of construction equipment costs
Using the direct compensation method:
CLM =
𝑆𝐿𝑀 𝑥 (Đ𝐺𝑀
− Đ𝐺𝑀 )
Table 2.2.5: Unit price of fuel (Unit: Vietnam dong)
No.
Fuel
Unit
Price
1
Diezel
Liter
22.591
2
Mazut
Liter
0
3
Electricity
kWh
1.685
4
A92 Gasoline
Liter
22.791
DANG PHAM VIET ANH – 1500665 – 65KTE
15
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Table 2.2.6: Unit price of construction equipment
Quota
Type of machine and
equipment
Number
of shifts
per year
Historical
cost
Recovery
coefficient
Deprecupon
liquidation iation
Cost
Repair
Other
cost
Depreciation
Repair
Other
cost
Fuel and energy
Secondary
consumption
fuel
norms of 1 shift
factor
Fuel costs
Compesition
rank of
machine
operate
Machine
operator
salary
Machine
shift price
Concrete pump –
Capacity: 40 – 60 m3/h
220
1.245.106.000
0,9
0,13
0,065
0,050
662.170
367.872
282.979
182
kWh
1,05
322.003,5
1x3/7 + 1x5/7
– Group 4
503.443
2.172.758
Bending machine for rebar –
Capacity: 5,0 kW
240
18.200.000
1,0
0,14
0,041
0,040
10.617
3.109,2
3.033
9
kWh
1,05
15.923,3
1 x 3/7 –
Group 4
210.146
244.524
Single bucket, crawler
excavator –
Bucket capacity: 1,25 m3
280
1.863.636.000
0,9
0,17
0,058
0,050
1.018.344
386.038,89
332.792
22.591
Liter
Diezel
1,03
1.931.304,6
1 x 4/7 –
Group 4
249.454
3.300.867
Needle vibrator for concrete
– Capacity: 1,5 kW
150
7.395.000
1,0
0,20
0,088
0,040
9.860
4.338,40
1.972
7
kWh
1,05
12.384,8
1 x 3/7 –
Group 4
210.146
240.020
Vibratory plate compactor
for concrete –
Capacity: 1,0 kW
150
6.420.000
1,0
0,25
0,088
0,040
10.700
3.766,40
1.712
1.686
kWh
1,05
8.846,3
1 x 3/7 –
Group 4
210.146
236.112
Handheld soil compactor –
Weight: 70kg
200
35.771.000
0,9
0,20
0,054
0,040
32.194
9.658,17
7.154
22.791
Liter
A92
gasoline
1,02
92.987,3
1 x 3/7 –
Group 4
210.146
337.488
AC welding machine –
Capacity: 23kW
200
16.000.000
1,0
0,21
0,048
0,050
16.800
3.840,00
4.000
1.685
kWh
1,05
84.924,0
1 x 4/7 –
Group 4
249.454
368.062
Concrete mixer –
Capacity: 250,0 liters
165
30.210.000
0,9
0,19
0,065
0,050
31.309
11.900,91
9.155
1.685
kWh
1,05
19.461,8
1 x 3/7 –
Group 4
210.146
284.045
Bulldozer –
Capacity: 110 CV
280
851.855.000
0,9
0,14
0,058
0,050
383.335
176.455,68
152.117
22.591
Liter
Diezel
1,03
1.070.361,6
1 x 4/7 –
Group 4
249.454
1.689.735
Dump truck –
Capacity: 5,0 T
260
437.559.000
0,9
0,17
0,075
0,060
257.487
126.218,94
100.975
41
Liter
Diezel
1,03
954.017,9
1 x 2/4
truck operator
234.000
1.367.883
DANG PHAM VIET ANH – 1500665 – 65KTE
16
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Table 2.2.7: Price difference of construction equipment
No.
1
2
3
Machine
Unit
Concrete pump –
Capacity: 40 – 60 m3/h
Bending machine for rebar –
Capacity: 5,0 kW
Single bucket, crawler excavator –
Bucket capacity: 1,25 m3
Quantity
Shift
29,171
Shift
17,139
Shift
4,974
Norm
price (đ)
2.172.758
Current
notice (đ)
2.138.467
244.524
Difference
Total difference
-34.291
-1.000.316
242.828
-1.696
-29.067
3.300.867
3.917.934
617.067
3.069.491
240.020
238.701
-1.319
-110.042
236.112
235.171
-941
-19.418
4
Needle vibrator for concrete – Capacity: 1,5 kW
Shift
83,429
5
Vibratory plate compactor for concrete –
Capacity: 1,0 kW
Shift
20,636
6
Handheld soil compactor – Weight: 70kg
Shift
76,373
337.488
352.140
14.652
1.119.020
7
AC welding machine – Capacity: 23kW
Shift
45,197
368.062
359.018
-9.044
-408.765
8
Concrete mixer – Capacity: 250,0 liters
Shift
22,027
284.045
281.972
-2.073
-45.662
9
Bulldozer – Capacity: 100,0 CV
Shift
0,662
1.689.735
2.031.723
341.988
226.301
10
Dump truck – Capacity: 5,0 T
Shift
48,145
1.367.883
1.672.699
304.816
14.675.366
11
Other machines
%
-11.104
TOTAL
17.465.662
Total construction machine cost: M = C + CLNC = 225.364.840 + 17.465.662 = 242.830.502 (dong)
DANG PHAM VIET ANH – 1500665 – 65KTE
17
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
5. Bid package price
The bid package estimate is
a. Direct cost (T)
T = VL + NC + M
= 1.989.890.030 + 392.347.309 + 242.830.502
= 2.625.067.841 (VND)
b. Indirect cost (GT)
GT = C + LT + TT
In which:
o C: General cost.
o LT: Cost for temporary housing and construction management.
o TT: The cost for some work cannot be determined form the design.
General cost (C)
C = ĐMTL (%) x T
ĐMTL = 7,3% according to Appendix 3 - Circular 11/2021/TT-BXD.
C = 7.3% x 2.625.067.841 = 191.629.952 (VND)
Cost for temporary housing and construction management (LT)
LT = ĐMTL (%) x T
ĐMTL = 1,1% according to Appendix 3 - Circular 11/2021/TT-BXD.
LT = 1,1% x 2.625.067.841 = 28.875.746 (VND)
Cost for some work cannot be determined form the design (TT)
TT = ĐMTL (%) x T
ĐMTL = 2,5% according to Appendix 3 - Circular 11/2021/TT-BXD.
TT = 2,5% x 2.625.067.841 = 65.626.696 (VND)
Total indirect cost:
GT = C + LT + TT
= 191.629.952 + 28.875.746 + 65.626.696
= 286.132.394 (VND)
c. Pre-determined taxable income (TL)
TL = ĐMTL x (TT + GT)
ĐMTL: Norms (%) is determined according to Appendix 3, table 3.5 of Circular 11/2021/TT-BXD
dated August 31, 2021, issued by The Ministry of Construction, DMTL = 5,5%
TL = 5,5% x (2.625.067.841 + 286.132.394) = 160.116.013 (VND)
d. Construction cost before taxes (G)
G = T + GT + TL
= 2.625.067.841 + 286.132.394 + 160.116.013
= 3.071.316.248 (VND)
e. Value added tax (GTGT)
GTGT = 10% x G = 10% x 3.071.316.248
= 307.131.625 (VND)
f. Construction cost after taxes (𝐺 )
G = G + GTGT = 3.071.316.248 + 307.131.625
= 3.378.447.873 (VND)
g. Contigency cost (𝐺 )
G
=G
+G
G : is the type of cost used in case of arising volume of construction package estimate, which is
determined by the following formula:
G
=G xK
K : Contingency factor for arising volumes of works (K ≤ 5%)
DANG PHAM VIET ANH – 1500665 – 65KTE
18
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Choose K
= 5%
G
= 3.378.447.873 x 5%
= 168.922.394 (dong)
G : The contingency cost for the price inflation factor in the construction package estimate, which is
determined by the following formula:
G
=
G x [(I
± ΔI
)t – 1]
In which:
o T: Length of time of implementation of construction investment project: T > 1 year (330 days
~ 1 year = 4 quarters)
o t: Ordinal number of capital allocation year under the project implementation plan: t =1
o GXD : Estimated construction cost before contingency;
o IXDCTbq: Construction price index;
o ±∆IXDCT: The average fluctuation of construction price index by year of works construction.
The construction price index is shown in the table below:
Table 2.2.8: Construction price index – Continuous construction price index
No.
Year
2
2020
3
2021
4
2022
Average construction price index
Continuous construction cost index
111,01%
104,92%
111,26%
109,063%
The contingency cost of inflation is determined as below:
GDP2 = (IXDCTbq – 1) x GXD
= (1,09063 – 1) x 3.378.447.873
= 306.188.731 (VND)
Total contingency cost (𝐺 ):
G =G
+G
= 168.922.394 + 306.188.731
= 475.111.125 (VND)
h. Other cost (𝐺 )
Other costs are determined by making estimates of taking a percentage of direct cost in order to
suit the specific conditions of each bid package.
Within the scope of the project, according to the contractor’s experience with the similar bid
package, choose other cost equal to 2% of the direct cost.
G = 2% x G
= 2% x 3.378.447.873
= 67.568.957 (dong)
DANG PHAM VIET ANH – 1500665 – 65KTE
19
PROJECT CONSTRUCTION ECONOMICS AND PROCUREMENT OPERATION – PH.D NGUYEN TUAN ANH
Table 2.2.8: Summary of the bid package price
No.
Content
Symbol
Calculation
Value
T
VL + NC + M
2.625.067.841
I
DIRECT COST
1
Material
VL
A
1.989.890.030
2
Labor
NC
B1
392.347.309
3
Construction machine
M
C1
242.830.502
II
INDIRECT COST
GT
C + LT + TT
286.132.394
1
General cost
C
T x 7,3%
191.629.952
2
Cost for temporary housing and
construction management.
LT
T x 1,1%
28.875.746
3
The cost for some work cannot be
determined form the design
TT
T x 2,5%
65.626.696
PRE-CALCULATED TAX INCOME
TL
(T+GT) x 5,5%
160.116.013
G
(T+GT+TL)
GTGT
G x 10%
III
Construction cost (VAT excluded)
IV
VALUE ADDED TAX
Construction cost (VAT included)
G
V
CONTINGENCY COST
𝐆𝐃𝐏
1
Contingency cost for rising volume of
works
G
2
Contingency cost for price inflation
G
VI
OTHER COST
BID PACKAGE PRICE
ROUNDING VAVLUE
𝐆𝐤
G + GTGT
𝐆𝐃𝐏𝟏 + 𝐆𝐃𝐏𝟐
G
x 5%
3.071.316.248
307.131.625
3.378.447.873
475.111.125
168.922.394
306.188.731
𝐆𝐗𝐃 x 2%
𝐆𝐗𝐃 + 𝐆𝐃𝐏 + 𝐆𝐤
67.568.957
3.921.127.955
3.921.127.000
III. Determine the bid price
1. Principles of bid price
The selected technical and technological measures applied to the bidding package must fully satisfy
the requirements of the bidding documents.
The private norm for labor and machine of the enterprise must be consistent with the technical and
technological solutions applied to the bidding package.
The unit price of materials, labor and construction machines within the enterprise must be consistent
with the technical and technological solutions applied to the bidding package.
The volume of construction work must comply with the bidding documents and the design provided
by the investor.
The financial and commercial plans applied to the bidding package must fully satisfy the requirements
of the bidding documents.
Construction site management costs are determined according to technical - technological plan,
construction organization plan, site design plan and site management department.
Enterprise-level general costs allocated to the bidding package are taken according to the average
DANG PHAM VIET ANH – 1500665 – 65KTE
20