HANOI PEOPLES COMMITTEE
HANOI METROPOLITAN RAILWAY MANAGEMENT BOARD (MRB)
DAELIM INDUSTRIAL CO., LTD

METHOD STATEMENT
PROJECT: HANOI PILOT LIGHT METRO LINE
Section Nhon - Hanoi Railway Station
PACKAGE: LINE-ELEVATED SECTION
PACKAGE NUMBER: HPLMLP/CP-01
METHOD STATEMENT FOR SHORED EXCAVATION
Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City

PROJECT IMPLEMENTATION CONSULTANT: SYSTRA S.A
January, 2015
Project Reference: DLM-IMP-PPG-WVO-J07-00001-E-1A


METHOD STATEMENT
PROJECT: HANOI PILOT LIGHT METRO LINE
Section Nhon - Hanoi Railway Station
PACKAGE: LINE-ELEVATED SECTION
PACKAGE NUMBER: HPLMLP/CP-01
METHOD STATEMENT FOR SHORED EXCAVATION

Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City

Hanoi, 03 January, 2015

HANOI METROPOLITAN
RAILWAY MANAGEMENT
BOARD (MRB)



CONTRACTOR
(DAELIM)

PROJECT
IMPLEMENTATION
CONSULTANT
(SYSTRA S.A.)


Hanoi Pilot Light Metro Project

Method statement for shored excavation

Contractor Approval / Revision Record Sheet

Revision

Date

Subject of issue / Revision

Authors

1A

03/01/2015

First Issue


Nguyen Thai Vu

Revision
N°:

1A

Name

Date

Prepared by

NGUYEN THAI VU

03/01/2015

Checked by

OH SEUNG JONG

03/01/2015

Validated by

SEO YOUNG HWA

03/01/2015

Signature


Contractor specific comments:

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 3/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

CONTENTS
1. INTRODUCTION OF PROJECT..........................................................................................6
1.1 INTRODUCTION

6

2. SCOPE OF WORK..................................................................................................................6
2.1 GENERAL
2.2 SCOPE
2.3 REFERENCE

6
7
7

3. CONSTRUCTION PROCEDURE.........................................................................................8
3.1 QUANTITY OF WORK
3.2 REFERENCE TO BORE HOLE

3.3 SCHEDULE OF WORK

8
17
21

4. PERSONNEL ORGANIZATION........................................................................................22
4.1 PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR
4.2 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE
4.3 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE

22
23
24

5. MATERIALS, EQUIPMENT AND MANPOWER............................................................25
5.1 MATERIALS
5.2 EQUIPMENT
5.3 MANPOWER

25
25
26

6. CONSTRUCTION METHOD..............................................................................................27
6.1 CONSTRUCTION FLOW CHART
27
6.2 DETAIL OF CONSTRUCTION METHOD
28
6.2.1 MOBILIZATION AND PREPARATION WORKS................................................................................28

6.2.2 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES)............................................................28
6.2.3 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES)............................................................29
6.2.3.1 Excavation Stage 1: About install struts and wales..............................................................................29
6.2.3.2 Excavation Stage 2: Excavation by machine until design level and hauling out of excavated material
30
6.2.3.3 Excavation Stage 3: Trimming and leveling work...............................................................................30
6.2.3.4 Construction for temporary drainage system (Dewatering).................................................................30
6.2.3.5 Cleaning up site....................................................................................................................................30

7. QUALITY CONTROL..........................................................................................................31
8. HEALTH, SAFETY AND ENVIRONMENT CONTROL................................................31
8.1 HEALTH AND SAFETY CONTROL
8.2 ENVIRONMENT CONTROL
8.3 HAZARD ANALYSIS

31
32
32

9. TRAFFIC CONTROL...........................................................................................................33
10. APPENDIX...........................................................................................................................33
10.1 APPENDIX 1: METHOD DRAWING
34
10.1.1 SHORED EXCAVATION METHOD DRAWING FOR TYPICAL BRIDGE.....................................34
10.1.2 SHORED EXCAVATION METHOD DRAWING FOR SPECIAL BRIDGE......................................34
10.2 APPENDIX 2: INSPECTION AND TESTING PLAN
35
10.3 APPENDIX 3: TYPICAL SCHEDULE FOR SHORED EXCAVATION OF 01 PILE CAP
36


Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 4/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

Abbreviations
MRB
PIC
DLM

Hanoi Metropolitan Railway Management Board
Project Implementation Consultant (SYSTRA S.A.)
Daelim Industrial Co., Ltd

Project References
Ref N°

Ref ID number

1

DLM-IMP-PPG-WVO-J07-00001-E-1A

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Ref description

Method statement for shored excavation

Page 5/36


Hanoi Pilot Light Metro Project

1.

Method statement for shored excavation

INTRODUCTION OF PROJECT

1.1INTRODUCTION
Hanoi Pilot Light Metro Line, section Nhon - Hanoi Railway Station is a major project fo r Hanoi City.
According to the Hanoi Transportation Master Plan till 2020, total length of HPLML (Line 3) shall reach
21,5km from Nhon to Hoang Mai.The first phase of this line, and part of this Contract is from Nhon to
Hanoi Railway Station, with about 8.5 km elevated section and 4.0 km underground section. This line
includes 12 stations (with 8 elevated and 4 underground stations). The Depot is located at Nhon with area
of 150,550m2.
The CP01 Contract’s work scope is Viaduct Line at Elevated Section, including the construction of
viaduct structures which link along the National Road No32, Ho Tung Mau, Xuan Thuy, Cau Giay and
interfaces with underground section at the beginning of Kim Ma Street. The contract shall be completed
and within 30 months from the date of the Commencement Date.
Both metro and structure alignment follow the current and/or planned median road. Viaduct structures are
divided into standard viaducts which cover most of the elevated section and special viaducts where long or
special spans are required to pass over major constraints (2nd Ring Road, 3rd Ring Road, Nhue River).
Other non-typical structure consists in Cross Over (metro line requires switches), ramps to depot and
underground sections and Y-bridge (branches off to depot). The overview of the project is shown in photo
below:


Overview of project

2.

SCOPE OF WORK

2.1GENERAL
Structure excavation work of Project will be carried out within the narrow area and with the great depth of
excavated hole. Therefore, Shored excavation method will be applied to ensure stability of excavation
hole for structure construction.
Shored Excavation shall be undertaken in accordance with clause “3.4 - Shored excavation, Part II,
Chapter II-2” of Technical Requirement. This method is generally applied to Shored excavation to the
design bottom elevation for all pile caps using shoring system.

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 6/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

This method also includes disposal of unsuitable excavated material, dewatering works and related works
to be free from the accumulation of ground water and artificial runoff water inside excavated area. Shored
Excavation shall be done in accordance with the perimeters and slope as indicated on the approved
working drawing.
2.2SCOPE
The Contractor shall set up and submit method of shored excavation. The Contractor can adjust method

for shored excavation in accordance with the actual condition on the site or at the direction of Consultant
Engineer. All adjustments will be reviewed and approved by the Consultant Engineer, Employer.
After obtaining consent from the Consultant Engineer, Employer, the Contractor will carry out shored
excavation.
Shored excavation part including:
• Shored excavation for pilecap type I (Standard pile cap).
• Shored excavation for pilecap type II (Cantilever pile cap).
• Shored excavation for pilecap type III (Special pile cap).
The Contractor will use method of excavation works of foundation pit by excavator and manpower.
2.3REFERENCE
Reference document:
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Section 3. Earthwork.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.4.Shored excavation
-Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.3.Common excavation.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.5. Preparation and
inspection of foundations.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.8. Grade preparation.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.9. Water Control.
- Construction Management Plan, document No :
DLM – IMP – PPG – ZCO – J00 – 00001 – E
- Quality Plan, document No :
DLM – IMP – PPG – ZPQ – J00 – 00001 – E
- Delivery Management Plan, document No:
DLM – IMP – PPG – ZPO – J00 – 00001 – E
- Traffic Management Plan, document No:
DLM – IMP – PPG – ZPO – J00 – 00004 – E
- H&S Management Plan, document No:
DLM – IMP – PPG – ZSO – J00 – 00003 – E
- Environment Management Plan, document No:
DLM – IMP – PPG – ZSO – J00 – 00002 – E

- Security Management Plan, document No:
DLM – IMP – PPG – ZSO – J00 – 00001 – E

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 7/36


Hanoi Pilot Light Metro Project

3.

Method statement for shored excavation

CONSTRUCTION PROCEDURE

3.1QUANTITY OF WORK
The estimated quantity is as followings table. Below quantity is only reference. Final quantity shall be
calculated in accordance with approved working drawing. Topographic survey of original ground which
had been approved shall be applied to calculate the quantity for structure excavation.

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 8/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation


Dimension of Excavation

No.

Type of
bridge

Pier

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical


P21
P35
P36
P37
P38
P39
P40
P41
P42
P43
P44
P45
P46
P47
P48
P49
P50
P51
P52
P53
P54
P55
P56
P57
P58
P59
P60
P61
P62

P63
P64
P65
P66
P67
P68
P69
P70
P79
P80
P81

Length
(m)
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

No.

Type of
bridge


Pier

Dimension of Excavation

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

Depth of Excavation
(m)

Excavation Volume
(m3)

1.75
2.49
2.35
2.25
1.99

1.90
1.93
2.11
2.23
2.39
2.40
2.30
2.47
2.54
2.50
2.53
2.29
2.46
2.45
2.19
1.95
2.01
2.04
2.12
2.12
2.11
1.88
1.61
1.48
1.78
1.96
1.99
1.97
2.04
2.07

2.07
2.17
2.32
2.28
2.09

80.69
114.91
108.43
103.81
91.79
87.62
89.01
97.34
102.88
110.28
110.74
106.12
113.98
117.22
115.37
116.76
105.66
113.52
113.06
101.03
89.94
92.71
94.10
97.80

97.80
97.34
86.70
74.22
68.20
82.08
90.40
91.79
90.86
94.10
95.49
95.49
100.11
107.05
105.20
96.46

Depth of Excavation
(m)

Excavation Volume
(m3)
Page 9/36


Hanoi Pilot Light Metro Project

41
42
43

44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73

74
75
76
77
78
79
80

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

P82
P83
P84
P85
P86
P87
P88
P89
P90
P91
P92

P93
P94
P95
P96
P97
P98
P99
P100
P101
P102
P103
P104
P105
P106
P107
P108
P109
P110
P111
P112
P113
P114
P115
P116
P117
P118
P119
P120
P129


No.

Type of
bridge

Pier

Method statement for shored excavation
Length
(m)
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

Width
(m)
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8

Dimension of Excavation
Length
(m)

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)

1.91
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.36
2.16
2.19
1.76

88.09
100.57
100.57
100.57
100.57
100.57

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

108.90
99.65
101.03
81.15

Depth of Excavation
(m)

Excavation Volume
(m3)

Page 10/36


Hanoi Pilot Light Metro Project
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95

96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120

Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical

P130
P131
P132
P133
P134
P135
P136
P137A
P137B
P138
P139
P140
P141
P142
P143
P144
P145
P146
P147
P148
P149
P150
P163

P164
P165
P166
P167
P168
P169
P170
P171
P172
P173
P174
P175
P176
P177
P178
P179
P180

No.

Type of
bridge

Pier

121
122

Typical
Typical


P181
P182

Method statement for shored excavation
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

Dimension of Excavation
Length
(m)

6.8
6.8

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)
6.8
6.8

1.86
2.14
1.76
1.58
1.46
1.75
1.94
2.11
2.34
2.54
2.22
2.22
2.28
2.32
2.05
2.22
2.18
2.14
2.07
2.05

2.10
2.30
2.43
2.54
2.28
2.36
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

85.78
98.72
81.15
72.83
67.28
80.69
89.47
97.34
107.97

117.22
102.42
102.42
105.20
107.05
94.56
102.42
100.57
98.72
95.49
94.56
96.87
106.12
112.13
117.22
105.20
108.90
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

100.57

Depth of Excavation
(m)

Excavation Volume
(m3)

2.18
2.18

100.57
100.57
Page 11/36


Hanoi Pilot Light Metro Project
123
124
125
126
127
128
129
130
131
132
133
134
135

136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
No.

161
162


Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Type of
bridge
Typical
Typical

P183
P184
P185
P186
P187
P188
P189
P190
P191
P192
P193
P194
P195
P196
P197
P198
P199

P200
P201
P202
P203
P212
P213
P214
P220
P221
P222
P223
P224
P225
P226
P227
P228
CPC4
229
CPC4
230
P231
P232
CPC4
233

Method statement for shored excavation
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8


6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8

2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.33
2.23
2.23
2.02
1.90
1.85

1.85
1.87
1.91
2.03
2.02
2.01
2.03

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
107.51
102.88

102.88
93.17
87.62
85.31
85.31
86.24
88.09
93.64
93.17
92.71
93.64

6.8

6.8

2.63

121.38

6.8
6.8
6.8

6.8
6.8
6.8

2.90
2.45

2.26

133.86
113.06
104.27

6.8

6.8

2.71

125.08

Dimension of Excavation
Pier
CPC4
234
P235

Length
(m)

Width
(m)

6.8
6.8

6.8

6.8

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Depth of Excavation
(m)

Excavation Volume
(m3)

2.57
2.28

118.61
105.20

Page 12/36


Hanoi Pilot Light Metro Project

163
164
165
166
167
168
169
170
171

172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195

Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

CPC3

236
CPC1
237
CPC1
238
P239
CPC4
244
CPC3
245
CPC3
246
P247
P256
P257
P258
P259
P260
P261
P262
P263
P264
P265
P266
P267
P268
P269
P270
P271
P272

P273
P274
P275
P276
P277
P278
P279
P280

Method statement for shored excavation

6.8

6.8

2.68

123.69

7.6

7.6

3.68

212.27

7.6
6.8


7.6
6.8

3.68
2.18

212.27
100.57

6.8

6.8

2.68

123.69

6.8

6.8

2.68

123.69

6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

2.68
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

123.69
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

Depth of Excavation
(m)

Excavation Volume
(m3)

2.18
2.18
2.68

100.57
100.57
123.69


Dimension of Excavation

No.

Type of
bridge

Pier

196
197
198

Typical
Typical
Typical

P281
P282
CPC4 283

Length
(m)
6.8
6.8
6.8

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A


Width
(m)
6.8
6.8
6.8

Page 13/36


Hanoi Pilot Light Metro Project
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218

219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

P284
P285
P286
P287

P288
P289
P290
P291
P292
P293
P294
P295
P296
P297
P298
P299
P300
P301
P310
P311
P312
P313
P314
P315
P316
P317
P318
P319
CPC4 320
CPC4 321
CPC4 322
CPC4 323
CPC4 324
CPC4 325

CPC4 326
P327
P328

No.

Type of
bridge

Pier

236
237
238
239
240

Typical
Typical
Typical
Typical
Typical

P329
CPC4 330
CPC4 331
CPC4 332
CPC4 333

Method statement for shored excavation

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

Dimension of Excavation
Length
(m)
6.8
6.8
6.8
6.8
6.8

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)
6.8

6.8
6.8
6.8
6.8

2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

2.18
2.18
2.18
2.68
2.68
2.68
2.68
2.68
2.68
2.68
2.18
2.18

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57
123.69
123.69
123.69
123.69
123.69
123.69
123.69
100.57
100.57

Depth of Excavation
(m)

Excavation Volume
(m3)

2.18
2.68
2.68

2.68
2.68

100.57
123.69
123.69
123.69
123.69
Page 14/36


Hanoi Pilot Light Metro Project
241
242
243
244
245
246
247
248
249
250
251
252
253
254

Typical
Typical
Typical

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

255

Typical

256

Typical

257
258
259
260
261
262
263
264
265
266

267
268
269
270
271
272

Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical
Typical

No.

Type of
bridge

Pier


273
274
275
276
277
278

Special
Special
Special
Special
Special
Special

P1
P2
P3
P4
P1DR5
P6

CPC4 334
P335
P336
P337
P338
P339
CPC4 340
CPC4 341

P342
P359
P360
P361
P362
P363
P1T364-1
P1T364-2
P2T365-1
P2T365-2
P366
P367
P368
P369
P370
P371
P372
P373
P374
P375
P376
P377
P378
P379
P380
P381

Method statement for shored excavation
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
7.6
7.6
7.6
7.6
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
7.6
7.6
7.6
7.6
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8
6.8

6.8
6.8
6.8
6.8
6.8
6.8
6.8

Dimension of Excavation
Length
(m)
6.6
6.6
6.6
6.6
6.6
6.6

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)
6.6
6.6
6.6
6.6
6.6
6.6

2.68

2.18
2.18
2.18
2.18
2.18
2.68
2.68
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18
2.18

2.18
2.18
2.18

123.69
100.57
100.57
100.57
100.57
100.57
123.69
123.69
100.57
100.57
100.57
100.57
100.57
100.57
125.63
125.63
125.63
125.63
100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

100.57
100.57
100.57
100.57
100.57
100.57
100.57
100.57

Depth of Excavation
(m)

Excavation Volume
(m3)

2.18
2.18
2.18
2.18
2.18
2.18

94.74
94.74
94.74
94.74
94.74
94.74

Page 15/36



Hanoi Pilot Light Metro Project
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305

306
307
308

Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special
Special

Special
Special
Special
Special

No.

Type of
bridge

Pier

309
310
311
312
313
314
315
316

Special
Special
Special
Special
Special
Special
Special
Special


3RI242
3RT243
3RT343
3RI344
3RI345
3RT346
COP347
COP348

P7
P8
P9
P10
P11
P1DA12
P2DA13
P3DA14
P15
COTP16
COP17
COP18
COP19
COTP20
COTP30
COP31
COP32
COP33
COTP34
NHT151
NHI152

NHI153
NHT154
COTP215
COP216
COP217
COP218
COTP219
3RT240
3RI241

Method statement for shored excavation
6.6
6.6
6.6
6.6
6.6
6.9
6.9
6.9
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6

6.6
12.9
12.9
6.6
6.6
6.6
6.6
6.6
6.6
6.6
12.9

6.6
6.6
6.6
6.6
6.6
6.5
6.5
6.5
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6

6.6
6.6
9.4
9.4
6.6
6.6
6.6
6.6
6.6
6.6
6.6
9.4

Dimension of Excavation
Length
(m)
12.9
6.6
6.6
12.9
12.9
6.6
6.6
6.6

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Width
(m)
9.4

6.6
6.6
9.4
9.4
6.6
6.6
6.6

2.18
2.18
2.18
2.18
2.18
2.48
2.48
2.48
2.18
2.18
2.10
2.01
1.91
1.90
2.79
2.71
2.35
2.46
2.77
2.23
4.47
4.37

2.42
1.93
1.89
2.00
1.98
2.04
2.18
4.18

94.74
94.74
94.74
94.74
94.74
111.00
111.00
111.00
94.74
94.74
91.26
87.34
82.98
82.55
121.31
117.83
102.15
106.94
120.44
96.92
541.43

529.30
105.20
83.85
82.11
86.90
86.03
88.64
94.74
506.26

Depth of Excavation
(m)

Excavation Volume
(m3)

4.18
2.18
2.18
4.18
4.18
2.18
2.18
2.18

506.26
94.74
94.74
506.26
506.26

94.74
94.74
94.74

Page 16/36


Hanoi Pilot Light Metro Project
317
318

Special
Special

COP349
COTP350

Method statement for shored excavation
6.6
6.6

6.6
6.6

2.18
2.18

94.74
94.74


3.2REFERENCE TO BORE HOLE
Based on alignment geological borehole, we have reference table of geological boreholes in accordance
with pier position. Reference table is established for piers of Typical Bridge and Special Bridge.
With dimension, depth and geology of borehole at position of piers, Contractor calculated and proposed
all piers in alignment have to use sheet piles cofferdam during excavation process.
Also, at position of pier caps with dimension (10.9x7.4x3.5m và 5.6x4.8x3.0m), Contractor use bracing
system inside steel piles cofferdam.
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap on
Typical Bridge is shown in the attached drawing in section 10.1.1.
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap on
Special Bridge is shown in drawing DLM-IMP-GPV-WVO-JOO-10003-B and DLM-IMP-GNS-WVOJOO-10018-B (attached in section 10.1.2).
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam without
wales & struts inside, will be submitted separately.
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam and wales &
struts inside, will be submitted separately.

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 17/36


Hanoi Pilot Light Metro Project

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Method statement for shored excavation

Page 18/36



Hanoi Pilot Light Metro Project

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Method statement for shored excavation

Page 19/36


Hanoi Pilot Light Metro Project

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Method statement for shored excavation

Page 20/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

3.3SCHEDULE OF WORK
The schedule for Shored Excavation will be submitted later after get approved of the Master schedule and
base on actually of work, the said schedule shall be submitted on weekly and monthly schedule.
Please refer to item 10.3 for typical schedule for 01 pile cap of 01 construction area.

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 21/36



Hanoi Pilot Light Metro Project

4.

Method statement for shored excavation

PERSONNEL ORGANIZATION

4.1PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 22/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

4.2PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE

GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁN
Mr.Lê Lệnh Bắc
Phone: 0913253582

Construction Manager/
Chỉ Huy Trưởng
Mr. Lê Thảo Tâm

Phone: 0987.520.820

Designer/
Thiết kế
Mr. Lê Minh Trà
Phone: 0912-337-176
Mr. Bùi Trần Hà
Phone: 0983-718-345

Design Team/
Tổ Thiết kế

Construction Team/
Bộ phận thi công
Mr. Trần Hữu Thắng
Phone: 0983-899-315

QA, QC/
Quản lý chất lượng
Mr. Ngô Thế Quỳnh
Phone: 0916-042-060

QA, QC Team/
Tổ quản lý chất lượng
Mr. Cấn Mạnh Hùng
Mr. Lê Văn Long
Phone: 0947-211-268

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A


Sheet pile Team/
Tổ cọc ván thép

Excavation
Team/
Tổ thi công đào

Planning,QS Team/
Bộ phận Kế hoạch, khối lượng
Mr. Lê Thăng Quân
Phone: 01683-636-867

Drainage Team/
Tổ thi công thoát
nước tạm

Mechanical Team/
Bộ phận máy thi công
Mr. Cao Tiến Sơn
Phone: 0985-320-691

Clinic Team/
Tổ Y tế

Surveyor Team/
Đội Trắc đạc
Mr. Khuất Hữu Thuận
Phone: 0972-796-481

S.H.E/

Bộ phận An tòan, Sức khỏe, Môi
trường
Mr. Nguyễn Quang Hiếu
Phone: 0919-780-066
Mr. Nguyễn Thanh Thản
Phone: 0913-560-427

Safety Team/
Tổ An toàn
Mr. Phạm Ngọc Tiến
Phone: 01686-539-171

Traffic Assurance
Team/
Tổ Đảm bảo giao thông

Page 23/36


Hanoi Pilot Light Metro Project

Method statement for shored excavation

4.3PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE
GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁN
Mr.Nguyễn Tuấn Anh
Phone: 0989059379
Email:

PHÓ GIÁM ĐỐC BAN ĐIỀU HÀNH

Phụ trách quản lý thi công, ATLĐ, đảm bảo giao
thông
Mr: Trần Ngọc Quý
Phone: 0979267723
Email:

PHÓ GIÁM ĐỐC BAN ĐIỀU HÀNH
Phụ trách kế hoạch, thanh toán, kỹ thuật
Mr: Đào Đức Huynh
Phone: 0913060752

THIẾT KẾ
Mr. Nguyễn Thắng An
Phone:0989643926

Mr. Lê Văn Tuấn
Phone:0972405191

QUẢN LÝ CHẤT LƯỢNG
Mr. Phạm Xuân Nghĩa
Phone: 0912774678

Mr. Đàm Quang Chiến
Phone:0984322270

BỘ PHẬN THI CÔNG
Mr. Nguyễn Trung Kiên
Phone: 0979898568

Mr. Nguyễn Văn Đô

Phone:0918488598

BỘ PHẬN KẾ HOẠCH,
KHỐI LƯỢNG
Mr. Bùi Quang Vinh
Phone: 0949393492

Mr. Trần Văn Cường
Phone:0972405191

BỘ PHẬN MÁY THI
CÔNG
Mr. Đỗ Đường Tú
Phone: 0974112422

ĐỘI TRẮC ĐẠC
Mr. Trương Quốc Ninh
Phone: 0904545744

Mr. Nguyễn Văn Hùng
Phone:0936672916

NHÓM AN TOÀN SỨC KHỎE ,
MÔI TRƯỜNG
Mr. Trương Công Thịnh
Phone: 0979032579

Mr. Nguyễn An Quang
Phone:01689615196


Mr. Nguyễn Sỹ Thường
Phone:016689912487

Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 24/36


Hanoi Pilot Light Metro Project

5.

Method statement for shored excavation

MATERIALS, EQUIPMENT AND MANPOWER

The list of equipment and worker for one team of shored excavation is shown as followings. Detail of
equipment and workers should be submitted separately in order to be checked and approved by the
Engineer before commencement of bored piling work.
5.1MATERIALS
List of Materials for one team of shored excavation

No.

Items

Qty.

Description


1.

Sheet pile

01 Set

Larsen IV, L=6~8m

2.

Frame strut and wale

01 Set

H400x400 & H250x250

Remark
Driving of sheet pile work
(profile of sheet pile, wales
and struts will be submitted
before constructing)

5.2EQUIPMENT
List of equipment are shown as below (for one team of shored excavation)
That equipment will be submitted to the Engineer for approval before construction.
List of Equipment for one team of shored excavation
No.

Items


Qty.

Description

1.

Excavator

01 Pc

0.6~1.2m3 bucket

2.

01 Pc

40 ton

01 Set

KGK-130 or equivalent

4.

Crane
Static sheet
machine
Dump truck

01 Pc


10~25m3

5.

Diesel Generator

01 Pc

100~250 KVA

6.

Pump

01 Pc

20~50 m3/hours

7.

Total station/ leveling machine

01 Set

8.

Lighting systems

01 Set


9.

Welding machine

01 Set

10.

Bar cut machine

01 Set

11.

Ladder

01 Set

3.

pile

compression

Remark

Above stated schedule of equipment shall be increased in quantity if required and necessary. Above
equipment could be replaced by equivalent equipment depend on condition of the Contractor or site
condition.


Doc N° DLM-IMP-PPG-WVO-J07-00001-E-1A

Page 25/36


×