Bài tập về Quản trị dự án trong xây dựng
Being responsible for the team working the first phase of the project, specifically “cooperate with local authorities for land clearance, compensation, land preparation
(Backfilling) for construction with the deadline on June 20, 2013’’, my detailed action
plan is as follows:
Part I: Introduction to management of the first task under the project
The main work of the first task under the project is land clearance, compensation and
land preparation. This task can be divided into two main activities as “Land clearance
and compensation” and “Backfilling”.
The tasks are divided into 25 categories that need construction schedules. In which,
“Land clearance and compensation” consists of 19 categories (details in table 1) and
“Backfilling” consists of 6 categories (details in table 2).
Diagram on management of the first task under the project
New Urban Zone Construction Project
MAGACO Corporation
Land clearance and compensation
Planning &
PMU
Item
1
Backfilling
Finance
HR
Administration
Item
Item
Item
Item
Item
2
3 ÷17
18
19
20
1
Site inspection carried out in Tu Liem District where the project will be implemented
states that land is mostly farming land with relatively terrain and no ponds or lakes
over the area of 200 m2. However, 60 farmer households plotted in the area and need
removing.
Part II: Implementation of Land Clearance and Compensation.
A- Work of Land Clearance and Compensation
Work breakdown structure for Content of work for Land Clearance and Compensation
is listed in details as follows:
Table 1
Item
Content of work
1
Legal basis for implementation. (referred in Appendix 1)
2
Release the Council for Compensation – Rehabilitation &
Resettlement (CCR&R)
3
4
+ Prepare, approve detailed progress of land clearance, through
Compensation Council, rehabilitation and resettle, submit to the
District People’s Committee for approval.
+ Prepare, inspect cost estimate for land clearance, decide to
approve the cost estimate.
Release working Team for land clearance, publicly list all legal
documents relating to land clearance, inform through
broadcasting system of the ward.
Implementing
time
Implementing Unit
15-18/01/2013
Administrative
Department & PMU
15/01/2013
CCR&R
16-18/01/2013
19-23/01/2013
5
Measure cadastral map – prepare records of Land dimension of
households.
24-29/01/2013
6
Organize meeting with local people to inform land recovery
decision, deliver declarations of lands, assets on land, population,
records of Land dimension. Collect declarations of lands, assets
on land, population
30-31/01/2013
7
Inspect current situations, make inspection minutes, clarify
declared details of assets, plants, vegetables of households.
01-05/02/2013
8
Publicly list all results of clarification, confirmation
9
Prepare draft of detailed solution for compensation, rehabilitation
and resettlement to households whose land is recovered through
Acceptance Team for draft of detailed solution.
CCR&R, Planning and
Finance Department of
district level, Ward
People’s Committee,
Employer
CCR&R. Working
team, Ward People’s
Committee and bodies
under Ward.
Measurement party
hired by the Employer.
Working team, Ward
People’s Committee
and bodies under
Ward.
Working team, Ward
People’s Committee
and bodies under
Ward.
06/02/2013
Working team,
Employer
07-08/02/2013
Working team,
Employer
2
10
+ Publicly list and collect opinions on draft of detailed solution
for compensation, rehabilitation and resettlement at working
office of Ward People’s Committee.
+ Inspect solutions with complaints (if any).
11
12
13
14
15
16
17
18
19
09-20/02/2013
Working team, Ward
People’s Committee,
Employer
Answer all complaints and queries of people (if any).
21/02/2013
Working team, Ward
People’s Committee,
Employer
Complete, accept compensation solution after they have been
publicly listed.
22/02/2013
CCR&R
23-25/02/2013
CCR&R
26-27/02/2013
CCR&R
28/0201/03/2013
Tu Liem Distrit
People’s Committee
01-05/03/2013
Working team, Ward
People’s Committee
06-10/03/2013
Working team,
Employer
Department of Natural Resources and Environment advices the
District People’s Committee in land recovery decisions to land
users.
Submit to District People’s Committee for decision on detailed
and general solution for compensation, rehabilitation and
resettlement
Make decide on solution for compensation, rehabilitation and
resettlement
Publicly list detailed solution for compensation, rehabilitation
and resettlement approved by the District People’s Committee,
deliver approval decision and solution for compensation,
rehabilitation and resettlement to each household, inform the time
to receive funds of compensation, rehabilitation and resettlement,
time to get resettlement, time to handle area.
+ Build payment plan for compensation, rehabilitation and
resettlement
+ Make payment plan for compensation, rehabilitation and
resettlement.
Handle area (after payment of compensation, rehabilitation and
resettlement or after handling resettlement houses and lands.
Enforce households that do not accept compensation for land
clearance
11-14/03/2013
15/3/2013
CCR&R, Working
team, Ward People’s
Committee, Employer,
People whose land is
withdrawn
Working team, Ward
People’s Committee,
Employer, Police of
Ward
Note:
Council for Compensation – Rehabilitation & Resettlement is reffered as CCR&R.
B- Gantt diagram for land clearance and compensation.
Details in Appendix II as bellows:
3
Appendix II
PROGRESS OF CONSTRUCTION, LAND CLEARANCE AND COMPENSATION
Implementing
No.
1
2
3
4
5
6
7
8
9
10
Item
Collect legal basis
Release the Council for Compensation –
Rehabilitation & Resettlement (CCR&R)
Prepare, approve detailed progress. Prepare, inspect
and approve cost estimate for land clearance
Organize meeting, publicize documents, reports
about land clearance through broadcasting system
Measure cadastral map – prepare records of Land
dimension of households
Organize meeting with local people to inform land
recovery decision, deliver forms and documents for
people to declare. Collect all declarations.
Inspect current situations, make inspection minutes,
clarify declared details of assets, plants, vegetables
of households
Publicly list all results of clarification, confirmation.
Prepare draft of detailed solution for compensation,
rehabilitation and resettlement to households whose
land is recovered through Acceptance Team for draft
of detailed solution
Publicly list and collect opinions on draft of detailed
solution for compensation, rehabilitation and
resettlement at working office of Ward People’s
Committee.Inspect solutions with complaints(if any)
date
January/ 2013
W3
W4
February/ 2013
W1
W2
W3
March /2013
W4
W1
W2
Jan 15 - 18
Jan 15
Jan 16 - 18
Jan 19 - 23
Jan 24 - 29
Jan 30 - 31
Feb 1 - 5
Feb 6
Feb 7 - 8
Feb 9 - 20
4
11
12
13
14
Answer all complaints and queries of people (if
any).
Complete, accept compensation solution after they
have been publicly listed.
Department of Natural Resources and Environment
advices the District People’s Committee in land
recovery decisions to land users.
Submit to District People’s Committee for decision
on detailed and general solution for compensation,
rehabilitation and resettlement.
17
Make decide on solution for compensation,
rehabilitation and resettlement.
Publicly list detailed solution for compensation,
rehabilitation and resettlement approved by the
District People’s Committee, deliver approval
decision
and
solution
for
compensation,
rehabilitation and resettlement to each household,
inform the time to receive funds of compensation,
rehabilitation and resettlement, time to get
resettlement, time to handle area.
Build payment plan for compensation, rehabilitation
and resettlement. Make payment plan for
compensation, rehabilitation and resettlement
18
Handle area (after payment of compensation,
rehabilitation and resettlement or after handling
resettlement houses and lands.
19
Enforce households that do
compensation for land clearance.
15
16
not
accept
Feb 21
Feb 22
Feb 23 - 25
Feb 26 - 27
Feb 28 - Mar
1
Mar 1 - 5
Mar 6 - 10
Mar 11 - 14
Mar 15, 2013
Remarks:
Lunar newyear festival (Incl. Lunar carlendar date: Dec 29, Jan 1, 2, 3. Equally with solar carlendar date from Feb 9 to Feb 12, 1023).
When we made schedule we have calculated to this period of time and it will have no negative effect to our project’s progress (item 10).
5
Part III: Backfilling.
1) Diagram of work implementation:
Investment owner
Bidder representative
Site steering
committee
Dept of industrial
safety
Work
executive
team
Geodesic
team
Dept of Planning
Materials- Equipment
Water &
Electric
executive
team
Dept of Technical –
Progress of project
Plastering
team
Site cleaning
team
6
2)
Analyse of work item:
The main work is backfilling. Implementation durations is from March 16 to March 20,
2013. Work breakdown structure for Content of work for backfilling is listed in details as
follows:
Table 2
Item
1
(20)
2
(21)
3
(22)
4
(23)
5
(24)
6
(25)
Contents of work
Implementing
days
Person in
charge
Number
of days
Prepare offices, tents
16-21/3/2013
05
Collect machineries, equipment
16-21/3/2013
05
Remove organic soil, transport
and dispose
20/3 – 16/4/2013
26
Dig land
12/4 – 12/5/2013
30
Fill black sand, roll and compact
2/5 – 18/6/2013
47
Complete other works, clean
12/5 – 20/6/2013
9
Total: 98 days
16/3 – 20/6/2013
Head of Planning
– Materials –
Equipment
Department
Head of Planning
– Materials –
Equipment
Department
Heads of Labour
Safety and Project
Technical –
Progress
Departments
Heads of Labour
Safety and Project
Technical –
Progress
Departments
Heads of Labour
Safety and Project
Technical –
Progress
Departments
Heads of Labour
Safety, Project
Technical –
Progress and
Planning –
Materials –
Equipment
Departments
3) GANTT diagram for Backfilling
Based on the above mentioned planning, we have got GANTT diagram
project’s progress) as bellowing Appendix III:
(Table of
7
Appendix III
TABLE OF PROJECT’S PROGRESS
ITEM: BACKFILLING
NEW URBAN ZONE PROJECT
TT
1
2
3
4
5
6
Item
Prepare offices, tents
Collect
machineries,
equipment
Remove organic soil,
transport and dispose
Dig land
Fill black sand, roll and
compact
Complete other works,
clean.
Implementing
date
No
of
date
16/3 – 21/3
5
16/3 – 21/3
5
20/3 – 16/4
26
12/4 – 12/5
30
2/5 – 18/6
47
12/6 – 20/6
9
March
2013
W3
W4
April 2013
W1
W2
W3
May 2013
W4
W1
W2
W3
June 2013
W4
W1
W2
W3
W4
8
Part IV: Estimate cost for implementation
PROJECT COST ESTIMATE
Project : New Urban Zone
Item: Land clearance, compensation and backfilling
Unit: VND
No
Content
Formula
Value before
tax
VAT
Value after tax
Marks
(1)
(2)
(3)
(4)
(5)
(6)
(7)
1
2
3
3.1
3.2
Cost for preparing
investment project and
land clearance solution
Cost for compensation
of land clearance
Cost for implementing
project
Backfilling
Water drainage
2,05%*500
Billion
10,250,000,00
0
1,025,000,00
0
11,275,000,000
60*2 Billion
120,000,000,00
0
12,000,000,00
0
132,000,000,000
G1+G2+G3
281,558,139,545
28,155,813,955
G1
254,155,454,545
37,500,000,000
279,571,000,000
G2
23,418,500,000
2,341,850,000
25,760,350,000
G3
3,984,185,00
0
398,418,500
4,382,603,500
5,969,032,558
596,903,256
6,565,935,814
GQLDA
12,388,558,140
1,238,855,814
13,627,413,954
GTV
309,713,953,500
Gxd
Cost for building
temporary houses
Cost for project
management
Cost for consultancy and
investment of the project
2.12%*Gxd
5.1
Cost for design
2,04%*Gxd
5,743,786,046
574,378,605
6,318,164,651
5.2
Cost for inspecting
working drawings
0,158%*Gxd
444,861,860
44,486,186
489,348,046
5.3
Cost for inspecting
estimate
0,153%*Gxd
430,783,954
43,078,395
473,862,349
5.4
Cost for supervising the
project
2,053%*Gxd
5,780,388,605
578,038,860
6,358,427,465
6
Other costs
2,871,893,023
287,189,302
3,159,082,326
6.1
Cost for inspecting and
approving acount
0,38%*Gxd
1,069,920,930
106,992,093
1,176,913,023
6.2
Cost for auditing
0,64%*Gxd
1,801,972,093
180,197,209
1,982,169,320
7
Provision cost
21,508,286,512
2,150,828,651
23,659,115,163
7.1
Provision cost for
additional works
(1+2+3+4+5)*5%
21,645,039,225
2,164,503,922
23,659,115,163
GDP1
Total
(1+2+3+4+5+6+7)
500,000,500,757
T
3.3
4
5
Round
GK
500,000,500,000
Remarks:
+ Fund for project (compensation, land clearance and backfilling) is calculated as 10% of total
fund for the whole project.
+ Estimated compensation to each household is 2 billion Vietnamese dong.
9
Appendix I:
Legal basis for implementation of the project.
(Details of Item 1)
1. 2003 Land Law
2. Decree No. 197/2004/NĐ-CP dated 03/12/2004 of the Government on
compensation, rehabilitation and resettlement in the event of land recovery by
State
3. Decree No. 84/2007/NĐ-Cp dated 25/5/2007 of the Government with
additional provisions on issuance of land use right certificates; on land
recovery; on exercise of land use right; on order and procedures for
compensation, assistance and resettlement when the State recovers land; and
on resolution of complaints about land.
4. Decisions of Hanoi People’s Committee allowing MAGACO to implement the
project of new urban zone in Tu Liem District, Hanoi City.
5. Decision No. 62/2008/QĐ-UBND dated 31/12/2008 of Hanoi People’s
Committee issuing Regulations on prices of land types in Hanoi City in 2009.
6. Notice No. 14/TB-STC-QLCS dated 21/01/2009 of Hanoi Department of
Finance on announcing unit price as the basis for compensation, assistance to
vegetables, animals on lands of land clearance in Hanoi City.
7. Decision No. 40/2008/QĐ-UBND dated 22/10/2008 of Hanoi People’s
Committee issuing prices of building new houses, temporary houses, structures
in Hanoi city.
8. Maps of Hanoi City, Tu Liem District, map of project border.
9. Approved detailed map of the project.
10. Approval documents relating to the project.
10