PROFESSIONAL RESPONSIBILITY
1. Answer: c
There should be a change procedure in the project to handle changes that might
be initiated by customers. The change procedure should include the cost for
managing the change and the cost of developing the estimate for the effects of
the change.
2. Answer: c
Estimating is just that, an estimating process. Perhaps it would have been better
for the project manager to have given all the information to the person responsi-
ble for the estimate. At this point the best thing to do is to use all of the
information available to create the most accurate estimate that is practical.
3. Answer: b
In this kind of situation it is important that the customs and culture in the
foreign country be respected. By consulting with your company’s management,
the gift can usually be accepted and disposed of in the proper way.
4. Answer: c
Unless the employee has signed a nondisclosure agreement with his or her pre-
vious company, there is no obligation for him or her not to share knowledge
that was gained while working for the competitor.
5. Answer: a
The first thing that should be done is to look for tasks in the project where
there is an ability to reschedule to free resources for this problem. If the problem
is severe and additional budget and time is needed, it may be necessary to speak
to the stakeholders, but the project impacts and plan for the correction should
come first.
6. Answer: c
It is usually in the best interest of the project if the project team decides matters
of personal time themselves unless there are significant reasons for the project