HA NOI CITY RING ROAD NO.3 CONSTRUCTION PROJECT
Package 03: THANH XUAN - NORTH LINH DAM LAKE SECTION
***
construction method DRAWING
Item:
girder erection of spans P154-P155 and P155-P156 (From casting yard no.1)
submitted 1.st
ELEVATION
A
Crane 100T
Crane 100T
P155
A
PLAN VIEW
P156
P155
12000
P154
P155
P156
P154
P155
- Transported girder to installation girder span follow that had been approved.
10000
10000
- Girders are installation with two cranes 100T. Before loading girders to span, it is
necessary to try girders loading test about 20cm from girder truck and then stop to check
brake and winch system of the crane. Girders loading would only be continued after
ensuring the safety.
1
Access road 50cm sand compacted
2
4
Crane 100T
Crane 100T
- Those who have done absolutely obey the orders of the commander, the commander
must have a whistle, orders flags to be clear.
c
n
c
nh
nh nh c a n
c huy, n
c huy
,c
nh nh
cr
- In this drawing showing arrangement method for girder launching at span P155-P156.
With span P154-P155 the work progresses similar.
5
22400
22400
Median range between
28000
3
6
7
8
R7.9m
9
.9m
R7
10
- Dimensions are mm, levels are m.
40000
12000
- Control traffic see other drawing
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
typical section
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
SECTION A - A
CL
8000
sidewalk
2%
12000
nmv lane
6%
Detail 1
frontage road - 2 lanes
Point mark cone /
Fence
6%
2%
2%
28000
R.o.w limit b=68.0m
Super T girder
3000
6000
2300
3600
31000
3600
2300
6000
3000
DETAIL 1
200 200
Wooden sleeper 1000x200x200
Steel plate 1500x6000x20 mm
20
38000
7700
- Dimensions are mm, levels are m.
- Location of the crane must be supported strongly.
15800
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
drawing TITLE
scale
PROJECT MANAGEMENT UNIT THANG LONG
as shown
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
typical cross-section
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
P155
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P156
P155
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to
pier head, move two crane inside. During this time, the truck run to the
yard girder to get girder.(45 minutes)
P156
Move crane
Move crane
Crane 100T
Crane 100T
This position to get down girder to change Crane
Crane 100T
Crane 100T
R7.9m
R7.9m
1
R7.9m
R7.9m
1
P155
STEP 3:
- Left crane rotate girders into place, move crane inside.
right crane hang girder . (45 minutes)
P156
P155
Move crane
STEP 4:
- Two crane rotate girders into place. Move left crane
inside. (45 minutes)
Move crane
Crane 100T
P156
Crane 100T
Crane 100T
Next position of girder
R7.9m
Next position of girder
R7.9m
Crane 100T
R7.9m
1
R7.9m
1
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
drawing no.
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(1/14)
02
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 6:
- To get the girder down to position (5 minutes)
STEP 5:
- Two crane rotate girders into place. (10 minutes)
P155
P156
P155
P156
Crane 100T
R7.9m
Crane 100T
1
R7.9m
Crane 100T
Crane 100T
R7.9m
R7.9m
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 160 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(2/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to pier head, move two
crane inside. During this time, the truck run to the yard girder to get girder.(45 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
P156
Move crane
Move crane
Crane 100T
Crane 100T
This position to get down girder to change Crane
Crane 100T
Crane 100T
R7.9m
R7.9m
2
R7.9m
R7.9m
2
STEP 3:
- Left crane rotate girders into place, move crane inside. right crane
hang girder . (45 minutes)
P155
STEP 4:
- Two crane rotate girders into place. (10 minutes)
P156
P155
P156
Move crane
Crane 100T
Crane 100T
Crane 100T
Next position of girder
R7.9m
R7.9m
Next position of girder
Crane 100T
R7.9m
2
R7.9m
2
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(3/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 5:
- To get the girder down to position (5 minutes)
P155
P156
Crane 100T
R7.9m
R7.9m
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 115 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(4/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to pier head, move two
crane inside. During this time, the truck run to the yard girder to get girder.(45 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
P156
Move crane
Move crane
Crane 100T
Crane 100T
This position to get down girder to change Crane
Crane 100T
Crane 100T
R7.9m
R7.9m
3
R7.9m
R7.9m
3
STEP 3:
- Left crane rotate girders into place, move crane inside. right crane
hang girder . (45 minutes)
P155
STEP 4:
- Two crane rotate girders into place. (10 minutes)
P156
P155
P156
Move crane
Crane 100T
Crane 100T
Crane 100T
R7.9m
Next position of girder
R7.9m
R7.9m
Crane 100T
3
R7.9m
3
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(5/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 5:
- To get the girder down to position (5 minutes)
P155
P156
Crane 100T
R7.9m
R7.9m
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 115 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(6/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to pier head, move two
crane inside. During this time, the truck run to the yard girder to get girder.(45 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
P156
Move crane
Move crane
Crane 100T
Crane 100T
This position to get down girder to change Crane
Crane 100T
Crane 100T
R7.9m
R7.9m
4
R7.9m
R7.9m
4
STEP 3:
- Left crane rotate girders into place, move crane inside. right crane
hang girder . (45 minutes)
P155
STEP 4:
- Two crane rotate girders into place. (10 minutes)
P156
P155
P156
Move crane
Crane 100T
Crane 100T
Crane 100T
R7.9m
Next position of girder
R7.9m
R7.9m
Crane 100T
4
R7.9m
4
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(7/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 5:
- To get the girder down to position (5 minutes)
P155
P156
R7.9m
R7.9m
Crane 100T
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 115 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(8/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to pier head, move two
crane inside. During this time, the truck run to the yard girder to get girder.(45 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
P156
Move crane
Move crane
Crane 100T
Crane 100T
Crane 100T
This position to get down girder to change Crane
R7.9m
R7.9m
Crane 100T
5
R7.9m
R7.9m
5
STEP 3:
- Left crane rotate girders into place, move crane inside. right crane
hang girder . (45 minutes)
P155
STEP 4:
- Right crane rotate girders into place. left crane hang girder . (10 minutes)
P156
P155
P156
Move crane
Crane 100T
Crane 100T
Crane 100T
R7.9m
R7.9m
R7.9m
5
R7.9m
5
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
Crane 100T
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(9/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 5:
- To get the girder down to position (5 minutes)
P155
P156
Crane 100T
R7.9m
R7.9m
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 115 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(10/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside, get the girder down to pier head, move two
crane inside. During this time, the truck run to the yard girder to get girder.(45 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
P156
Move crane
Move crane
Crane 100T
Crane 100T
This position to get down girder to change Crane
Crane 100T
R7.9m
R7.9m
Crane 100T
6
R7.9m
R7.9m
6
STEP 3:
- Left crane rotate girders into place, move crane inside. right crane
hang girder . (45 minutes)
P155
STEP 4:
- To get the girder down to position (5 minutes)
P156
P155
Move crane
P156
Move crane
Crane 100T
Crane 100T
R7.9m
R7.9m
6
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 105 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(11/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside. During this time, the truck run to the yard
girder to get girder.(15 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
Crane 100T
P156
Crane 100T
Crane 100T
R7.9m
R7.9m
7
R7.9m
R7.9m
Crane 100T
7
STEP 3:
- To get the girder down to position (5 minutes)
P155
P156
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 30 minutes
R7.9m
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(12/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 2:
- Take rotating crane to move the girder inside. During this time, the truck run to the yard
girder to get girder.(15 minutes)
STEP 1:
- Lift up the girder to pier head and combination to rotate the crane to
move the girder inside. (10minutes)
P155
P156
P155
Crane 100T
P156
Crane 100T
Crane 100T
R7.9m
R7.9m
R7.9m
8
R7.9m
Crane 100T
8
STEP 3:
- To get the girder down to position (5 minutes)
P155
P156
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder is 30 minutes
R7.9m
R7.9m
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(13/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
STEP 1:
- Lift up the girder to pier head. (10minutes)
P155
STEP 2:
- To get the girder down to position (10 minutes)
P156
P155
1
1
2
2
4
4
5
Crane 100T
P156
5
Crane 100T
6
6
7
7
R7.9m
9m
R7.
9
Crane 100T
Crane 100T
STEP 1:
- Lift up the girder to pier head. (10minutes)
P155
STEP 2:
- To get the girder down to position (10 minutes)
P156
P155
1
1
2
2
4
4
5
Crane 100T
P156
5
Crane 100T
6
6
7
7
R7.9m
9m
R7.
10
Crane 100T
Crane 100T
- Dimensions are mm, levels are m.
- Total estimated installation time a girder(number 9 or 10) is 20 minutes
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
scale
drawing TITLE
PROJECT MANAGEMENT UNIT THANG LONG
as shown
(14/14)
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
Vehicle lane
/ Ph
Transported girder direction /
28000
Truck carry girder
Point mark cone 3m/unit
6000
Barrie (3 mobile barrie)
Flag man
6000
Vehicle lane
/ Ph
Median range between
Fence
NOTES:
127
134
125
SPEED LIMIT 20Km/h
FINISH SPEED LIMITS 20Km/h
DISALLOW OVERCOME
133
DISALLOW OVERCOME
- Dimension drawing unit mm.
- Only progress installation the girder after 23h p.m
- Comply with road signs charter 22TCN 237-01
- During the girder installation must be arranged worker to
ensure safety for people and vehicles traffic.
- Traffic safe layout for each installation span girder. The signs
are always revolving for each installation span girder
AHEAD
AHEAD
100m
50m
WORKS
WORKS
PROHIBIT ALL EXCEEDED
442b
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
442c
drawing TITLE
scale
PROJECT MANAGEMENT UNIT THANG LONG
traffic safe while erection girder
as shown
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8
BARRIE
2100
The sign
T2
T2
T3
53
0
1200
1450
200
T1
T4
200
T5
150
8x200
150
Solid rubber tyre
MINISTRY OF TRANSPORT
ha noi city ring road no.3 construction project
500
750
drawing TITLE
scale
PROJECT MANAGEMENT UNIT THANG LONG
traffic safe while erection girder
as shown
drawing no.
title
full NAME
DESIGNED BY:
Phan anh tai
CHECKED BY:
dong nhu thai
APPROVED BY:
pham van hung
SIGNATURE
DATE
tlc - cienco 4 - cienco 8